A project has been undertaken in order to prevent leakages of the Tank due to which the 30% of the ULP storage capacity of Western Australia is on a verge of collapse. Furthermore, the organization has been paying $20,000 per month as environmental fines due to the leakage. The condition of the tanks is critical mainly due to its age as the tanks are over 50 years old. Therefore, repairing the tanks is essential in order to prevent the collapse of 30% of the company’s capacity of unleaded petrol. The project budget is represented in the following table (Walker, 2015)-
Task Name |
Cost |
Fuel Tank Repairing |
$774,616.00 |
Project Starts |
$0.00 |
Planning Stage |
$18,528.00 |
Analysing the Requirements |
$4,368.00 |
Schedule Estimation |
$11,040.00 |
Budget and Resource Estimation |
$3,120.00 |
Documenting the Requirements |
$0.00 |
M1: End of Planning and Requirements Gathering |
$0.00 |
Repairing Work Implementation |
$750,760.00 |
Working on Tank 1 |
$231,200.00 |
Fixing the 4 steel patches |
$13,600.00 |
Adding 4 Steel anchor on top of the tank |
$30,000.00 |
Cleaning the outside of Tank |
$3,600.00 |
Repainting the Tank after cleaning |
$184,000.00 |
M2: Completion of Work on Tank 1 |
$0.00 |
Working on tank 2 |
$237,560.00 |
Fixing seven steel patches on the Tank |
$18,280.00 |
Working on the steel anchor |
$31,680.00 |
Cleaning works done |
$3,600.00 |
Repainting the outside of the Tank |
$184,000.00 |
M3: Completion of Work on Tank 2 |
$0.00 |
Working on Tank 3 |
$282,000.00 |
working on six steel patches |
$23,000.00 |
Working on the 4 anchors |
$35,000.00 |
Replacing the supply Valve |
$36,400.00 |
Cleaning the Tank |
$3,600.00 |
Repainting the outside of the Tank |
$184,000.00 |
M4: Completion of Work on Tank 3 |
$0.00 |
Project Completion and Handover |
$5,328.00 |
Checking whether the leakage has been fixed |
$2,208.00 |
Documenting the project work |
$0.00 |
Payment completion |
$1,872.00 |
Resource Release |
$1,248.00 |
Client Sign off |
$0.00 |
Feedback and improvements |
$0.00 |
M5: End of Project |
$0.00 |
Table 1: The prepared budget
(Source: Created by author using MS Project)
An activity based budgeting technique is used to prepare this budget for the project. The cost of materials and the labours are considered while preparing this budget. The main assumptions associated with this budget are as follows (Saadé, Dong & Wan, 2015)-
Repairing, cleaning and repainting all the three tanks are the main objectives of the project. The schedule prepared for implementing the project is represented in the following table (Kim, Kang & Hwang, 2012). The major milestone of the project is marked in red. It is estimated that the project tank will take a minimum of four and half months will be required to implement this project. The project would not have been complex if the site were easily accessible (Kogan et al., 2017).
