Project Management has always been helpful for executing the project in an orderly process for easing the implication of the operations. The scheduling, planning, budgeting, estimating, and managing of the projects are well executed for developing the successful completion of the project. The support and development of the projects had eased the implication and alignment for developing the support for improving the utilization of the factors. The alignment would also be helpful for supporting the development of the options for aligning with the implication of the effective project management principles for the project of 24X7 facilities and services in the upper west side. The following assignment would be developed based on the implication of the facilities defining the implication of the operations and aligning the utilization of the factors.
The following assignment has been made for implementing the 24X7 facilities and services in the upper west side. The alignment would be dependent on forming the support and implementation of the effective alignment of the facilities. The improved services in the building would be installed for developing the improved facilities and operations. The successful alignment would be helpful for easing the implication of the factors defining the support and influence of activities. The completion of the improved functional analysis would form the major impact on the alignment of the support and configuration of the options. The camera services, Existing camera is reviewed, development of information hub, ordering keys and swipes, developing parcel delivery system, improving general cleanliness, upgrade lightning and design, BBQ area signage, and Madison Tower Level Upgrade. The implication of the activities would help in easing the alignment of the factors defining the alignment of the improved services for the complex building.
The project has the primary objective of defining the implication of the improved facilities and aligning the utilization of the factors. The project objective would include the factors of developing the improved services for the development of the factors. The implication would be eased with the utilization of the support and development. The deployment would be eased with the utilization of the factors aligning the development of the support and integration. The support and integration would be utilized for easing the implication and alignment of operations so that the improved functional development can be achieved. The negotiation with the client on objectives and timeline of the project would be based on the implication of the factors defining the analysis of the support and development. The analysis of the factors would be affected by the simplification of the support and development.
The stakeholders of the project are Owners Corporation 1, Owners Corporation 2, Owners Corporation 4, Owners Corporation 5, Owners Corporation 6, Owners Corporation 7, and Australian Property Management Pty Ltd.
The following table would show the roles and responsibilities of the individual for the execution of the project.
Name |
Roles and Responsibilities |
Shawn Lu – Australian Property Management Pty Ltd |
Management of the project and execution for successful completion of the project |
Esin Ibrahim – Australian Property Management Pty Ltd |
In charge of project resources and estimation of the budget required for the project |
Lip Phua – Australian Property Management Pty Ltd |
Scheduling and Planning the project for ensuring the smooth operations of the service development for upper west side |
Justin Barr – Australian Property Management Pty Ltd |
Making required documentation and reports that would be helpful for executing the project activities. |
Tapan Reang – Australian Property Management Pty Ltd |
Supporting documentation and development for easing development of the factors for developing the implication of the operations and aligning the development of the factors. |
Carla Nessel – Australian Property Management Pty Ltd |
Execution of the development and renovation activities for easing the formation of the utilities to form the extension of the operations |
Paul Alabach – Australian Property Management Pty Ltd |
Deploying the utilization of the factors developing the alignment of the improved functional and effective development of operations |
Sonia Arora – Australian Property Management Pty Ltd |
In charge of HR activities for developing the successful integration of the functions aligning the significant formation of improved activities |
The project of 24X7 facilities and services in the upper west side is developed for improving the functional analysis of the factors supporting the utilization of the support and development. The deliverables of the project are,
Security Camera Upgrade: The security camera upgrade would be developed for aligning with the development of the facilities for aligning the implication of the effective and smart processing.
Community Hub: The community hub would be developed for supporting the effective communication and alignment of the factors supporting the implication of the improved operations.
Improvement of general cleanliness: The general cleanliness would be improved with the help of the innovative technology and new management installation.
Upgrade lightning and design: The upgrade of the lightning and design would be required for the technology innovation and development of the factors aligning the simplification.
BBQ area signage: The BBQ area signage would be developed for easing the utilization of the development factors for general meeting and communication development.
