The project management is the analysis of the works dependent on the alignment of the specific and smart alignment of the operations. The WBS stands for work breakdown structure and it involves the development of the work and aligning the significant listing of functions. The work breakdown structure would allow the division of the complete project into specific smaller operations for ensuring that the implication of the works would be implied with the implication and development. The WBS would be developed for ensuring the division of the smaller work packages and it would allow the easy division of the works. The complete project would be subdivided into smaller sub projects for ensuring the work division is aligned cohesively. The division of the work would be helpful for ensuring the alignment of the specific work allocation and development.
(a) Project Schedule
(b) Schedule Baseline
(c) Schedule Management Plan
(d) Schedule Network Diagram
Answer: Schedule Baseline is helpful for keeping track of schedule progress by keeping accounts of activities completed, activities in program, actual start and finish dates, percentage complete, hours spent, resource allocations, etc.
The project baseline can be defined as the implication for storing the scheduled values estimated at the project planning method to act as a reference point.
The project baseline includes the values of schedule, cost, and resource usage that had been estimated at the initial planning phase. It helps in keeping track of the project progress enabling whether the project would be completed successfully.
The milestone tracking is helpful for enabling the use of tracking methods like checklist, documentation, and log books for analyzing the progress of the project. The milestone identification would be done considering the practical perspective of the work. The achievement of the specific points would be dependent on the alignment of the works and formation of the smart work development and alignment of the successive work development. The use of the milestone tracking would be helpful for defining the project milestones, overseeing the project progress, and identifying the project status. The completion of the project activities would be implied with the listing of the activities and forming the utilization and information listing for the operations.
The project progress would be completed with the formation and listing the application management. The percent complete approach would be effectively measures with the formation of the works and allocation of the smart management works. The complete approach would be implied with the functional listing of the works. The project progress would be effectively implied with the continuation of the works and development of the implied management works. The measurement of the project progress would be implied with the continuation management. The completion of the project would be effectively managed with the utilization management formation. The measurement of the project progress would be implied for the successful listing of the alignment management.
The cost variance is the value difference between the cost’s actual management and the budgeted amount of utilization. The cost variance calculation would be aligned with implication management and utilization of the factors. The completion of the smart and effective management would be implied with the listing of the cost variance calculation. The cost variance calculation would be required for aligning the management of the information and taking care of the conceptive management of the works. The calculation of the cost variance is done by subtracting actual cost from earned value.
Hence, for over budgeted projects, CV would be negative whereas under budgeted project would have positive value. The value ‘0’ of CV would be helpful for ensuring that the project final budget and estimated budget is same.
The execution phase is characterized by the use of the proper documents like project charter, schedule, resource usage, cost budget, risk management plan, and design for achieving the final output of the project. The development of the works would be effectively implied with the continuation of the effective work experience. The execution phase involves the simplification of the improved work experience for forming the utilization management. The formation of the works would be supported by the utilization of the works and formation of the smart work development. The project execution would be aligned with the formation of the implication management. The project execution would be effectively implied for taking care of the factors for managing the development model. The execution phase would be responsible for executing the works and forming the successful implication of the works.
