In the year 1960, the water usage in the United Arab Emirates has increased significantly due to growth in population, higher standards of living and expansion in the agricultural and industry areas. [1]
UAE citizens receive their water supply mostly from desalinated seawater. Basically, in the UAE there are two main sources of water, which are desalinated seawater and groundwater. In 2008 the groundwater contributed 71% of the total water demand for all purposes while the desalinated water contribution was around 24%. [2] By the time the reliance on the fresh groundwater resources in the UAE depleted rapidly, hence, the non-conventional water supplies are needed to sustain the economic development in the UAE. The half of annual water production is used for irrigation and the other half is used for the domestic uses. [1]
To supply houses with clean water the water supply network is mandatory, it is a system of engineered hydrologic and hydraulic components. Since the water is transported from Supplier Company to villa via pipeline, it is really important to specify pipe, fittings and accessories specification based on the latest issue of the ISO standards and codes. The material that used for the piping is the ductile iron because of its availability in the warehouse. The are a lot of challenges in this project such as urgent connections were required, main pipeline was not exist, deliver potable water with stable pressure minimum 1.25 bar.
To overcome these challenges, the project management institutes (PMI) standards and practice should be followed which provides a wide range of services to the project management profession (PM) such as setting professional standards, performing research and offering access to a wealth of information and resources. [3] By following the PMI ensure smooth implementation of any as per specification. PMI promotes a drastic career and professional development and offers certification, networking and interest opportunities. PMI standards and methods are flexible and adaptable to any kind of projects.
A continuing sustainable water supply is needed for domestic uses at the customer land. The proposed project water supply capacity is approximately 3408 gal/day. The purpose of the project is to accomplish an implantation of pipeline that supplies water to the villas. To achieve project goal, the following action should be taken:
Project Charter uses as the project initiation is recommended by the PMI’s PMBOK.
”A document issued by the project initiator or sponsor that formally authorizes the existence of a project, and provides the project manager with the authority to apply organizational resources to project activities.” (PMBOK® Guide, Third Edition) [4]
Project Name: |
Network Extension in Al Adla – Abu Dhabi |
Anticipated Start Date: |
April 24, 2014 |
Anticipated End Date: |
June 26, 2014 |
Eng. Fatima Al Hammadi |
|
Eng. Asma Al Mulla |
|
Eng. Abeer Al Hammadi |
|
Project Scope |
|
Deliver potable water to customer (land) via linking150 mm ductile iron pipe from existing 280mm high-density polyethylene far from the land by around 600 meter, with minimum pressures equal 1.25 bar. |
|
Business Need: |
|
Villas need a water supply about 3408 gal/day. The existence water manifold size is 280 mm with very high pressure and the type of the pipe is a high-density polyethylene (HDPE). However, the distance between the manifold and the first villa is around 10 meter and 20 meter far from second villa. The plan is to use a water manifold size 280mm, which is about 600 meter far from the villa with 150 mm diameter ductile iron pipe. |
|
Project Description: |
|
The work covers the surveying of the site, site preparation, commissioning pipelines and associated fittings, chambers, and accessories, as per company standard specifications, and all incidental work associated with the proposed project, tender B.O.Q and work orders issued by the USER for providing the water connection to the customer, relocation of existing services. |
|
Assumptions: |
|
1. The project can be completed in 3-5months 2. The project cost is estimated around 700,000 AED. 3. The project will solve the unavailability of water pipeline suitable for house connection tapping in the area. 4. The project will deliver potable water with pressure around 1.25 bar. |
|
Constraints: |
|
1. Maximum size of 300 mm diameter is allowed for the house connection 2. Allowable minimum water pressure is 1.25 bar 3. Allowable maximum tensile strength for pipe centrifugally cast 420 MPa 4. Ductile iron material should be used for the piping. 5. Pipe coating shall be completely free from porosity. |
|
Risk: |
|
1. Pipe explosion due to over pressurizing 2. Backflow might occur which is the reversal of normal flow direction where water flows from the intended point of delivery towards the supply. 3. Backflow caused by a lower pressure in the potable supply than at the point of delivery. |
The Networking extension Team will use different tools and technique to identify the stakeholder in the project like: brainstorming session, historical data and expert judgment.
The brainstorming session will consist of the project team and project sponsor and it will contain two parts. The first part will focus on internal stakeholders within the company. These stakeholders may include functional managers, operations and finance personnel, and any other of the company employee who will be affected by the Networking extension project. The second part will focus on external stakeholders. These may include suppliers, contractors, partner organizations, or any other individuals who reside outside of the company.
Also we will refer to the historical data for smeller projects to ensure the identification of stakeholder as required to this kind of project, and finally we will take the expert judgment in consideration while brainstorming session.
Once all Networking extension Project stakeholders have been identified, the project manger will classify and analyze each stakeholder regarding to their possible interests they may have in the project and the influence (power) that they have over the project .
