This project is based on the relocation of Jeff and his family that includes his wife, children and dogs. Due to change in job for Jeff, the entire family has to relocate from Sunshine Coast to Perth. In the previous report, the entire plan was developed that included packing and leaving of the existing rental apartment, reaching Perth and then relocating to the new rental apartment. Due to the time difference between leaving Sunshine Coast and entering new apartment in Perth, it was decided that the family will stay in Perth hotel after reaching there before the commencement of the new rental. However, a new situation has arrived in which, Kelly has been sick and needs to be rested for 2 weeks. Furthermore, hotels at Perth will not be available for some time due to some event celebrations. Hence, suitable changes are required in the relocation plan for Jeff & Kelly and their family.
As a result of the new situations as mentioned in the case study, some changes are to be made in the project schedule. The main changes are highlighted in yellow in the following table.
WBS |
Task Name |
Duration |
Start |
Finish |
0 |
Revised Relocation Schedule for Jeff and Kelly |
30 days |
Wed 1/2/19 |
Thu 1/31/19 |
1 |
Initiation |
5 days |
Wed 1/2/19 |
Sun 1/6/19 |
1.1 |
Planning for Relocation |
1 day |
Wed 1/2/19 |
Wed 1/2/19 |
1.2 |
Fixing Date for Move |
1 day |
Thu 1/3/19 |
Thu 1/3/19 |
1.3 |
Contact Relocation Planner for Moving Furniture and Luggage |
1 day |
Fri 1/4/19 |
Fri 1/4/19 |
1.4 |
Confirm Date for Moving |
2 days |
Sat 1/5/19 |
Sun 1/6/19 |
M1 |
Milestone 1: Initial Plan Complete |
0 days |
Sun 1/6/19 |
Sun 1/6/19 |
2 |
Planning |
4 days |
Mon 1/7/19 |
Thu 1/10/19 |
2.1 |
Plan for Relocation Activities |
1 day |
Mon 1/7/19 |
Mon 1/7/19 |
2.2 |
Prepare Relocation Schedule |
1 day |
Tue 1/8/19 |
Tue 1/8/19 |
2.3 |
Contingency Planning |
1 day |
Wed 1/9/19 |
Wed 1/9/19 |
2.4 |
Allocation of Resources to Various Activities |
1 day |
Thu 1/10/19 |
Thu 1/10/19 |
M2 |
Milestone 2: Relocation Planning Complete |
0 days |
Thu 1/10/19 |
Thu 1/10/19 |
3 |
Pre-relocation activities |
18 days |
Fri 1/11/19 |
Mon 1/28/19 |
3.1 |
Hire Packers and Movers Team |
1 day |
Fri 1/11/19 |
Fri 1/11/19 |
3.2 |
Pack Furniture and Luggage |
1 day |
Sat 1/12/19 |
Sun 1/13/19 |
3.3 |
Dispose Unwanted Items |
1.5 days |
Sat 1/12/19 |
Sun 1/13/19 |
3.4 |
Sign Contract End Paper with Landlord |
2 days |
Sun 1/13/19 |
Tue 1/15/19 |
3.5 |
Filing Paperwork |
1 day |
Tue 1/15/19 |
Wed 1/16/19 |
3.6 |
Admission of Kelly in Hospital |
0 days |
Tue 1/15/19 |
Tue 1/15/19 |
3.7 |
Complete Bed Rest for Kelly |
14 days |
Tue 1/15/19 |
Mon 1/28/19 |
3.8 |
Submit Online Application in Perth School for the Children |
2 days |
Wed 1/16/19 |
Fri 1/18/19 |
3.9 |
Cleaning Up the Old Apartment |
1 day |
Fri 1/18/19 |
Sat 1/19/19 |
M3 |
Milestone 3: Vacating the Apartment |
0 days |
Sat 1/19/19 |
Sat 1/19/19 |
4 |
Relocation |
12.5 days |
Sat 1/19/19 |
Thu 1/31/19 |
4.1 |
Moving to Local Hotel |
9 days |
Sat 1/19/19 |
Mon 1/28/19 |
4.2 |
Travel to Perth |
0 days |
Mon 1/28/19 |
Mon 1/28/19 |
4.3 |
Receiving Furniture and Luggage from Transport Company |
0.5 days |
Tue 1/29/19 |
Tue 1/29/19 |
4.4 |
Signing Paperwork |
0.5 days |
Tue 1/29/19 |
Tue 1/29/19 |
4.5 |
Unpacking and Decorations |
2 days |
Wed 1/30/19 |
Thu 1/31/19 |
M4 |
Milestone 4: Relocation Complete |
0 days |
Tue 1/29/19 |
Tue 1/29/19 |
In this table, there are some activities that are highlighted in yellow. These activities have been added considering the new conditions presented in the scenario compared to the previous scenario. As per the previous plan, the family was to check out from the existing apartment, travel to Perth and stay in a hotel in Perth until their new rental starts. However, Kelly has fallen sick and requires 2 weeks of bed rest. Accordingly, the schedule has been changed such that Kelly can have the rest in hospital and meanwhile, the rest of the family will stay in a hotel in Sunshine Coast. After Kelly is released, they will travel to Perth and by that time, their new rental will start and the delayed delivery of the luggage will be completed.