Task Name |
Duration |
Start |
Finish |
Fuel Tank Repairing |
135 days |
Wed 02-05-18 |
Tue 06-11-18 |
Project Starts |
0 days |
Wed 02-05-18 |
Wed 02-05-18 |
Planning Stage |
23 days |
Wed 02-05-18 |
Fri 01-06-18 |
Analyzing the Requirements |
7 days |
Wed 02-05-18 |
Thu 10-05-18 |
Schedule Estimation |
10 days |
Fri 11-05-18 |
Thu 24-05-18 |
Budget and Resource Estimation |
5 days |
Fri 25-05-18 |
Thu 31-05-18 |
Documenting the Requirements |
1 day |
Fri 01-06-18 |
Fri 01-06-18 |
M1: End of Planning and Requirements Gathering |
0 days |
Fri 01-06-18 |
Fri 01-06-18 |
Repairing Work Implementation |
98 days |
Mon 04-06-18 |
Wed 17-10-18 |
Working on Tank 1 |
31 days |
Mon 04-06-18 |
Mon 16-07-18 |
Fixing the 4 steel patches |
6 days |
Mon 04-06-18 |
Mon 11-06-18 |
Adding 4 Steel anchor on top of the tank |
5 days |
Tue 12-06-18 |
Mon 18-06-18 |
Cleaning the outside of Tank |
10 days |
Tue 19-06-18 |
Mon 02-07-18 |
Repainting the Tank after cleaning |
10 days |
Tue 03-07-18 |
Mon 16-07-18 |
M2: Completion of Work on Tank 1 |
0 days |
Mon 16-07-18 |
Mon 16-07-18 |
Working on tank 2 |
33 days |
Tue 17-07-18 |
Thu 30-08-18 |
Fixing seven steel patches on the Tank |
6 days |
Tue 17-07-18 |
Tue 24-07-18 |
Working on the steel anchor |
6 days |
Wed 25-07-18 |
Wed 01-08-18 |
Cleaning works done |
10 days |
Thu 02-08-18 |
Wed 15-08-18 |
Repainting the outside of the Tank |
10 days |
Thu 16-08-18 |
Wed 29-08-18 |
M3: Completion of Work on Tank 2 |
1 day |
Thu 30-08-18 |
Thu 30-08-18 |
Working on Tank 3 |
35 days |
Thu 30-08-18 |
Wed 17-10-18 |
working on six steel patches |
5 days |
Thu 30-08-18 |
Wed 05-09-18 |
Working on the 4 anchors |
5 days |
Thu 06-09-18 |
Wed 12-09-18 |
Replacing the supply Valve |
5 days |
Thu 13-09-18 |
Wed 19-09-18 |
Cleaning the Tank |
10 days |
Thu 20-09-18 |
Wed 03-10-18 |
Repainting the outside of the Tank |
10 days |
Thu 04-10-18 |
Wed 17-10-18 |
M4: Completion of Work on Tank 3 |
0 days |
Wed 17-10-18 |
Wed 17-10-18 |
Project Completion and Handover |
14 days |
Thu 18-10-18 |
Tue 06-11-18 |
Checking whether the leakage has been fixed |
2 days |
Thu 18-10-18 |
Fri 19-10-18 |
Documenting the project work |
1 day |
Mon 22-10-18 |
Mon 22-10-18 |
Payment completion |
3 days |
Tue 23-10-18 |
Thu 25-10-18 |
Resource Release |
2 days |
Fri 26-10-18 |
Mon 29-10-18 |
Client Sign off |
1 day |
Tue 30-10-18 |
Tue 30-10-18 |
Feedback and improvements |
5 days |
Wed 31-10-18 |
Tue 06-11-18 |
M5: End of Project |
0 days |
Tue 06-11-18 |
Tue 06-11-18 |
Table 2: The Milestone and Project Schedule
The tools used for preparing this project schedule include different scheduling tools such as Gantt chart and Ms Project. A sequential approach is chosen for project implementation and therefore, the schedule has been created following a waterfall approach. Simultaneous working on all the tanks will not be possible due to its limited accessibility and therefore, the chosen method is appropriate for project implementation (Ruël, Bondarouk & Smink, 2012). Furthermore, in order approaches, such as PRINCE2 there is a chance of scope creep which cannot be considered in this project as the project needs to be implemented as soon as possible.
One of the significant merits of waterfall approach is that it helps in implementing a project within the set schedule (Kim, Kang & Hwang, 2012). The use of work break down structure has considerably helped in breaking up of the entire task in smaller executable form. The schedule identified for the project is needed to be followed throughout the project implementation phase in order to successfully implement the project (De Brucker, Macharis & Verbeke, 2013).