The main purpose of this analysis is to plan the best approach for each stakeholder and to determine the appropriate communication plan with him or her.
Networking extension Project stakeholders |
|
Internal Stakeholders |
Project team, Project manager, Operation and maintenance Dept., Supply Dept., Customer service Dept., Assets Dept., Project Dept. and HSEQ Dept. |
External Stakeholder |
Contractor, Owner, External supplier |
The chart below will be used to set up stakeholders and their levels of influence (power) and interest.
Key |
Internal/ External |
Name |
Power (1-5) |
Interest (1-5) |
A |
Internal |
Project team |
2 |
5 |
B |
Internal |
Project manager |
5 |
5 |
C |
Internal |
Operation and maintenance Dept. |
1 |
4 |
D |
Internal |
Supply Dept. |
2 |
1 |
E |
Internal |
Customer service Dept. |
1 |
1 |
F |
Internal |
Assets Dept. |
4 |
1 |
G |
Internal |
Project Dept. |
5 |
4 |
H |
Internal |
HSEQ Dept. |
4 |
2 |
I |
External |
Contractor |
2 |
5 |
J |
External |
Owner |
5 |
5 |
K |
External |
External supplier |
1 |
4 |
Below is the power/interest chart for the Networking extension Project stakeholders.
High power |
Keep satisfied HSEQ Dept. |
Manage closely Project manager Assets Dept. Project Dept. Owner |
Low Power |
Monitor (Minimum effort) Supply Dept. Customer service |
Keep informed Operation and maintenance Dept. Project team Contractor External supplier |
Low interest |
High interest |
Based on the analysis and chart above, for the stakeholders HSEQ Dept. (high power, less interest) project manger should put enough work in with them to keep them satisfied but not so much that they become bored form the messages. Stakeholders Project manager, Assets Dept., project Dept. and the owner (high power, high interest) must be fully engage and make maximum efforts to satisfy them during the project. For the Stakeholders Supply Dept. and Customer service (low power, low interest) the project manger has to monitor them but do not bore them with excessive communication. Finally the Stakeholder Operation and maintenance Dept., Project team, Contractor and External supplier (low power, high interest) must kept adequately informed and talk to them to insure that no major issues or risk are arising.
Stakeholder |
Interest |
Influence |
Classification |
Strategy for gaining support |
Project manager |
H |
H |
Internal |
Manage closely |
Project team |
H |
L |
Internal |
Keep informed |
Operation and maintenance |
H |
L |
Internal |
Keep informed |
Supply Dept. |
L |
L |
Internal |
Monitor |
Customer service |
L |
L |
Internal |
Monitor |
Assets Dept. |
H |
H |
Internal |
Manage closely |
Project Dept. |
H |
H |
Internal |
Manage closely |
HSEQ Dept. |
H |
L |
Internal |
Keep satisfied |
Contractor |
H |
L |
External |
Keep informed |
Owner |
H |
H |
External |
Manage closely |
External supplier |
H |
L |
External |
Keep informed |
Project scope management processes include; plan scope management, collect requirements, define scope, creating breakdown structure, verify scope and control scope.
Benefit of project scope management during project planning:
Project scope description:
“ The project scopes are to deliver potable water to customer (land) via linking150 mm DI pipe from existing 280mm HDPE far from the land by around 600 meter with minimum pressure equal 1.25 bar. The water pipeline shall do the following function, close the network when it’s required, and maintain the validity of water. “
Requires the project manager and the project team to perform multiple actions to execute the project management plan to accomplish the work defined in the project scope statement. [7]
Project Deliverables:
Project Constrains:
Project Assumptions:
Create Work Breakdown Structure:Project Time Management:
Project time management is one of the most important management that lead to project success and its part of project management that includes the processes required ensuring timely completion of the project. It consists of activity definition, activity estimate duration, sequencing activity and finally develop schedule. Also it’s called project planning or project scheduling. To develop project schedule, first activities will be defined then based on the PERT analysis the activity duration will be estimate, after that the activity will arrange as a sequence based on dependency, finally the schedule will be developed.
Define activities involve identifying and documenting the specific activities that must be performed in order to produce the deliverables and sub deliverables identified in the WBS.
Following are the activities for our project:
Table 1: Define activities.