The addition of new activities in the project has resulted in some addition of budget to the total budget prepared by Jeff. The new resource costs and the revised budget are shown in the following table.
Resource Name |
Type |
Max. Units |
Std. Rate |
Jeff |
Work |
100% |
$0.00/hr |
Relocation Planner |
Work |
200% |
$100.00/hr |
Packers and Movers |
Work |
200% |
$100.00/hr |
Packaging Costs |
Material |
$1,000.00 |
|
Transport Team |
Work |
100% |
$75.00/hr |
Transportation Cost |
Material |
$500.00 |
|
Hospital Costs |
Material |
$2,000.00 |
|
Hotel Costs |
Material |
$700 |
WBS |
Task Name |
Duration |
Resource Names |
Cost |
0 |
Revised Relocation Schedule for Jeff and Kelly |
30 days |
$14,800.00 |
|
1 |
Initiation |
5 days |
$0.00 |
|
1.1 |
Planning for Relocation |
1 day |
Jeff |
$0.00 |
1.2 |
Fixing Date for Move |
1 day |
Jeff |
$0.00 |
1.3 |
Contact Relocation Planner for Moving Furniture and Luggage |
1 day |
Jeff |
$0.00 |
1.4 |
Confirm Date for Moving |
2 days |
Jeff |
$0.00 |
M1 |
Milestone 1: Initial Plan Complete |
0 days |
$0.00 |
|
2 |
Planning |
4 days |
$3,200.00 |
|
2.1 |
Plan for Relocation Activities |
1 day |
Relocation Planner |
$800.00 |
2.2 |
Prepare Relocation Schedule |
1 day |
Relocation Planner |
$800.00 |
2.3 |
Contingency Planning |
1 day |
Relocation Planner |
$800.00 |
2.4 |
Allocation of Resources to Various Activities |
1 day |
Relocation Planner |
$800.00 |
M2 |
Milestone 2: Relocation Planning Complete |
0 days |
$0.00 |
|
3 |
Pre-relocation activities |
18 days |
$8,500.00 |
|
3.1 |
Hire Packers and Movers Team |
1 day |
Jeff |
$0.00 |
3.2 |
Pack Furniture and Luggage |
1 day |
Packers and Movers[200%], Packaging Costs[1] |
$2,600.00 |
3.3 |
Dispose Unwanted Items |
1.5 days |
Relocation Planner[200%] |
$2,400.00 |
3.4 |
Sign Contract End Paper with Landlord |
2 days |
Jeff |
$0.00 |
3.5 |
Filing Paperwork |
1 day |
Jeff |
$0.00 |
3.6 |
Admission of Kelly in Hospital |
0 days |
$0.00 |
|
3.7 |
Complete Bed Rest for Kelly |
14 days |
Hospital Costs[1] |
$3,500.00 |
3.8 |
Submit Online Application in Perth School for the Children |
2 days |
Jeff |
$0.00 |
3.9 |
Cleaning Up the Old Apartment |
1 day |
$0.00 |
|
M3 |
Milestone 3: Vacating the Apartment |
0 days |
$0.00 |
|
4 |
Relocation |
12.5 days |
$2,400.00 |
|
4.1 |
Moving to Local Hotel |
9 days |
Jeff, Hotel Costs |
$700.00 |
4.2 |
Travel to Perth |
0 days |
Jeff |
$0.00 |
4.3 |
Receiving Furniture and Luggage from Transport Company |
0.5 days |
Transport Team, Transportation Cost[1] |
$800.00 |
4.4 |
Signing Paperwork |
0.5 days |
Jeff |
$0.00 |
4.5 |
Unpacking and Decorations |
2 days |
Packers and Movers |
$1,600.00 |
M4 |
Milestone 4: Relocation Complete |
0 days |
$0.00 |
The adjustments are made to the schedule in two separate phases that are shown in the following tables.