Madison Tower Level Upgrade: The tower level would be upgraded with the general alignment of the technology development and execution.
Reduction in Levies Owning: The reduction of the levies owning would be eased in the project activities execution and development.
The project has the primary goal of defining the implication of the improved facilities and aligning the utilization of the factors. The project goal would include the factors of developing the improved services for the development of the factors. The implication would be eased with the utilization of the support and development. The deployment would be eased with the utilization of the factors aligning the development of the support and integration. The support and integration would be utilized for easing the implication and alignment of operations so that the improved functional development can be achieved.
The strategies used for the development of the project activities would be eased with the implication of the facilities defining the alignment of the improved factors. The scheduling, planning, budgeting, estimating, and managing of the projects are well executed for developing the successful completion of the project. The support and development of the projects had eased the implication and alignment for developing the support for improving the utilization of the factors. The alignment would also be helpful for supporting the development of the options for aligning with the implication of the effective project management principles for the project of 24X7 facilities and services in the upper west side.
The monitoring and reporting of the project of 24X7 facilities and services in the upper west side would be deployed with the help of easing the implication of the factors of supporting the implication of the factors aligning the definition of the activities favouring the alignment of the activities. The use of the Gantt chart and checklist would be helpful for keeping track of the project progress and schedule. The use of various testing processes like alpha testing, beta testing, prototyping, and simulation would be helpful for easing the development of the activities. The various strategies of monitoring and reporting in the project include,
Baseline Report: The baseline report is helpful for ensuring that the effective communication process is implied successfully. The support and development would also be helpful for easing the process of the keeping track of the project activities. For example: the report would help in checking how much work of the project has been completed after time interval of one fourth, half, three fourth, and full completion of the estimated time.
Checklist Development: The checklist development would be helpful for easing the utilization of effective implication management. The checklist would be developed keeping in mind the implication of the successful completion of the operations. For example- the developed checklist would keep track of the achievement of the deliverables of plan, documentation, infrastructure, technology, equipments, and final report.
Progress Journal: The progress journal is helpful for noting the day to day activities and aligning the implication of the successful development of the factors. The progress journal would allow the implication of the factors for easing the utilization of the operations. For example- the progress journal would help in back tracking the problem of schedule and change it so that the rest of the project can be completed successfully.
Figure 1: Project Life Cycle Analysis
Source:
The risk management plan would be developed aligning the utilization of the factors defining the simplification of the factors supporting the utilization of the factors aligning the simplicity of the activities deploying the utilization of the factors developing the simplification of the operations. The risk management plan comprises of risk analysis and risk mitigation for supporting the utilization of the factors defining the implication of the operations. The risk management would involve the following factors,
Risk |
Cause of the risk |
Likelihood |
Severity |
Mitigation |
Ranking |
Delay in completion |
The delay can be resulted by many reasons such as lack of the materials, human errors, or equipment failure that would result in halting the progress of the project. |
Likely |
Moderate |
Accept |
3rd |
Over budget |
The over budget is resulted due to the lack of the proper development process and inclusion of the effective implication of the factors. |
Possible |
Major |
Avoid |
2nd |
Technology Issues |
The technology issues are resulted when the equipments fail to involve the alignment of the operations and significant development of the factors. The device may fall short for aligning the simplification and developed operations |
Unlikely |
Critical |
Mitigate |
1st |
The 24X7 facilities and services in the upper west side project would be based on the ground works and the technology innovation implementation. The following legislative requirements must be followed for the project,
The 24X7 service technology implementation for Upper West Side project would involve the use of the technology innovation for development of the effective plan development supporting the implication of the improved development process. The following is the project plan for the improved facilities and services of upper west side, ordering keys and swipes, development of information hub, developing parcel delivery system, improving general cleanliness, upgrade lightning and design, BBQ area signage, and Madison tower level upgrade.