Activity |
Backfilling |
Engineering |
Chamber works |
Prepare and submit site survey report |
Gate valve chamber No.1 |
Prepare and submit shop (draft) drawing |
Excavation |
Review and approve shop drawing |
Blinding |
Prepare and submit of schedule |
Casting of RC base slab |
Material Procurement |
Installation of valves and fittings |
Issue material |
Shuttering steel and casting wall |
Construction |
External water proofing |
Installation DN 150mm Ductile Iron waterline |
Backfilling |
Pipe wrapping |
Installation of cover slab |
Trench excavation |
Fixing of ladders and internal finishing |
Pipeline installation |
Gate valve chamber No.2 |
Laying warning tape |
Excavation |
Gate valve chamber No.2 |
External water proofing |
Blinding |
Backfilling |
Casting of RC base slab |
Installation of cover slab |
Installation of valves and fittings |
Fixing of aluminum ladders and internal finishing |
Shuttering steel and casting wall |
Pillar type fire hydrant No.1 |
External water proofing |
Installation of pillar type fire hydrant |
Backfilling |
Commissioning |
Installation of cover slab |
Pressure test |
Fixing of ladders and internal finishing |
Flushing and disinfection |
Washout chamber No.1 |
Lab test and report |
Excavation |
Approval for Shutdown |
Blinding |
Shutdown and commissioning |
Casting of RC base slab |
Installation of house connection |
Installation of valves and fittings |
Completion of Project |
Shuttering steel and casting wall |
END |
The above-mentioned activities were not in order sequences.
Sequence Activity:
Sequences activities involve identify and document interactivity dependencies, were activity list, scope statement and milestone list used to help in sequence activities. Finish to Start relation were used to sequencing activities.
Estimate Activity Duration:
In estimate activity duration, PERT technique were used, Three point estimate; Optimistic, most likely, pessimistic.
Example of calculate the duration for pipe wrapping using PERT technique:
Develop schedule means determining start and finish dates for the project, to build project schedule we use activities list, activities sequences, activities duration, resources estimation and Microsoft Project.
Project cost management in planning phase focus on plan cost management, cost estimation and cost budgeting.
In developing cost estimation, the cost was dividing into two parts, civil work and construction, erection and commissioning.
Following tables will show the cost estimate of overall civil work and construction work. The price per service is confidential.
S/N |
DESCRIPTON |
DIA |
UNIT |
QUANTITY |
1 |
EXCAVATION & BACKFILL FOR D.I. PIPELINE |
150 |
MR |
15.00 |
2 |
EXCAVATION & BACKFILL FOR HDPE PIPELINE |
225 |
MR |
3.00 |
3 |
EXCAVATION & BACKFILL FOR D.I. PIPELINE |
150 |
MR |
600.00 |
4 |
EXCAVATE, DEWATER AND BACKFILL FOR EVERY ADDITIONAL DEPTH |
80-150 |
MR |
20.00 |
5 |
CONSTRUCT THRUST / LINE ANCHOR BLOCKS |
CUM. |
2 |
|
6 |
CONSTRUCT LINE VALVE CHAMBER |
– |
CUM. |
13 |
7 |
CONSTRUCT WASHOUT VALVE CHAMBER |
CUM. |
||
8 |
CONSTRUCT STAND BLOCK FOR FIRE HYDRANT |
NOS. |
1 |
|
9 |
CONSTRUCT & SUPPLY MARKER POST |
80 |
NOS. |
4 |
10 |
CONSTRUCT & SUPPLY MARKER POST FOR FIRE HYDRANT |
100 |
NOS. |
4 |
11 |
CONSTRUCT SIGN POST FOR FIRE HYDRANT |
NOS. |
1 |
|
12 |
CONSTRUCT PULLING BOX |
NOS. |
4 |
|
13 |
CONSTRUCT STOP VALVE BOX |
NOS. |
2 |
|
Total Estimate Cost of Civil Work = 87,663 AED |
S/N |
DESCRIPTON |
DIA |
UNIT |
QUANTITY |
1 |
INSTALLATION OF HDPE PIPES |
225 |
MR |
3.00 |
2 |
INSTALLATION OF HDPE STUB FLANGE WITH BACKING RING |
160 |
NOS. |
1 |
3 |
INSTALLATION OF HDPE ELECTROFUSION COUPLER |
225 |
NOS. |
3 |
4 |
INSTALLATION OF D.I PIPES |
100 |
MR |
15.00 |
5 |
INSTALLATION OF D.I PIPES |
150 |
MR |
600.00 |
6 |
INSTALLATION OF DI FITTINGS COMPLETE |
100-150 |
NO |
23.00 |
7 |
INSTALLATION OF D.I GATE VALVE & FIRE HYDRANTS |
150 |
NO |
4 |
8 |
CONNECTION / DISCONNECTION TO EXISTING HDPE PIPELINE |
200-300 |
NO |
1 |
9 |
COROSION PROTECTION FOR PIPES, VALVES, FITTINGS ETC ASSEMBLED IN CHAMBER FOR ANY KIND |
80-150 |
NO |
2.00 |
10 |
COROSION PROTECTION FOR PIPES, VALVES, FITTINGS ETC ASSEMBLED IN CHAMBER FOR GATE VALVE |
NO |
1.00 |
|
11 |
COROSION PROTECTION FOR D.I. PIPES AND FITTINGS FOR ANY KIND |
100 |
MR |
15.00 |
12 |