Since the repairing works of the tank is particularly complex, it is very necessary to identify the resources required for successful implementation of the project. The resourcing stress points include choice of skilled workers who would be able to work on heights and on the tanks which are difficult to access (Kerzner, 2017). The resources identified for repairing and cleaning the Tanks are as follows-
The resources that will be responsible for performing each task associated with the project that has been identified in the project planning stage is indicated in the following table (Kerzner & Kerzner, 2017)-
Task Name |
Resource Names |
Fuel Tank Repairing |
|
Project Starts |
Project Manager |
Planning Stage |
|
Analyzing the Requirements |
Project Manager |
Schedule Estimation |
Appointing Business Analyst, Project Manager |
Budget and Resource Estimation |
Project Manager |
Documenting the Requirements |
|
M1: End of Planning and Requirements Gathering |
|
Repairing Work Implementation |
|
Working on Tank 1 |
|
Fixing the 4 steel patches |
Steel Patch 2m2[1],Large crane on rent[1],Renting small crane[1] |
Adding 4 Steel anchor on top of the tank |
Steel anchors for Tank 1[1] |
Cleaning the outside of Tank |
Cleaning Staffs appointed, Large crane on rent[1],Renting small crane[1] |
Repainting the Tank after cleaning |
Large crane on rent[1],Paint to be bought[1],Painter chosen, Renting small crane[1] |
M2: Completion of Work on Tank 1 |
|
Working on tank 2 |
|
Fixing seven steel patches on the Tank |
Steel Patch 3m2[1],Workers and laborers, Large crane on rent[1],Renting small crane[1] |
Working on the steel anchor |
Steel anchors for Tank 2[1],Workers and laborers |
Cleaning works done |
Cleaning Staffs appointed, Large crane on rent[1],Renting small crane[1] |
Repainting the outside of the Tank |
Paint to be bought[1],Painter chosen, Large crane on rent[1],Renting small crane[1] |
M3: Completion of Work on Tank 2 |
|
Working on Tank 3 |
|
working on six steel patches |
Steel Patch1.5m2[1],Workers and laborers, Large crane on rent[1],Renting small crane[1] |
Working on the 4 anchors |
Steel anchors for Tank 3[1],Workers and laborers, Large crane on rent[1],Renting small crane[1] |
Replacing the supply Valve |
Tank 3 Supply Valve[1],Workers and laborers |
Cleaning the Tank |
Cleaning Staffs appointed, Large crane on rent[1],Renting small crane[1] |
Repainting the outside of the Tank |
Paint to be bought[1],Painter chosen, Large crane on rent[1],Renting small crane[1] |
M4: Completion of Work on Tank 3 |
|
Project Completion and Handover |
|
Checking whether the leakage has been fixed |
Project Manager ,Appointing Business Analyst |
Documenting the project work |
Archieve |
Payment completion |
Project Manager |
Resource Release |
Project Manager |
Client Sign off |
|
Feedback and improvements |
|
M5: End of Project |
Table 3: The Resources responsible for each task
A standard rate has been assumed for the resources on an hourly basis. The cost of the materials is also considered on basis of standard rates of the materials (Burke, 2013). The table below represents the resources and the rate on which the resources will be paid during the project implementation phase (Tavana, Abtahi & Khalili-Damghani, 2014)-
Resource Name |
Type |
Max. Units |
Std. Rate |
Project Manager |
Work |
100% |
$78.00/hr |
Steel Patch 2m2 |
Material |
$12,000.00 |
|
Steel Patch 3m2 |
Material |
$15,000.00 |
|
Steel Patch1.5m2 |
Material |
$20,000.00 |
|
Steel anchors for Tank 1 |
Material |
$30,000.00 |
|
Steel anchors for Tank 2 |
Material |
$30,000.00 |
|
Steel anchors for Tank 3 |
Material |
$32,000.00 |
|
Tank 3 Supply Valve |
Material |
$35,000.00 |
|
Workers and laborers |
Work |
2,000% |
$35.00/hr |
Paint to be bought |
Material |
$180,000.00 |
|
Cleaning Staffs appointed |
Work |
1,000% |
$25.00/hr |
Painter chosen |
Work |
2,000% |
$30.00/hr |
Archieve |
Cost |
||
Appointing Business Analyst |
Work |
100% |
$60.00/hr |
Large crane on rent |
Material |
$1,000.00 |
|
Renting small crane |
Material |
$600.00 |
Table 4: Representing the details of the Resources identified
One of the major complexities associated with this project is the accessibility of the tanks. Therefore, skilled workers are needed who will be able to work in the site which is triangular in shape and accessible only from one side. Hence the choice of skilled workers is a major stress point associated with the project.