WBS |
Task Name |
Duration |
Start |
Finish |
Predecessors |
0 |
24X7 service technology implementation for Upper West Side |
61 days |
Thu 11/16/17 |
Thu 2/8/18 |
|
1 |
Initialization |
8 days |
Thu 11/16/17 |
Mon 11/27/17 |
|
1.1 |
Project Analysis |
2 days |
Thu 11/16/17 |
Fri 11/17/17 |
|
1.2 |
Resource Accumulation |
3 days |
Mon 11/20/17 |
Wed 11/22/17 |
2 |
1.3 |
Initiation documents |
2 days |
Thu 11/23/17 |
Fri 11/24/17 |
3 |
1.4 |
Submission of documents |
1 day |
Mon 11/27/17 |
Mon 11/27/17 |
4 |
1.5 |
Project Kick off |
0 days |
Mon 11/27/17 |
Mon 11/27/17 |
5 |
2 |
Planning |
13 days |
Tue 11/28/17 |
Thu 12/14/17 |
|
2.1 |
Activity Listing |
2 days |
Tue 11/28/17 |
Wed 11/29/17 |
6 |
2.2 |
Scheduling the activities |
1 day |
Thu 11/30/17 |
Thu 11/30/17 |
8 |
2.3 |
Plan Outline Development |
3 days |
Fri 12/1/17 |
Tue 12/5/17 |
9 |
2.4 |
Review of Plan |
2 days |
Wed 12/6/17 |
Thu 12/7/17 |
10 |
2.5 |
Complete Plan Development |
5 days |
Fri 12/8/17 |
Thu 12/14/17 |
11 |
2.6 |
Plan Approval |
0 days |
Thu 12/14/17 |
Thu 12/14/17 |
12 |
3 |
Execution |
34 days |
Fri 12/15/17 |
Wed 1/31/18 |
|
3.1 |
Security Camera Upgrade |
10 days |
Fri 12/15/17 |
Thu 12/28/17 |
|
3.1.1 |
Existing Camera is reviewed |
2 days |
Fri 12/15/17 |
Mon 12/18/17 |
13 |
3.1.2 |
Upgrading the camera function |
4 days |
Tue 12/19/17 |
Fri 12/22/17 |
16 |
3.1.3 |
Additional and multiple cameras are installed |
4 days |
Mon 12/25/17 |
Thu 12/28/17 |
17 |
3.2 |
Community Hub |
9 days |
Fri 12/29/17 |
Wed 1/10/18 |
|
3.2.1 |
Development of Information Hub |
3 days |
Fri 12/29/17 |
Tue 1/2/18 |
18 |
3.2.2 |
Ordering Keys and Swipes |
2 days |
Wed 1/3/18 |
Thu 1/4/18 |
20 |
3.2.3 |
Developing parcel delivery system |
4 days |
Fri 1/5/18 |
Wed 1/10/18 |
21 |
3.3 |
Other Works |
15 days |
Thu 1/11/18 |
Wed 1/31/18 |
|
3.3.1 |
Improving general cleanliness |
3 days |
Thu 1/11/18 |
Mon 1/15/18 |
22 |
3.3.2 |
Upgrade lightning and design |
3 days |
Tue 1/16/18 |
Thu 1/18/18 |
24 |
3.3.3 |
BBQ area signage |
3 days |
Fri 1/19/18 |
Tue 1/23/18 |
25 |
3.3.4 |
Madison Tower Level Upgrade |
3 days |
Wed 1/24/18 |
Fri 1/26/18 |
26 |
3.3.5 |
Reduction in Levies Owning |
3 days |
Mon 1/29/18 |
Wed 1/31/18 |
27 |
4 |
Closure |
6 days |
Thu 2/1/18 |
Thu 2/8/18 |
|
4.1 |
Final report is developed |
3 days |
Thu 2/1/18 |
Mon 2/5/18 |
28 |
4.2 |
Submission of reports |
1 day |
Tue 2/6/18 |
Tue 2/6/18 |
30 |
4.3 |
Review and sign off |
2 days |
Wed 2/7/18 |
Thu 2/8/18 |
31 |
4.4 |
Project is closed |
0 days |
Thu 2/8/18 |
Thu 2/8/18 |
32 |
The resources required for the execution of the project 24X7 facilities and services in the upper west side are given below,
Human |
Materials |
Project Manager, Planner, Budgeter, Documenter, Analyst, Technician, Material, and Contractor |
Construction Materials, System, Camera, Other Devices |
The project of 24X7 facilities and services in the upper west side is developed for improving the functional analysis of the factors supporting the utilization of the support and development. The deliverables of the project are,
Security Camera Upgrade: The security camera upgrade would be developed for aligning with the development of the facilities for aligning the implication of the effective and smart processing.