COROSION PROTECTION FOR D.I. PIPES AND FITTINGS FOR ANY KIND |
150 |
MR |
600.00 |
13 |
COROSION PROTECTION FOR FLANGED REST JOINTS |
80-150 |
NO |
6.00 |
14 |
COLLECT AND TRANSPORT |
|||
15 |
DI PIPES |
80 -150 |
MR |
615.00 |
16 |
DI FITTINGS |
80 -150 |
NO |
27.00 |
COLLECT AND TRANSPORT |
||||
17 |
DI COVER AND FRAMES |
600 |
NO |
4.00 |
18 |
ALUMINIUM SURFACE BOX |
NO |
3.00 |
|
19 |
ALUMINIUM COVER AND FRAME FOR H.C. |
350×350 |
NO |
2.00 |
20 |
ALUMINIUM SEALING FLANGE |
150 |
NO |
2.00 |
21 |
ALUMINIUM LADDERS |
NO |
4.00 |
|
22 |
CHAMBER INDICATION PLATES |
NO |
6.00 |
|
23 |
SUPPLY, CONSTRUCT & INSTALL SERVICE HOUSE CONNECTION upto stop valve box |
NOS |
2 |
|
24 |
COLLECT&TRANSPORT HC PIPES |
MR |
240 |
|
25 |
COLLECT&TRANSPORT SADDLE STRAP |
NO |
2 |
|
26 |
COLLECT&TRANSPORT HC FITTINGS |
NO |
6 |
|
27 |
COLLECT&TRANSPORT HC GATE VALVE |
NO |
2 |
|
28 |
COLLECT&TRANSPORT COVER&FRAME FOR PULLING BOX |
NO |
4 |
|
29 |
COLLECT&TRANSPORT COVER&FRAME FOR STOP VALVE BOX |
NO |
2.00 |
|
Total estimate cost for construction, erection and commissioning = 175,286 AED |
In cost budgeting, the total cost will be calculated, direct, indirect and contingency cost.
Direct Cost |
Total (AED) |
Civil Work |
87,663 |
Construction, Erection and Commissioning |
175,286 |
Site survey (LS 1% from Civil work plus construction) |
2630.0 |
Materials |
280,000 |
Indirect Cost |
Total |
Mobilization (LS 0.5% from Civil work plus construction) |
1315.0 |
Demobilization and site clearance (LS 0.5% from Civil work plus construction) |
1315.0 |
As built documentation and construction documentation (LS 1% from Civil work plus construction) |
2630.0 |
Supervision for the company (20% for direct and indirect) |
110,168 |
Contingency (5% from total) |
33,050 |
Total |
694,057 |
The Purpose of this PQP is to set out the specific work practices, methods, events, procedures, audit plan, allocation of resources, responsibilities and authority, schedules etc. for different phase of the work in accordance with the contract documents and shall be fulfilled, implemented and maintained during the execution of project to the satisfaction of the Engineer and Employer.
The Project Quality Plan shall be designed to assure the implementation and continuous maintenance of the specified quality throughout the period of the Contract. It shall cover, but not be limited to the following activities:
The Project Quality Plan details the requirements that are to be undertaken by project manager to ensure that the requirements for quality are complied with the Contract and are proven to be clear, effective and efficient. Emphasis shall be placed on the prevention of deficiencies at all stages of the Contract rather than rectifying the deficiencies. This document shall be read in conjunction with the various sections of the Contract Drawings & Documents and any subsequent revisions or approved deviations of it together with approved shop drawings & documents.
Any revisions to the Project Quality Plan shall be agreed with the affected parties prior to their incorporation. The new Rev. No. and its effective date shall be entered on the affected page. The revised areas will be identified by bold and italic letters or by marking on the right hand side by a line.
Anyone affected by the Project Quality Plan is encouraged to offer constructive criticism with a view to improving its efficiency, but only the Site QA/QC Engineer (or his delegate) is authorized to change an agreed Quality Document, and only after the necessary consultations have been made.
SL |
Document |
Prepared By |
Reviewed By |
Approved By |
1 |
Project Quality Plan |
Process Owner QA/QC Engineer Project Engineer |
QA/OC Manager Project’s Manager Project Manager |
Project Manager |
2 |
Forms |
Process Owner QA/QC Engineer Project Engineer |
QA/OC Manager Project’s Manager Project Manager |
Project Manager |
3 |
Other Documents, instructions, inspection -test |
Process Owner |
Project Manager |
Project Manager |
3.5 Project Human Resource Management:
The processes required making involved people to the project more effective by identify them first, then obtain them, finally develop them.
Plan human resource includes identifying the human resource, assign responsibilities and specify when each party of human resources will be brought onto and taken off from the project.