For proper resource identification, it is essential to develop a proper project plan as the budget of the project is determined according to the tasks required to be performed for successful project implementation. Easy availability of the materials needed for implementation of the project is another major resources stress point associated with the project.
References
Burke, R., 2013. Project management: planning and control techniques. New Jersey, USA.
De Brucker, K., Macharis, C., & Verbeke, A. 2013. Multi-criteria analysis and the resolution of sustainable development dilemmas: A stakeholder management approach. European journal of operational research, 224(1), 122-131.
Kerzner, H. 2017. Project management metrics, KPIs, and dashboards: a guide to measuring and monitoring project performance. John Wiley & Sons.
Kerzner, H., & Kerzner, H. R. 2017. Project management: a systems approach to planning, scheduling, and controlling. John Wiley & Sons.
Khodakarami, V., & Abdi, A. 2014. Project cost risk analysis: A Bayesian networks approach for modeling dependencies between cost items. International Journal of Project Management, 32(7), 1233-1245.
Kim, J., Kang, C., & Hwang, I. 2012. A practical approach to project scheduling: considering the potential quality loss cost in the time–cost tradeoff problem. International Journal of Project Management, 30(2), 264-272.
Kogan, L., Papanikolaou, D., Seru, A. and Stoffman, N., 2017. Technological innovation, resource allocation, and growth. The Quarterly Journal of Economics, 132(2), pp.665-712.
Larson, E.W. and Gray, C., 2013. Project Management: The Managerial Process with MS Project. McGraw-Hill.
Maravas, A., & Pantouvakis, J. P. 2012. Project cash flow analysis in the presence of uncertainty in activity duration and cost. International journal of project management, 30(3), 374-384.
Ruël, H. J., Bondarouk, T., &Smink, S. 2012. The Waterfall Approach and Requirement Uncertainty: An In-Depth Case Study of an. Project Management Techniques and Innovations in Information Technology, 49.
Saadé, R. G., Dong, H., & Wan, J. 2015. Factors of project manager success. Interdisciplinary Journal of Information, Knowledge, and Management, 10, 63-80.
Tavana, M., Abtahi, A. R., & Khalili-Damghani, K. 2014. A new multi-objective multi-mode model for solving preemptive time–cost–quality trade-off project scheduling problems. Expert Systems with Applications, 41(4), 1830-1846.
Walker, A. 2015. Project management in construction. John Wiley & Sons.
Essay Writing Service Features
Our Experience
No matter how complex your assignment is, we can find the right professional for your specific task. Contact Essay is an essay writing company that hires only the smartest minds to help you with your projects. Our expertise allows us to provide students with high-quality academic writing, editing & proofreading services.Free Features
Free revision policy
$10Free bibliography & reference
$8Free title page
$8Free formatting
$8How Our Essay Writing Service Works
First, you will need to complete an order form. It's not difficult but, in case there is anything you find not to be clear, you may always call us so that we can guide you through it. On the order form, you will need to include some basic information concerning your order: subject, topic, number of pages, etc. We also encourage our clients to upload any relevant information or sources that will help.
Complete the order formOnce we have all the information and instructions that we need, we select the most suitable writer for your assignment. While everything seems to be clear, the writer, who has complete knowledge of the subject, may need clarification from you. It is at that point that you would receive a call or email from us.
Writer’s assignmentAs soon as the writer has finished, it will be delivered both to the website and to your email address so that you will not miss it. If your deadline is close at hand, we will place a call to you to make sure that you receive the paper on time.
Completing the order and download