Community Hub: The community hub would be developed for supporting the effective communication and alignment of the factors supporting the implication of the improved operations.
Improvement of general cleanliness: The general cleanliness would be improved with the help of the innovative technology and new management installation.
Upgrade lightning and design: The upgrade of the lightning and design would be required for the technology innovation and development of the factors aligning the simplification.
BBQ area signage: The BBQ area signage would be developed for easing the utilization of the development factors for general meeting and communication development.
Madison Tower Level Upgrade: The tower level would be upgraded with the general alignment of the technology development and execution.
Reduction in Levies Owning: The reduction of the levies owning would be eased in the project activities execution and development.
WBS |
Task Name |
Duration |
Start |
Finish |
Predecessors |
0 |
24X7 service technology implementation for Upper West Side |
61 days |
Thu 11/16/17 |
Thu 2/8/18 |
|
1.5 |
Project Kick off |
0 days |
Mon 11/27/17 |
Mon 11/27/17 |
5 |
2 |
Planning |
13 days |
Tue 11/28/17 |
Thu 12/14/17 |
|
2.1 |
Activity Listing |
2 days |
Tue 11/28/17 |
Wed 11/29/17 |
6 |
2.2 |
Scheduling the activities |
1 day |
Thu 11/30/17 |
Thu 11/30/17 |
8 |
2.3 |
Plan Outline Development |
3 days |
Fri 12/1/17 |
Tue 12/5/17 |
9 |
2.4 |
Review of Plan |
2 days |
Wed 12/6/17 |
Thu 12/7/17 |
10 |
2.5 |
Complete Plan Development |
5 days |
Fri 12/8/17 |
Thu 12/14/17 |
11 |
2.6 |
Plan Approval |
0 days |
Thu 12/14/17 |
Thu 12/14/17 |
12 |
3 |
Execution |
34 days |
Fri 12/15/17 |
Wed 1/31/18 |
|
3.1 |
Security Camera Upgrade |
10 days |
Fri 12/15/17 |
Thu 12/28/17 |
|
3.1.1 |
Existing Camera is reviewed |
2 days |
Fri 12/15/17 |
Mon 12/18/17 |
13 |
3.1.2 |
Upgrading the camera function |
4 days |
Tue 12/19/17 |
Fri 12/22/17 |
16 |
3.1.3 |
Additional and multiple cameras are installed |
4 days |
Mon 12/25/17 |
Thu 12/28/17 |
17 |
3.2 |
Community Hub |
9 days |
Fri 12/29/17 |
Wed 1/10/18 |
|
3.2.1 |
Development of Information Hub |
3 days |
Fri 12/29/17 |
Tue 1/2/18 |
18 |
3.2.2 |
Ordering Keys and Swipes |
2 days |
Wed 1/3/18 |
Thu 1/4/18 |
20 |
3.2.3 |
Developing parcel delivery system |
4 days |
Fri 1/5/18 |
Wed 1/10/18 |
21 |
3.3 |
Other Works |
15 days |
Thu 1/11/18 |
Wed 1/31/18 |
|
3.3.1 |
Improving general cleanliness |
3 days |
Thu 1/11/18 |
Mon 1/15/18 |
22 |
3.3.2 |
Upgrade lightning and design |
3 days |
Tue 1/16/18 |
Thu 1/18/18 |
24 |
3.3.3 |
BBQ area signage |
3 days |
Fri 1/19/18 |
Tue 1/23/18 |
25 |
3.3.4 |
Madison Tower Level Upgrade |
3 days |
Wed 1/24/18 |
Fri 1/26/18 |
26 |
3.3.5 |
Reduction in Levies Owning |
3 days |
Mon 1/29/18 |
Wed 1/31/18 |
27 |
4.4 |
Project is closed |
0 days |
Thu 2/8/18 |
Thu 2/8/18 |
32 |
The communication in the project are developed supplying the alignment of the improved functional and development model. The communication in the project can be eased with the implication of the factors defining the synthesis of improved communication development. The communication would be eased with the simplification of the effective communication strategies like,
The various documents like initiation document, charter document, project plan document, communication list, risk management plan, development listing, formation plan, and other documents would be inclined for the development of project report.