HR Responsibility Assignment Matrix (RAM)
Person |
Phase |
Initiation |
Design |
Procurement |
Construction |
Commissioning |
Close |
Project Manager |
P |
R |
P |
R |
R |
R |
|
HSEQ Engineer |
P/S |
P |
|||||
Asset Engineer |
R |
RR/S |
S |
||||
Supply Engineer |
R/S |
||||||
O&M Engineer |
P |
P |
RR/S |
S |
|||
CS Engineer |
P |
||||||
Contractor |
P |
RR |
R |
R |
R |
||
R: Responsible, P: Participant, RR: Review Required, S: Sign off Required |
Project procurement management contains the following processes planning for procurement, conduct procurement, control procurement and close it.
Procurement includes the processes required to acquire goods and services, to attain project scope, from outside the performing organization. [6]
In this project the procurement plan is different were the materials are exist in the store and you order it from their based on your project scope requirements. The procurement plan is in separate project managed by supply (procurement) department. Only the process is to reserve the required materials prior project start and after the inspection and approval. In this project the plan was to order the material after finish from designed and approved drawing.
During the execution, five different types of materials were not available in store, in this case project manager can purchase mentioned materials from one of approved supplier in vender list. After materials inspection and price comparison, project manager can go for procurements.
Table: List of outsource materials
Material Description |
Size |
Unit |
Number |
HDPE TEE |
OD280X280 |
NO |
1 |
HDPE ELECTROFUSION COUPLING |
OD280 |
NO |
2 |
Sp Sp REDUCER |
OD280X200 |
NO |
1 |
Sp Sp REDUCER |
OD200X160 |
NO |
1 |
LADDER |
2 meter |
NO |
4 |
Below is the list of materials (Issued form company store):
Table: List of material issued from company’s store
Material Description |
DIA |
UNIT |
Total Material Issue d by Store |
STUB FLANGE |
160 |
NO |
1 |
HDPE PIPE |
225 |
MR |
3.00 |
HDPE TEE |
225X160 |
NO |
1 |
D.I PIPE |
150 |
MR |
599.50 |
D.I PIPE |
100 |
MR |
18.00 |
ALL SOCKET TEE |
150X100 |
NO |
1 |
SSF TEE |
150X80 |
NO |
1 |
DBL SOC BEND |
150X90º |
NO |
2 |
DBL FLANGE BEND |
80X45º |
NO |
1 |
DBL FLANGEPIPE WITH ANCHOR FLANGE (.L=900mm,D=350mm) |
150 |
NO |
2 |
DBL FLANGEPIPE WITH ANCHOR FLANGE (.L=900mm,D=350mm) |
80 |
NO |
1 |
FL SPIGOT WITH ANCHOR FLANGE (L=900mm,D=350mm) |
80 |
NO |
1 |
DBL FLANGE PIPEPIECE.L=300mm |
80 |
NO |
1 |
SEALING FLANGE |
150 |
NO |
2 |
FL SOCKET |
150 |
NO |
4 |
FL SOCKET |
100 |
NO |
1 |
BLANK FLANGE |
150 |
NO |
1 |
BLANK FLANGE |
80 |
NO |
1 |
COLLAR |
150 |
NO |
1 |
FL ADAPTOR |
150 |
NO |
2 |
FL ADAPTOR |
80 |
NO |
1 |
GATE VALVE |
150 |
NO |
2 |
GATE VALVE |
80 |
NO |
1 |
PILLAR TYPE FIRE HYDRANT |
100 |
NO |
1 |
S BEND |
100 |
NO |
1 |
D,I COVER&FRAME |
600 |
NO |
4 |
SURFACE BOX |
350 mm |
NO |
4 |
CHAMBER INDICATION PLATE |
100 mm |
NO |
2 |
INFORMATION PLATE |
100 mm |
NO |
3 |
VENT PIPE |
60 mm |
NO |
8 |
DBL FLANGE BEND |
100X90º |
NO |
1 |
DBL SOC BEND |
100X90º |
NO |
1 |
LDPE H.C PIPE |
11/2” |
NO |
240 |
uPVC PIPE |
160 |
MR |
240.00 |
SADDLE STRAP |
6” |
NO |
2 |
FERRULE |
11/2” |
NO |
2 |
GATE VALVE |
11/2” |
NO |
2 |
MALE ADAPTOR |
11/2” |
NO |
4 |
SQUARE COVER&FRAME |
650X650 |
NO |
4 |
SQUARE COVER&FRAME |
350X350 |
NO |
2 |
POLYETHYLENE SLEEVES |
MR |
600.00 |
The communication management plan identifies all forms of communication that will be used during the project. For each communication device, such as written reports, a kick off meeting, monthly meeting or a progress report, the plan will indicate the intended audience beside the purpose, medium and frequency of the communication.
This plan consist of the roles and responsibly of stakeholders that involved in the project, communications matrix which illustrate the communication requirements in the project, required contact information for each stakeholder in the project and the team meeting which the status and issues can flow between the project manger and the team.