(a) Start Work immediately
(b) Ascertain the impact of this change to scope, schedule, and cost before making any change
(c) Perform Quality Assurance
(d) Make sure that the scope baseline and schedule baseline are update to reflect the approved change before implementing the change
Answer: (d) Make sure that the scope baseline and schedule baseline are update to reflect the approved change before implementing the change
(a) Schedule Compression
(b) Schedule Model
(c) Schedule Data
(d) None of the above
Answer: (b) Schedule Model
(a) Alternative Analysis
(b) Bottom-up Estimating
(c) Parametric Estimating
(d) Three-point Estimating
Answer: (b) Bottom-up Estimating
(a) Use the triangle of constraints to understand and explain to the client that if the deadline is brought forward the scope and/or cost will increase
(b) Analyze the risk and add it to the Risk Breakdown Structure
(c) Use the Delphi Method to determine if this request can be accommodated
(d) Provide the client with the new schedule and communicate the risk of bringing forward the deadline
Answer: (d) Provide the client with the new schedule and communicate the risk of bringing forward the deadline
(a) Milestone
(b) Work packages can’t be decomposed into smaller units
(c) Activities
(d) Control Accounts
Answer: (c) Activities
(a) Make no changes to the schedule
(b) Make changes to the activity duration and schedule incorporating the changed competency levels
(c) Inform the customer that the project is behind schedule
(d) Ask the project team members to meet the original schedule by putting in overtime if required
Answer: (b) Make changes to the activity duration and schedule incorporating the changed competency levels
(a) Organizational Process Assets
(b) Enterprise Environmental Factors
(c) Requirements documentation
(d) Activity List
Answer: (d) Activity List
The work breakdown structure would allow the division of the complete project into specific smaller operations for ensuring that the implication of the works would be implied with the implication and development. The WBS would be developed for ensuring the division of the smaller work packages and it would allow the easy division of the works. The following diagram would show the work breakdown structure for the project,
Project Schedule
The project schedule has been developed using the implication of the project adaptive modulation development management. The scheduling of the adaptive framework would be effectively implied with the successful completion of the works. The scheduling of the works would be effectively developed compiling the management of the works would be effectively managed with the successful alignment of the works and formation of the successful work development. The project schedule has been divided into the following phases,
Initiation Phase: The first phase of the project development and it would be effectively implied with the formation of the smart development of works. The initiation phase involves the accumulation of the information and the alignment of the works cohesively. The utilization of the activities like requirement analysis, charter documentation, submission of documents, and sign off are considered in this phase.
Planning: The planning is the second phase of the project operations including the development of the activities that are required for execution for project. The planning phase would involve the identification of the works that are required in the latter phases. The planning phase involves the activities of activity scheduling, listing of tasks, completion of plan, and plan approval.
Designing: The designing is the third phase of the project operations that is being made for making the new design of the website. The website development would be effectively developed for entrapping the new features and programs in a new design. The design development would be effectively implied with the involvement of the functions and activities like website design platform selection, UI graphics are made, font is selected, content is listed, complete designing, and design approval.
Execution: It is the most crucial phase of the project activities as the main generation of the output is being done in this phase only. The execution of project activities that had been developed with the consideration of the smart project completion management would be implied with the consideration of the smart management processing. The activities included in this phase involves the UI is made, functions are made, website database is made, website domain is bought, privacy policy is made, security functions are made, integration of work functions, complete website is made, and website approved.
Testing and Monitoring: This phase is characterized by the analysis of the work requirements and the output of the project works. The testing and monitoring of the project outcomes would be effectively implied with the formation of the activities like Simulation, Alpha testing, Beta testing, and Testing Completed. The completion of this phase would involve the completion of the works and forming the alignment of the works dependent on the alignment of the work development.