The checklist for the project of 24X7 facilities and services in the upper west side is given below,
Item |
Check |
Gathering of initial information |
Yes No |
Resources are accumulated |
Yes No |
Alignment of operations and development of factors |
Yes No |
Project Plan is developed |
Yes No |
Infrastructure is developed |
Yes No |
Technology Innovation is installed |
Yes No |
The major problems for the execution of the project of 24X7 facilities and services in the upper west side are,
Delay in completion of the project is one of the most common issues that most of the projects have been facing in the contemporary world. However, the delay in projects would result in forming the major problems for project.
Over budget is another major problem that the project would have to face as it would result in forming the alignment of factors deploying the resource usage of the project.
The progress monitoring of the project of 24X7 facilities and services in the upper west side would be deployed with the help of easing the implication of the factors of supporting the implication of the factors aligning the definition of the activities favouring the alignment of the activities. The use of the Gantt chart and checklist would be helpful for keeping track of the project progress and schedule. The use of various testing processes like alpha testing, beta testing, prototyping, and simulation would be helpful for easing the development of the activities. The implication of the activities would be eased with the utilization of the innovation.
OLD |
NEW |
|
Owners Corporation 1 |
||
Legal cost & debt recovery |
$20,000.00 |
$5,000.00 |
Management Stationery |
$4,500.00 |
$2,500.00 |
Office Telephone charges |
$7,000.00 |
$3,000.00 |
Contingency line |
$10,000.00 |
$0.00 |
Provision of Maintenance Fund |
$10,000.00 |
$0.00 |
Insurance Recoverable |
$10,000.00 |
$1,000.00 |
Insurance Premiums |
$2,04,000.00 |
$2,60,000.00 |
Waste Compactor |
$12,000.00 |
$55,000.00 |
Electricity |
$18,000.00 |
$37,000.00 |
Water & Sewerage |
$2,10,000.00 |
$4,00,000.00 |
$5,05,500.00 |
$7,63,500.00 |
|
Owners Corporation 2 |
||
Function Room Expenses |
$7,50,000.00 |
$0.00 |
Contingency line |
$5,000.00 |
$0.00 |
Management Stationery |
$3,000.00 |
$1,000.00 |
General Maintenance |
$25,000.00 |
$40,000.00 |
Gym equipment |
$23,000.00 |
$60,000.00 |
Garden Maintenance |
$51,000.00 |
$1,10,000.00 |
Electricity |
$1,02,000.00 |
$1,44,000.00 |
$9,59,000.00 |
$3,55,000.00 |
|
Owners Corporation 4 |
||
Building Manager/Facilities |
$4,02,200.00 |
$1,89,024.00 |
Auto Door Repairs |
$10,000.00 |
$5,000.00 |
Steam Cleaning |
$13,500.00 |
$17,000.00 |
Bin Chute Repairs |
$6,000.00 |
$16,000.00 |
General Maintenance |
$20,000.00 |
$30,000.00 |
Electricity |
$92,000.00 |
$1,15,000.00 |
$5,43,700.00 |
$3,72,024.00 |
|
Owners Corporation 5 |
||
Building Manager/Facilities |
$4,05,000.00 |
$1,89,024.00 |
Essential Services Repairs |
$5,000.00 |
$15,000.00 |
Auto Door Repairs |
$1,500.00 |
$7,000.00 |
Bin Chute Repairs |
$3,000.00 |
$13,000.00 |
Electrical Repairs |
$10,000.00 |
$18,000.00 |
General Repairs |