Communication management consists of three processes, plan communication, Manage communication and control the communication.
In Plan communication we determined the information and communication needs of stakeholders.
Networking extension Project stakeholders
Networking extension Project stakeholders |
|
Internal Stakeholders |
Project team, Project manager, Operation and maintenance Dept., Supply Dept., Customer service, Assets Dept., Project Dept., HSEQ Dept. |
External Stakeholder |
1. Contractor 2. Owner 3. External supplier |
Networking extension Project stakeholders roles |
|
Stakeholder |
Role(s) |
Project manager |
1. Plan and mange the project execution |
Project team |
1. Execute the project plan |
Operation and maintenance Dept. |
1. Mange shutdown of the network 2. Test the water (suitable) 3. Operate the network |
Supply Dept. |
1. Supply material (store) 2. Mange outsourced material |
Customer service |
1. Customer registration 2. Billing the customer |
Assets Dept. |
1. Point of Connection approval |
Project Dept. |
1. Control the project |
HSEQ Dept. |
1. Insure safety and quality of the project |
Contractor |
1. Execute the project |
Owner |
1. Provide requirements |
External supplier |
1. Supply material |
Communication Type |
Description |
Frequency |
Format |
Participants/ Distribution |
Deliverable |
Weekly Status Report |
Email summary of project status |
Weekly |
|
Project Sponsor, Team and Stakeholders |
Status Report |
Weekly Project Team Meeting |
Meeting to review action register and status |
Weekly |
In Person |
Project Team |
Updated Action Register |
Project Monthly Review |
Present metrics and status to team and sponsor |
Monthly |
In Person |
Project Sponsor, Team, and Stakeholders |
Status and Metric Presentation |
Project Gate Reviews |
Present closeout of project phases and kickoff next phase |
As Needed |
In Person |
Project Sponsor, Team and Stakeholders |
Phase completion report and phase kickoff |
Steering Committee Meeting |
Meeting To discuss the project progress, major issues and risks |
Monthly |
In Person |
Project Steering Committee |
resolve any problem, risk and issue |
Project/Phase Acceptance meeting |
To arrange the project acceptance |
As per the schedule plan |
Letters, Meeting |
Project Sponsor, Team and Stakeholder |
Deliverables acceptance sign off |
Risk Management is the systematic application of management policies, procedures and practices to manage risks identified, to an acceptable level and in a consistent, transparent manner. It is a multifaceted process with many aspects carried out by multi-disciplinary teams. [5]
The main objectives for carrying out a risk assessment are to ensure that human health, the community and the environment are protected, and that the necessary resources are allocated in a prioritized and defensible manner to ensure that any unacceptable risks identified will be reduced to acceptable levels.
Where risk assessment identifies the potential for exposure to exceed the determined permissible or allowable exposure, then risk management is necessary to reduce the potential risk to human health, the environment or environmental values. [5]
General requirements
SN |
Hazard / Aspect |
Source of Hazard |
Condition that develop the hazard |
Consequences / Impact |
Risk Evaluation (BEFORE) |
Risk Level |
Recommended Control Measures P |
Risk Evaluation (AFTER) |
Risk Level |
||||
P |
S |
(H/M/L) |
P |
S |
(H/M/L) |
||||||||
Water Net work Activities |
|||||||||||||
WND 01 |
Noise |
Diesel Generator running, Water Pump, Pipe Cutters, A/C Window type. |
Pumping Operation Pipe Cutting Normal works |
Hearing damage, health effects |
H |
D |
3 |
M |
Eng: Maintenance program, using new A/C Admin: working procedure, signs, work duration PPE: Hearing Protection |
H |
A |
1 |
L |
Lost Time |
S |
B |
3 |
M |
S |
A |
1 |
L |
|||||
Non |
E |
E |
|||||||||||
WND 02 |
Slipping / tripping |
Oil & Water spillage in pumping station, loose sand |
Oil & Filter changing Water & oil mixing spillage in Pumping stations excavation |
Injury/fracture |
H |
E |
3 |
H |
Eng: oil spill contamination pit to control the spill/leakage Admin: working procedure, instruction, PTW, training, competency PPE: slip protection safety shoes |
H |
B |
1 |
L |
Lost time |
S |
D |
3 |
M |
S |
B |
1 |
L |
|||||
Soil contamination |
E |
B |
2 |
M |
E |
A |
1 |
L |
|||||
WND 03 |
Excavation. |
Excavation work for pipe line repairing / modification |
Excavation of pipes |
Injury/fracture |
H |
D |
3 |
M |
Eng.: design and soil type identification, protection method selection Admin: excavation procedure, Work instruction, , training and awareness, PTW PPE: fall protection, head protection, foot protection |
H |
C |
1 |
L |
Lost time |
S |
C |
3 |
M |
S |
B |
1 |
L |
|||||
Particles generation |
E |
C |
2 |
M |
E |
B |
1 |
L |
|||||
WND 04 |
Falling |
Working in water tanks, pipe lines |