Closing: The final phase of the project that would involve the activities of website domain is fixed, go live of website, final documentation, submission of documents, sign off, and closure. The completion of the phase would be helpful for documenting the project activities so that it can be used for future references. The project report would serve as the final project completion work.
WBS |
Task Name |
Duration |
Start |
Finish |
0 |
Redevelopment of Website for National Archives of Australia |
30 days |
Mon 12/3/18 |
Fri 1/11/19 |
1 |
Initiation Phase |
7 days |
Mon 12/3/18 |
Tue 12/11/18 |
1.1 |
Requirement Analysis |
2 days |
Mon 12/3/18 |
Tue 12/4/18 |
1.2 |
Charter Documentation |
4 days |
Wed 12/5/18 |
Mon 12/10/18 |
1.3 |
Submission of documents |
1 day |
Tue 12/11/18 |
Tue 12/11/18 |
M1 |
Sign off |
0 days |
Tue 12/11/18 |
Tue 12/11/18 |
2 |
Planning |
7 days |
Wed 12/5/18 |
Thu 12/13/18 |
2.1 |
Activity Scheduling |
3 days |
Wed 12/5/18 |
Fri 12/7/18 |
2.2 |
Listing of tasks |
4 days |
Mon 12/10/18 |
Thu 12/13/18 |
2.3 |
Completion of Plan |
7 days |
Wed 12/5/18 |
Thu 12/13/18 |
M2 |
Plan Approval |
0 days |
Thu 12/13/18 |
Thu 12/13/18 |
3 |
Designing |
6 days |
Fri 12/14/18 |
Fri 12/21/18 |
3.1 |
Website Design Platform Selection |
2 days |
Fri 12/14/18 |
Mon 12/17/18 |
3.2 |
UI Graphics are made |
3 days |
Wed 12/19/18 |
Fri 12/21/18 |
3.3 |
Font is selected |
1 day |
Tue 12/18/18 |
Tue 12/18/18 |
3.4 |
Content is listed |
3 days |
Wed 12/19/18 |
Fri 12/21/18 |
3.5 |
Complete Designing |
6 days |
Fri 12/14/18 |
Fri 12/21/18 |
M3 |
Design Approval |
0 days |
Fri 12/21/18 |
Fri 12/21/18 |
4 |
Execution |
15 days |
Tue 12/18/18 |
Mon 1/7/19 |
4.1 |
UI is made |
5 days |
Mon 12/24/18 |
Fri 12/28/18 |
4.2 |
Functions are made |
4 days |
Tue 12/18/18 |
Fri 12/21/18 |
4.3 |
Website Database is made |
3 days |
Mon 12/24/18 |
Wed 12/26/18 |
4.4 |
Website Domain is bought |
1 day |
Thu 12/27/18 |
Thu 12/27/18 |
4.5 |
Privacy Policy is made |
3 days |
Mon 12/24/18 |
Wed 12/26/18 |
4.6 |
Security functions are made |
4 days |
Thu 12/27/18 |
Tue 1/1/19 |
4.7 |
Integration of work functions |
3 days |
Wed 1/2/19 |
Fri 1/4/19 |
4.8 |
Complete Website is made |
8 days |
Thu 12/27/18 |
Mon 1/7/19 |
M4 |
Website Approved |
0 days |
Mon 1/7/19 |
Mon 1/7/19 |
5 |
Testing and Monitoring |
9 days |
Mon 12/24/18 |
Thu 1/3/19 |
5.1 |
Simulation |
3 days |
Mon 12/24/18 |
Wed 12/26/18 |
5.2 |
Alpha testing |
2 days |
Thu 12/27/18 |
Fri 12/28/18 |
5.3 |
Beta testing |
2 days |
Wed 1/2/19 |
Thu 1/3/19 |
M5 |
Testing Completed |
0 days |
Thu 1/3/19 |
Thu 1/3/19 |
6 |
Closing |
11 days |
Fri 12/28/18 |
Fri 1/11/19 |
6.1 |
Website Domain is fixed |
2 days |
Fri 12/28/18 |
Mon 12/31/18 |
6.2 |
Go Live of Website |
2 days |
Tue 1/1/19 |
Wed 1/2/19 |
6.3 |
Final Documentation |
4 days |
Fri 1/4/19 |
Wed 1/9/19 |
6.4 |
Submission of documents |
1 day |
Thu 1/10/19 |
Thu 1/10/19 |
6.5 |
Sign off |
1 day |
Fri 1/11/19 |
Fri 1/11/19 |
M6 |
Closure |
0 days |
Fri 1/11/19 |
Fri 1/11/19 |
The project has been developed using the alignment of the effective and smart work development model. The critical path of project comprise of those tasks that cannot be executed with each other and sum of their individual durations would provide the final project duration. The critical path is identified as the activities aligning with the progress of the project and developing the final outcome of the project. The identified critical path for the project is given in the following table and diagram,
WBS |
Task Name |
Duration |
1.1 |
Requirement Analysis |
2 days |
2.1 |
Activity Scheduling |
3 days |
2.2 |
Listing of tasks |
4 days |
2.3 |
Completion of Plan |
7 days |
M2 |
Plan Approval |
0 days |
3.1 |
Website Design Platform Selection |
2 days |
4.2 |
Functions are made |
4 days |
4.5 |
Privacy Policy is made |
3 days |
4.6 |
Security functions are made |
4 days |
5.3 |
Beta testing |
2 days |
M5 |
Testing Completed |
0 days |
6.3 |
Final Documentation |
4 days |
6.4 |
Submission of documents |
1 day |
6.5 |
Sign off |
1 day |
M6 |
Closure |
0 days |
Critical Path Description: The critical path of the project include the activities of Requirement Analysis, Activity Scheduling, Listing of tasks, Completion of Plan, Website Design Platform Selection, Functions are made, Privacy Policy is made, Security functions are made, Beta testing, Final Documentation, Submission of documents, and Sign off. The completion of these activities and the duration would be implied with the formation of the work that has been successfully. The integration would be effectively developed for integrating the alignment management. The summarization of the activities and the key listing would be implied with the development.