$38,376.00 |
$30,000.00 |
Lift Repairs |
$8,000.00 |
$15,000.00 |
Plumbing & drainage |
$8,000.00 |
$15,000.00 |
478876 |
302024 |
|
Owners Corporation 6 |
||
Building Manager/Facilities |
$4,04,300.00 |
$1,89,024.00 |
$4,04,300.00 |
$1,89,024.00 |
|
Owners Corporation 7 |
||
Building Manager |
$1,58,000.00 |
$1,28,599.00 |
Rubbish Chute repairs |
$20,000.00 |
$15,000.00 |
Electricity |
$60,000.00 |
$70,000.00 |
$2,38,000.00 |
$2,13,599.00 |
|
$31,29,376.00 |
$21,95,171.00 |
The project would be executed under the supervision of the project manager, contractor, and Engineer for ensuring that the project is completed successfully in the estimated time and budget estimation.
WBS |
Milestone |
Start date |
Finish date |
Status |
0 |
24X7 service technology implementation for Upper West Side |
Thu 11/16/17 |
Thu 2/8/18 |
Completed |
1.5 |
Project Kick off |
Mon 11/27/17 |
Mon 11/27/17 |
Completed |
2 |
Planning |
Tue 11/28/17 |
Thu 12/14/17 |
Completed |
2.1 |
Activity Listing |
Tue 11/28/17 |
Wed 11/29/17 |
Completed |
2.2 |
Scheduling the activities |
Thu 11/30/17 |
Thu 11/30/17 |
Completed |
2.3 |
Plan Outline Development |
Fri 12/1/17 |
Tue 12/5/17 |
Completed |
2.4 |
Review of Plan |
Wed 12/6/17 |
Thu 12/7/17 |
Completed |
2.5 |
Complete Plan Development |
Fri 12/8/17 |
Thu 12/14/17 |
Completed |
2.6 |
Plan Approval |
Thu 12/14/17 |
Thu 12/14/17 |
Completed |
3 |
Execution |
Fri 12/15/17 |
Wed 1/31/18 |
Completed |
3.1 |
Security Camera Upgrade |
Fri 12/15/17 |
Thu 12/28/17 |
Completed |
3.1.1 |
Existing Camera is reviewed |
Fri 12/15/17 |
Mon 12/18/17 |
Completed |
3.1.2 |
Upgrading the camera function |
Tue 12/19/17 |
Fri 12/22/17 |
Completed |
3.1.3 |
Additional and multiple cameras are installed |
Mon 12/25/17 |
Thu 12/28/17 |
Completed |
3.2 |
Community Hub |
Fri 12/29/17 |
Wed 1/10/18 |
Completed |
3.2.1 |
Development of Information Hub |
Fri 12/29/17 |
Tue 1/2/18 |
Completed |
3.2.2 |
Ordering Keys and Swipes |
Wed 1/3/18 |
Thu 1/4/18 |
Completed |
3.2.3 |
Developing parcel delivery system |
Fri 1/5/18 |
Wed 1/10/18 |
Completed |
3.3 |
Other Works |
Thu 1/11/18 |
Wed 1/31/18 |
Completed |
3.3.1 |
Improving general cleanliness |
Thu 1/11/18 |
Mon 1/15/18 |
Completed |
3.3.2 |
Upgrade lightning and design |
Tue 1/16/18 |
Thu 1/18/18 |
Completed |
3.3.3 |
BBQ area signage |
Fri 1/19/18 |
Tue 1/23/18 |
Completed |
3.3.4 |
Madison Tower Level Upgrade |
Wed 1/24/18 |
Fri 1/26/18 |
Completed |
3.3.5 |
Reduction in Levies Owning |
Mon 1/29/18 |
Wed 1/31/18 |
Completed |
4.4 |
Project is closed |
Thu 2/8/18 |
Thu 2/8/18 |
Completed |
The use of the Gantt chart and checklist would be helpful for keeping track of the project progress and schedule. The use of various testing processes like alpha testing, beta testing, prototyping, and simulation would be helpful for easing the development of the activities. The various documents like initiation document, charter document, project plan document, communication list, risk management plan, development listing, formation plan, and other documents would be inclined for the development of project report.