Maintenance work / inspection in water tanks and over head pipe lines, pumping station, filling station |
Injury/fracture |
H |
D |
3 |
M |
Eng: fixed Access protected ladders Admin: work instruction, training and awareness, PTW PPE: fall protection |
H |
B |
1 |
L |
Lost time |
S |
B |
3 |
M |
S |
B |
1 |
L |
|||||
non |
E |
E |
|||||||||||
WND 05 |
Flooding |
Pipe burst Tanks over flow Tanks failure |
Valve operating Pipe maintenance |
Death Breathing difficulties Drown |
H |
C |
4 |
H |
Eng. Isolation facilities Admin: Work instruction, safe work practices, training, ERP PPE: water proof uniform, life jacket, gum boots |
H |
C |
1 |
L |
Lost time, tank damage |
S |
B |
4 |
M |
S |
C |
1 |
L |
|||||
Water contamination |
E |
B |
3 |
M |
E |
B |
1 |
L |
|||||
WND 06 |
Toxic gases, Fumes & Vapors |
1-Chlorine 2 Rust 3-Diesel 4-Acid |
MAINTENANCE AND OPERATION ACTIVITIES |
Death, Allergy Breathing difficulties |
H |
C |
4 |
H |
Eng.: Gas detection system, Ventilation System Gas cylinder fixing Admin: work instruction, training, PTW, competency, MSDS, ERP, PPE: respiratory protection |
H |
C |
1 |
L |
Lost time, people, fire |
S |
C |
4 |
H |
S |
B |
1 |
L |
|||||
Gas release |
E |
C |
3 |
M |
E |
B |
1 |
L |
|||||
WND 07 |
Confined space hazard |
Generator room, containers, storms, pipe line, valve chambers, |
Acid Filling Replacement of batteries Diesel filling Leak of gas cylinders and tubes |
Death, Allergy Breathing difficulties |
H |
C |
4 |
H |
Eng: refer to WND 06 Admin: Work instruction, training, ERP, MSDS, confined space procedure, PPE: respiratory protection |
H |
C |
1 |
L |
Lost time, people, gases |
S |
C |
4 |
H |
S |
C |
1 |
L |
|||||
Gas released |
E |
C |
3 |
M |
E |
B |
1 |
L |
|||||
WND 08 |
Caught in between |
1-Pumps 2-Valve chambers |
Inspection, Replacement of fittings& pump parts |
Injury |
H |
C |
3 |
M |
Eng: Safe access, protection cover Admin: work instruction, signs, training, ERP PPE: non loose coverall, |
H |
B |
1 |
L |
Lost time |
S |
C |
2 |
M |
S |
B |
1 |
L |
|||||
NON |
E |
E |
|||||||||||
WND 09 |
Fire |
Hot work, heating, |
Maintenance work in diesel engine, welding works, |
Injury, death |
H |
B |
4 |
M |
Eng: fire fighting system Admin: Work instructions, training, ERP, Hot work Permit, PPE: |
H |
C |
1 |
L |
Lost time, lost equipments assets |
S |
B |
4 |
M |
S |
B |
1 |
L |
|||||
Smoke, gas |
E |
B |
2 |
M |
E |
B |
1 |
L |
|||||
WND 10 |
Lifting Falling objects |
Heavy engine Pipes and pumps Control panels valves , batteries Chlorine cylinders |
Loading /unloading transporting Dismantling and replacement of chlorine cylinders, parts batteries etc. |
Death Injury Fracture |
H |
C |
4 |
H |
Eng: lifting equipment maintenance and inspection Admin: Work instruction and lifting procedure, training, ERP, lifting equipments certifications PPE: hand, head and foot protection |
H |
B |
1 |
L |
Lost Time, equipments |
S |
C |
3 |
M |
S |
B |
1 |
L |
|||||
Gas released |
E |
C |
2 |
M |
E |
B |
1 |
L |
|||||
WND 11 |
Electrical hazards |
High Voltage cables |
Testing and operation of circuit breakers control panels Measuring of parameters Sockets Switchgear |
Death Injury Burn |
H |
C |
3 |
M |
Eng: system protection, fire system Admin: system safety rules, training, PTW, ERP PPE: electrical PPE |
H |
B |
1 |
L |
Lost time, assets |
S |
C |
3 |
M |
S |
A |
1 |
L |
|||||
E |
E |
||||||||||||
WND 12 |
Radiation |
Computer |
Using Computer in Office |
Eye strain |
H |
D |
3 |
M |
Eng: Non radiation monitor Admin: safe working practices, training PPE: screen filter |
H |
C |
1 |
L |
S |
S |
||||||||||||
E |
E |
||||||||||||
WND 13 |
Transportation |
Cars During duty time, fork lifts Cranes, Water tankers |
Driving cars Water tankers Falling in Sea |
Death Major Injury |
H |
C |
4 |
H |
Eng: car/forklift/tankers maintenance Admin: Work instructions, training, PPE: set belts |
H |
B |
1 |
L |
Lost time, people, assets |
S |
C |
3 |
M |
S |
B |
1 |
L |
|||||
E |
C |
3 |
M |
E |
B |
1 |
L |
||||||
WND 14 |
Ergonomics |
Standing long hours, shift working. Office work |
Routine operation |
Body Pain |
H |
E |
2 |
M |
Admin: training and awareness, work instruction |
H |
B |
1 |
L |
S |
S |
||||||||||||
E |
E |
||||||||||||
WND 15 |
Snakes& Dangerous Reptiles |
Inspection of chambers Desert &sand dunes |
During maintenance work for chambers operational issues |
Death poisoning |
H |
C |
3 |
M |
Admin: Inspection, work instruction, training, ERP PPE: hand and foot protection |
H |
B |
1 |
L |
Lost time |
S |
C |
2 |
M |
S |
A |
1 |
L |
|||||
E |
E |
Plan the stakeholder management is the process of developing appropriate strategic to effectively engage throughout the project .The stakeholder management will identify the Desired and current engagement level of stakeholder, the stakeholder communication requirements, information to be distributed and the time frame and frequency of information distribution throughout the project.