The communication of the schedule baseline would be effectively developed considering the utilization of the factors. Schedule Baseline is helpful for keeping track of schedule progress by keeping accounts of activities completed, activities in program, actual start and finish dates, percentage complete, hours spent, and resource allocations. The project baseline includes the values of schedule, cost, and resource usage that had been estimated at the initial planning phase. It helps in keeping track of the project progress enabling whether the project would be completed successfully. The schedule baseline date of 31st December 2018 has been selected for calculation of the baseline schedule. The following Gantt chart has been set for the baseline schedule for the date of 31st December,
The time rescheduling would be done by implying the use of the effective work development and integrating the listing of the effective work management. The time rescheduling would be effectively managed by the alignment of the implicit work development. The rescheduling of the work would be effectively managed with the help of resource inclusion, hiring contractor, and delaying the schedule. The project is largely impacted by the scope trio constraint and the rescheduling would be largely impacted by the formation of the effective alignment of works.
Out of the three options of rescheduling, hiring contractor would be selected as it would help in transferring the risk of delay to an external person that would be solely responsible for the completion of the work. The completion of the works would be highly impacted by the formation of the smart work development. The completion of the works would be eased by inclusion of the external people in the project.
in relation to the schedule?
The following two methods must be followed for implementing any agreed schedule changes
The project time performance can be understood by the following tables and graphs,
WBS |
Task Name |
Duration |
Start |
Finish |
Predecessors |
1.1 |
Requirement Analysis |
2 days |
Mon 12/3/18 |
Tue 12/4/18 |
|
1.2 |
Charter Documentation |
4 days |
Wed 12/5/18 |
Mon 12/10/18 |
2 |
1.3 |
Submission of documents |
1 day |
Tue 12/11/18 |
Tue 12/11/18 |
3 |
M1 |
Sign off |
0 days |
Tue 12/11/18 |
Tue 12/11/18 |
4 |
2.1 |
Activity Scheduling |
3 days |
Wed 12/5/18 |
Fri 12/7/18 |
2 |
2.2 |
Listing of tasks |
4 days |
Mon 12/10/18 |
Thu 12/13/18 |
7 |
2.3 |
Completion of Plan |
7 days |
Wed 12/5/18 |
Thu 12/13/18 |
2 |
M2 |
Plan Approval |
0 days |
Thu 12/13/18 |
Thu 12/13/18 |
8,9 |
3.1 |
Website Design Platform Selection |
2 days |
Fri 12/14/18 |
Mon 12/17/18 |
10 |
3.2 |
UI Graphics are made |
3 days |
Wed 12/19/18 |
Fri 12/21/18 |
12 |
3.3 |
Font is selected |
1 day |
Tue 12/18/18 |
Tue 12/18/18 |
12 |
3.4 |
Content is listed |
3 days |
Wed 12/19/18 |
Fri 12/21/18 |
14 |
3.5 |
Complete Designing |
6 days |
Fri 12/14/18 |
Fri 12/21/18 |
10 |
M3 |
Design Approval |
0 days |
Fri 12/21/18 |
Fri 12/21/18 |
16 |
4.1 |
UI is made |
5 days |
Mon 12/24/18 |
Fri 12/28/18 |
13 |
4.2 |
Functions are made |
4 days |
Tue 12/18/18 |
Fri 12/21/18 |
12 |
4.3 |
Website Database is made |
3 days |
Mon 12/24/18 |
Wed 12/26/18 |
15 |
4.4 |
Website Domain is bought |
1 day |
Thu 12/27/18 |
Thu 12/27/18 |
21 |
4.5 |
Privacy Policy is made |
3 days |
Mon 12/24/18 |
Wed 12/26/18 |
20 |
4.6 |
Security functions are made |
4 days |
Thu 12/27/18 |
Tue 1/1/19 |
23 |
4.7 |
Integration of work functions |
3 days |
Wed 1/2/19 |
Fri 1/4/19 |
19,22,24 |
4.8 |
Complete Website is made |
8 days |
Thu 12/27/18 |
Mon 1/7/19 |
21 |
M4 |
Website Approved |
0 days |
Mon 1/7/19 |
Mon 1/7/19 |
25,26 |
5.1 |
Simulation |
3 days |
Mon 12/24/18 |