The strategies used for the development of the project activities would be eased with the implication of the facilities defining the alignment of the improved factors. The scheduling, planning, budgeting, estimating, and managing of the projects are well executed for developing the successful completion of the project. The use of various testing processes like alpha testing, beta testing, prototyping, and simulation would be helpful for easing the development of the activities. The support and development of the projects had eased the implication and alignment for developing the support for improving the utilization of the factors.
Item |
Completed |
Gathering of initial information |
Yes |
Resources are accumulated |
Yes |
Alignment of operations and development of factors |
Yes |
Project Plan is developed |
Yes |
Infrastructure is developed |
Yes |
Technology Innovation is installed |
Yes |
a) Utilization of the project management methodology
b) Proper Training Program Development
c) Implementing the use of past documents and reports
Sign off:
<name of the project manager>
<name of the project manager>
Project Manager
Conclusion
Project Management had always been helpful for executing the project in an orderly process for easing the implication of the operations. The scheduling, planning, budgeting, estimating, and managing of the projects were well executed for developing the successful completion of the project. The support and development of the projects had eased the implication and alignment for developing the support for improving the utilization of the factors. The following assignment had been made for implementing the 24X7 facilities and services in the upper west side. The alignment had been dependent on forming the support and implementation of the effective alignment of the facilities.
Berger, Bruce K., and Juan Meng, eds. Public relations leaders as sensemakers: A global study of leadership in public relations and communication management. Routledge, 2014.
Bessis, Joel. Risk management in banking. John Wiley & Sons, 2015.
Binder, Jean. Global project management: communication, collaboration and management across borders. Routledge, 2016.
Fleming, Quentin W., and Joel M. Koppelman. “Earned value project management.” Project Management Institute, 2016.
Goetsch, David L., and Stanley B. Davis. Quality management for organizational excellence. Upper Saddle River, NJ: pearson, 2014.
Harbor, Jason, Laurie Carswell Petrucci, and Tatiana Bourlova. “Assignment 3 Project Documentation:? Creating a Content Module for Calculus 12.” (2015).
Harrison, Frederick, and Dennis Lock. Advanced project management: a structured approach. Routledge, 2017.
Heagney, Joseph. Fundamentals of project management. Amacom, 2016.
Hopkin, Paul. Fundamentals of risk management: understanding, evaluating and implementing effective risk management. Kogan Page Publishers, 2018.
Jousse, Jérémie, Nicolas Ginot, Christophe Batard, and Elisabeth Lemaire. “Power line communication management of battery energy storage in a small-scale autonomous photovoltaic system.” IEEE Transactions on Smart Grid 8, no. 5 (2017): 2129-2137.
Kerzner, Harold, and Harold R. Kerzner. Project management: a systems approach to planning, scheduling, and controlling. John Wiley & Sons, 2017.