Stakeholder |
Unaware |
Neutral |
Supportive |
Leading |
Project manager |
C, D |
|||
Project team |
C.D |
|||
Operation and maintenance Dept. |
C |
D |
||
Supply Dept. |
C.D |
|||
Customer service |
C |
D |
||
Assets Dept. |
C.D |
|||
Project Dept. |
C, D |
|||
HSEQ Dept. |
C |
D |
||
Contractor |
C |
D |
||
Owner |
C |
D |
||
External supplier |
C |
D |
Communication Requirements |
||||
Activities |
Frequency |
From Whom |
To Whom |
Medium |
Project charter |
Once |
Project Manger |
Sponsor |
Hard –soft copy |
Project Plan |
Once |
Project Manger |
Project team – head of the Dept. |
Hard –soft copy |
Drawings |
Once |
Project Manger |
Project team – contractor |
Hard –soft copy |
Quality Assurance Plan |
Once |
Quality manger |
Project team- HSEQ Dept. |
Soft copy |
Communications Plan |
Once |
Project Manger |
Project team |
Soft copy |
Risk Management plan |
Once |
Project Manger |
Project team- HSEQ Dept.- contractor |
Soft copy |
Update Project Planning Checklist |
Weekly |
Project Dept. |
Project Manger |
Soft copy |
Status reports |
Monthly |
Contractor |
Project Manger – head of the Dept. |
Hard –soft copy |
Progress reports |
Monthly |
Contractor |
Project Manger – head of the Dept. |
Hard –soft copy |
In the Project execution process, project manager responsibilities are to direct and manage project, perform quality assurance, develop and manage project team, manage communication, conduct the procurement and finally mange stakeholder engagement. For the above-mentioned responsibilities we mentioned it before in the related knowledge area.
List of deliverable:
In monitoring and controlling process the project manager responsibilities are to monitor and perform integrated changes control, validate and control scope, control schedule, control costs, control quality, control communications, control risk, control procurements and finally control stakeholders engagement. In this part we will focus in control over all project.
Performed to monitor project initiating, planning, executing and closing and is performed from inception to closeout.
The project engineer follow the below techniques to monitor and control the project work.
The intent of the project, as outlined in the project charter dated was an execution of water connection, network relocations and improvements in Eastern Region. The project was done within the budget and time because the project management was based on the PMI standards and practice.
Lesson Learned
Essay Writing Service Features
Our Experience
No matter how complex your assignment is, we can find the right professional for your specific task. Contact Essay is an essay writing company that hires only the smartest minds to help you with your projects. Our expertise allows us to provide students with high-quality academic writing, editing & proofreading services.Free Features
Free revision policy
$10Free bibliography & reference
$8Free title page
$8Free formatting
$8How Our Essay Writing Service Works
First, you will need to complete an order form. It's not difficult but, in case there is anything you find not to be clear, you may always call us so that we can guide you through it. On the order form, you will need to include some basic information concerning your order: subject, topic, number of pages, etc. We also encourage our clients to upload any relevant information or sources that will help.
Complete the order formOnce we have all the information and instructions that we need, we select the most suitable writer for your assignment. While everything seems to be clear, the writer, who has complete knowledge of the subject, may need clarification from you. It is at that point that you would receive a call or email from us.
Writer’s assignmentAs soon as the writer has finished, it will be delivered both to the website and to your email address so that you will not miss it. If your deadline is close at hand, we will place a call to you to make sure that you receive the paper on time.
Completing the order and download