WBS |
Task Name |
Duration |
Start |
Finish |
Resource Names |
Cost |
3.6 |
Admission of Kelly in Hospital |
0 days |
Tue 1/15/19 |
Tue 1/15/19 |
$0.00 |
|
3.7 |
Complete Bed Rest for Kelly |
14 days |
Tue 1/15/19 |
Mon 1/28/19 |
Hospital Costs[1] |
$3,500.00 |
This phase reflects admission of Kelly in hospital that was not preplanned. In this change, there are two activities – admission in hospital and bed rest for Kelly. Kelly will be in rest for 14 days and this activity will incur additional cost of $3500.
WBS |
Task Name |
Duration |
Start |
Finish |
Resource Names |
Cost |
4.1 |
Moving to Local Hotel |
9 days |
Sat 1/19/19 |
Mon 1/28/19 |
Hotel Costs[1],Jeff |
$700.00 |
4.2 |
Travel to Perth |
0 days |
Mon 1/28/19 |
Mon 1/28/19 |
Jeff |
$0.00 |
In this phase, the changes include moving of rest of the family to a local hotel and then travel to Perth after Kelly is released from the hospital. This change incurs an additional $700 for hotel cost.
Based on the changes, the total budget of Jeff increases to $14,800, which is more than the initial expenditure planned by Jeff. However, the budget still remains within the $15,000 limit set by Jeff and hence, the project is still feasible for Jeff and his family.
This module has given me valuable lesson in the field of project management and has allowed me to test my complex problem solving skills. I have learnt the application of various project management software and techniques to develop appropriate project plan based on the challenges presented by a scenario like above. I have also learnt to incorporate various changes within the scenario in order to bypass challenges presented in the scenario. In addition to the lessons specific to this learning course, I have also developed certain skills as follows.
Abbasian-Hosseini, S. A., Howell, G., & Liu, M. (2016). Relationship between on-site planning efforts and work plan reliability. In Construction Research Congress 2016 (pp. 2129-2138).
Binder, J. (2016). Global project management: communication, collaboration and management across borders. Routledge.
Fleming, Q. W., & Koppelman, J. M. (2016, December). Earned value project management. Project Management Institute.
Fuller, M. A., Valacich, J. S., George, J. F., & Schneider, C. (2017). Information Systems Project Management: A Process and Team Approach, Edition 1.1. Prospect Press.
Heldman, K. (2018). PMP: project management professional exam study guide. John Wiley & Sons.
Kerzner, H., & Kerzner, H. R. (2017). Project management: a systems approach to planning, scheduling, and controlling. John Wiley & Sons.
Lock, D. (2017). The essentials of project management. Routledge.
Ray, P. A., & Brown, C. M. (2015). Confronting climate uncertainty in water resources planning and project design: the decision tree framework. The World Bank.
Samset, K., & Volden, G. H. (2016). Front-end definition of projects: Ten paradoxes and some reflections regarding project management and project governance. International Journal of Project Management, 34(2), 297-313.
Young, T. L. (2016). Successful project management. Kogan Page Publishers.
Essay Writing Service Features
Our Experience
No matter how complex your assignment is, we can find the right professional for your specific task. Contact Essay is an essay writing company that hires only the smartest minds to help you with your projects. Our expertise allows us to provide students with high-quality academic writing, editing & proofreading services.Free Features
Free revision policy
$10Free bibliography & reference
$8Free title page
$8Free formatting
$8How Our Essay Writing Service Works
First, you will need to complete an order form. It's not difficult but, in case there is anything you find not to be clear, you may always call us so that we can guide you through it. On the order form, you will need to include some basic information concerning your order: subject, topic, number of pages, etc. We also encourage our clients to upload any relevant information or sources that will help.
Complete the order formOnce we have all the information and instructions that we need, we select the most suitable writer for your assignment. While everything seems to be clear, the writer, who has complete knowledge of the subject, may need clarification from you. It is at that point that you would receive a call or email from us.
Writer’s assignmentAs soon as the writer has finished, it will be delivered both to the website and to your email address so that you will not miss it. If your deadline is close at hand, we will place a call to you to make sure that you receive the paper on time.
Completing the order and download