Wed 12/26/18 |
16 |
5.2 |
Alpha testing |
2 days |
Thu 12/27/18 |
Fri 12/28/18 |
20 |
5.3 |
Beta testing |
2 days |
Wed 1/2/19 |
Thu 1/3/19 |
24 |
M5 |
Testing Completed |
0 days |
Thu 1/3/19 |
Thu 1/3/19 |
29,30,31 |
6.1 |
Website Domain is fixed |
2 days |
Fri 12/28/18 |
Mon 12/31/18 |
22 |
6.2 |
Go Live of Website |
2 days |
Tue 1/1/19 |
Wed 1/2/19 |
34 |
6.3 |
Final Documentation |
4 days |
Fri 1/4/19 |
Wed 1/9/19 |
32 |
6.4 |
Submission of documents |
1 day |
Thu 1/10/19 |
Thu 1/10/19 |
36 |
6.5 |
Sign off |
1 day |
Fri 1/11/19 |
Fri 1/11/19 |
37 |
M6 |
Closure |
0 days |
Fri 1/11/19 |
Fri 1/11/19 |
35,38 |
Now according to the given project file (or calendar list) it is possible for keeping track of the works. The completion of the project would be listed with the help of tracking Gantt chart as it would help in making sure that the project is working in time.
Date |
Description of problem |
Recommended Action for next time |
Lesson Learnt Raised by |
10/12/2018 |
Delay in Documentation |
Documentation template must be followed |
Process Documentation |
14/12/18 |
Website Design Errors |
Design Principles using SDLC must be followed |
Design Principle Implication |
21/12/18 |
Programming Issues |
External Expert must be followed |
Debugging of program bugs |
1/1/19 |
Go Live Issues |
Vendor must be consulted before implementing the website |
Implicational Issues Resolution |
5/12/18 |
Over Budget |
Provisional Budget would be used |
Budget Performance |
References
Burke, R., 2013. Project management: planning and control techniques. New Jersey, USA.
Carver, C.L. and Klein, C.S., 2013. Action research: A tool for promoting faculty development and continuous improvement in leadership preparation.
Clark, D.M., Silvester, K. and Knowles, S., 2013. Lean management systems: creating a culture of continuous quality improvement. Journal of clinical pathology, pp.jclinpath-2013.
Cohen-Vogel, L., Tichnor-Wagner, A., Allen, D., Harrison, C., Kainz, K., Socol, A.R. and Wang, Q., 2015. Implementing educational innovations at scale: Transforming researchers into continuous improvement scientists. Educational Policy, 29(1), pp.257-277.
Dale, B.G. and Plunkett, J.J., 2017. Quality costing. Routledge.
Dessinger, J.C. and Moseley, J.L., 2015. Confirmative evaluation: Practical strategies for valuing continuous improvement. John Wiley & Sons.
Fleming, Q.W. and Koppelman, J.M., 2016, December. Earned value project management. Project Management Institute.
Fryer, K., Ogden, S. and Anthony, J., 2013. Bessant’s continuous improvement model: revisiting and revising. International Journal of Public Sector Management, 26(6), pp.481-494.
Fuller, M.A., Valacich, J.S., George, J.F. and Schneider, C., 2017. Information Systems Project Management: A Process and Team Approach, Edition 1.1. Prospect Press.
Goetsch, D.L. and Davis, S.B., 2014. Quality management for organizational excellence. Upper Saddle River, NJ: pearson.
Harrison, F. and Lock, D., 2017. Advanced project management: a structured approach. Routledge.
Heagney, J., 2016. Fundamentals of project management. Amacom.
Holtskog, H., 2013. Continuous Improvement beyond the Lean understanding. Procedia CIRP, 7, pp.575-579.
Hwang, B.G. and Ng, W.J., 2013. Project management knowledge and skills for green construction: Overcoming challenges. International Journal of Project Management, 31(2), pp.272-284.
Intra, C. and Zahn, T., 2014. Transformation-waves–a brick for a powerful and holistic continuous improvement process of a Lean production system. Procedia CIRP, 17, pp.582-587.
Kerzner, H. and Kerzner, H.R., 2017. Project management: a systems approach to planning, scheduling, and controlling. John Wiley & Sons.