Kerzner, Harold. Project management best practices: Achieving global excellence. John Wiley & Sons, 2018.
Lam, J., 2014. Enterprise risk management: from incentives to controls. John Wiley & Sons.
Larson, Erik W., Clifford F. Gray, Ursula Danlin, Beverly Honig, and David Bacarini. Project management: The managerial process. Vol. 6. Grandview Heights, OH: McGraw-Hill Education, 2014.
MacWhinney, Brian. The CHILDES project: Tools for analyzing talk, Volume II: The database. Psychology Press, 2014.
Marchewka, Jack T. Information technology project management. John Wiley & Sons, 2014.
McNeil, Alexander J., Rüdiger Frey, and Paul Embrechts. Quantitative Risk Management: Concepts, Techniques and Tools-revised edition. Princeton university press, 2015.
Mir, Farzana Asad, and Ashly H. Pinnington. “Exploring the value of project management: linking project management performance and project success.” International journal of project management 32, no. 2 (2014): 202-217.
Mooney, Hailey, Jake Carlson, Karen Downing, and Lori Tschirhart. “Documentation in the Middle: Active Phase Project Documentation for Inclusive and Effective Team-Based Research.” (2017).
Nicholas, John M., and Herman Steyn. Project management for engineering, business and technology. Routledge, 2017.
Oliver, Kevin, and Jennifer Houchins. “Evidence of Computational Thinking in the After-School Makerspace from Written Project Documentation.” In EdMedia+ Innovate Learning, pp. 402-407. Association for the Advancement of Computing in Education (AACE), 2018.
O’Neill, Raymond. “Recommendations for Updating the Alaska Department of Transportation Construction Project Documentation Manual.” (2015).
Ruehl, Christopher Hendrik, and Diana Ingenhoff. “Communication management on social networking sites: Stakeholder motives and usage types of corporate Facebook, Twitter and YouTube pages.” Journal of Communication Management 19, no. 3 (2015): 288-302.
Svejvig, Per, and Peter Andersen. “Rethinking project management: A structured literature review with a critical look at the brave new world.” International Journal of Project Management 33, no. 2 (2015): 278-290.
Tench, Ralph, and Angeles Moreno. “Mapping communication management competencies for European practitioners: ECOPSI an EU study.” Journal of Communication Management 19, no. 1 (2015): 39-61.
Turner, Rodney. Gower handbook of project management. Routledge, 2016.
Verzuh, Eric. The fast forward MBA in project management. John Wiley & Sons, 2015.
Walker, Anthony. Project management in construction. John Wiley & Sons, 2015.
Wolke, Thomas. Risk Management. Walter de Gruyter GmbH & Co KG, 2017.
Wolke, Thomas. Risk Management. Walter de Gruyter GmbH & Co KG, 2017.
Essay Writing Service Features
Our Experience
No matter how complex your assignment is, we can find the right professional for your specific task. Contact Essay is an essay writing company that hires only the smartest minds to help you with your projects. Our expertise allows us to provide students with high-quality academic writing, editing & proofreading services.Free Features
Free revision policy
$10Free bibliography & reference
$8Free title page
$8Free formatting
$8How Our Essay Writing Service Works
First, you will need to complete an order form. It's not difficult but, in case there is anything you find not to be clear, you may always call us so that we can guide you through it. On the order form, you will need to include some basic information concerning your order: subject, topic, number of pages, etc. We also encourage our clients to upload any relevant information or sources that will help.
Complete the order formOnce we have all the information and instructions that we need, we select the most suitable writer for your assignment. While everything seems to be clear, the writer, who has complete knowledge of the subject, may need clarification from you. It is at that point that you would receive a call or email from us.
Writer’s assignmentAs soon as the writer has finished, it will be delivered both to the website and to your email address so that you will not miss it. If your deadline is close at hand, we will place a call to you to make sure that you receive the paper on time.
Completing the order and download