Kerzner, H., 2018. Project management best practices: Achieving global excellence. John Wiley & Sons.
Lam, M., O’Donnell, M. and Robertson, D., 2015. Achieving employee commitment for continuous improvement initiatives. International Journal of Operations & Production Management, 35(2), pp.201-215.
Larson, E.W., Gray, C.F., Danlin, U., Honig, B. and Bacarini, D., 2014. Project management: The managerial process (Vol. 6). Grandview Heights, OH: McGraw-Hill Education.
Leach, L.P., 2014. Critical chain project management. Artech House.
Lemire, M., Demers-Payette, O. and Jefferson-Falardeau, J., 2013. Dissemination of performance information and continuous improvement: a narrative systematic review. Journal of health organization and management, 27(4), pp.449-478.
Magar, V.M. and Shinde, V.B., 2014. Application of 7 quality control (7 QC) tools for continuous improvement of manufacturing processes. International Journal of Engineering Research and General Science, 2(4), pp.364-371.
Marchewka, J.T., 2014. Information technology project management. John Wiley & Sons.
Mir, F.A. and Pinnington, A.H., 2014. Exploring the value of project management: linking project management performance and project success. International journal of project management, 32(2), pp.202-217.
Mitra, A., 2016. Fundamentals of quality control and improvement. John Wiley & Sons.
Nadeem, E., Olin, S.S., Hill, L.C., Hoagwood, K.E. and Horwitz, S.M., 2013. Understanding the components of quality improvement collaboratives: a systematic literature review. The Milbank Quarterly, 91(2), pp.354-394.
Nicholas, J.M. and Steyn, H., 2017. Project management for engineering, business and technology. Routledge.
Oakland, J.S., 2014. Total quality management and operational excellence: text with cases. Routledge.
Okongwu, U., Morimoto, R. and Lauras, M., 2013. The maturity of supply chain sustainability disclosure from a continuous improvement perspective. International Journal of Productivity and Performance Management, 62(8), pp.827-855.
Owen, M., 2013. SPC and continuous improvement. Springer Science & Business Media.
Ross, J.E., 2017. Total quality management: Text, cases, and readings. Routledge.
Sahno, J., Shevtshenko, E., Karaulova, T. and Tahera, K., 2015. Framework for continuous improvement of production processes. Engineering Economics, 26(2), pp.169-180.
Schwalbe, K., 2015. Information technology project management. Cengage Learning.
Singh, J. and Singh, H., 2015. Continuous improvement philosophy–literature review and directions. Benchmarking: An International Journal, 22(1), pp.75-119.
Swartling, D. and Poksinska, B., 2013. Management initiation of continuous improvement from a motivational perspective. Journal of Applied Economics and Business Research, 3(2), pp.81-94.
von Thiele Schwarz, U., Augustsson, H., Hasson, H. and Stenfors-Hayes, T., 2015. Promoting employee health by integrating health protection, health promotion, and continuous improvement: a longitudinal quasi-experimental intervention study. Journal of Occupational and Environmental medicine, 57(2), pp.217-225.
Walker, A., 2015. Project management in construction. John Wiley & Sons.
Essay Writing Service Features
Our Experience
No matter how complex your assignment is, we can find the right professional for your specific task. Contact Essay is an essay writing company that hires only the smartest minds to help you with your projects. Our expertise allows us to provide students with high-quality academic writing, editing & proofreading services.Free Features
Free revision policy
$10Free bibliography & reference
$8Free title page
$8Free formatting
$8How Our Essay Writing Service Works
First, you will need to complete an order form. It's not difficult but, in case there is anything you find not to be clear, you may always call us so that we can guide you through it. On the order form, you will need to include some basic information concerning your order: subject, topic, number of pages, etc. We also encourage our clients to upload any relevant information or sources that will help.
Complete the order formOnce we have all the information and instructions that we need, we select the most suitable writer for your assignment. While everything seems to be clear, the writer, who has complete knowledge of the subject, may need clarification from you. It is at that point that you would receive a call or email from us.
Writer’s assignmentAs soon as the writer has finished, it will be delivered both to the website and to your email address so that you will not miss it. If your deadline is close at hand, we will place a call to you to make sure that you receive the paper on time.
Completing the order and download