CPB Contractors will carry out the shed construction project. The CPB Contractors will have to follow the project plan strictly. They may fail to stick with the project deliverables. This limitation can create many problems. The project manager can face several challenges to complete the project within scheduled deadline and budget.
CPB Contractors has certain norms and strategy. The construction team will follow those norms while constructing the shed. The project manager may find it challenging to align the project strategy with CPB Contractors’ strategy. There is a risk that the project can go out of track.
The project plan has already been prepared, however, in reality, the project manager can observe that the project is over budget or running behind schedule. It will be a great challenge for the project manager to change the plan and prepare a revised plan so that it can cope with the scheduled timeframe and budget.
The project manager will have to rely on CPB Contractors for the resources and the project quality. CPB Contractors will allocate resources and workforce for constructing the shed. However, there will be no scope for the project manager to check the resources quality and the workforce skills. The project manager can only acknowledge the issue if any disruptions occur within the project. The project manager will have to depend on CPB Contractors for receiving a quality project constantly.
The project manager will have to follow a certain methodology like Agile or Waterfall for the project, and he will have to stick with it. He cannot change the methodology and cannot choose random methodology. Otherwise, that can lead to a disaster. On the other hand, by choosing a unique methodology for the project, the project manager limits the potential of the project and the resources.
CPB Construction Team will consist of civil engineer, wood machinist, mason, builder, subcontractor, painter and the cleaning staff. They will carry out the minor demolition and the construction of the shed. The project manager is in charge of the construction team. The content writer will prepare documentations for the project. The 94WBR-shed project sponsor will provide fund for the project.
Demolition-Construction 94WBR-Shed Project Plan
Task Name |
Duration |
Start |
Finish |
Predecessors |
Resource Names |
Cost |
94WBR-Shed Project by CPB Contractors |
143 days |
Mon 16/04/18 |
Wed 31/10/18 |
$30,120.00 |
||
Resource Allocation for 94WBR-Shed Demolition-Construction Project |
5 days |
Mon 16/04/18 |
Fri 20/04/18 |
Project Manager |
$1,000.00 |
|
Demolition Works in Backyard |
11 days |
Mon 23/04/18 |
Mon 07/05/18 |
$3,008.00 |
||
Cutting Down Trees Using Electric Chainsaws |
4 days |
Mon 23/04/18 |
Thu 26/04/18 |
1 |
Wood Machinist |
$640.00 |
Removing Section of Backyard Boundary Wall Using 341 high reach demolition excavator |
4 days |
Fri 27/04/18 |
Wed 02/05/18 |
3 |
Builder |
$576.00 |
Cutting Small Plants and Grass |
5 days |
Fri 27/04/18 |
Thu 03/05/18 |
3 |
Cleaning Staff,Subcontractor |
$1,280.00 |
Clearance of Backyard Lot |
2 days |
Fri 04/05/18 |
Mon 07/05/18 |
3,4,5 |
Cleaning Staff,Subcontractor |
$512.00 |
Construction Works |
122 days |
Tue 08/05/18 |
Wed 24/10/18 |
$25,392.00 |
||
Site Work Step 1 |
2 days |
Tue 08/05/18 |
Wed 09/05/18 |
$320.00 |
||
Using Wooden Frame to Mark the Boundary of Shed |
2 days |
Tue 08/05/18 |
Wed 09/05/18 |
6 |
Subcontractor |
$320.00 |
Site Work Step 2 |
8 days |
Thu 10/05/18 |
Mon 21/05/18 |
$1,152.00 |
||
Digging Hole For First Block |
2 days |
Thu 10/05/18 |
Fri 11/05/18 |
9 |
Mason |
$288.00 |
Gravel Adding |
3 days |
Mon 14/05/18 |
Wed 16/05/18 |
11 |
Builder |
$432.00 |
Installation of Block |
3 days |
Thu 17/05/18 |
Mon 21/05/18 |
12 |
Builder |
$432.00 |
Site Work Step 3 |
3 days |
Tue 22/05/18 |
Thu 24/05/18 |
$1,008.00 |
||
Using a Level to Check Whether Corner Blocks are Implemented at the Same Height |
3 days |
Tue 22/05/18 |
Thu 24/05/18 |
13 |
Civil Engineer,Subcontractor |
$1,008.00 |
Building the Floor Step 1 |
11 days |
Fri 25/05/18 |
Fri 08/06/18 |
$1,584.00 |
||
Marking Joist Locations on Long Front Joists |
3 days |
Fri 25/05/18 |
Tue 29/05/18 |
15 |
Builder |
$432.00 |
Marking Joist Locations on Rear Rim Joists |
4 days |
Wed 30/05/18 |
Mon 04/06/18 |
17 |
Builder |
$576.00 |
Metal Hangers Installation with Joist Hanger Nails |
4 days |
Tue 05/06/18 |
Fri 08/06/18 |
18 |
Builder |
$576.00 |
Building The Floor Step 2 |
7 days |
Mon 11/06/18 |
Tue 19/06/18 |
$1,648.00 |
||
Doubling Front Joists and Rear Joists |
3 days |
Mon 11/06/18 |
Wed 13/06/18 |
19 |
Builder |
$432.00 |
Adding Plywood Floor |
4 days |
Thu 14/06/18 |
Tue 19/06/18 |
21 |
Builder,Wood Machinist |
$1,216.00 |
Wall Construction |
22 days |
Wed 20/06/18 |
Thu 19/07/18 |
$4,752.00 |
||
Cut Stock to Length for Window and Door Jack Studs and Wall Studs |
5 days |
Wed 20/06/18 |
Tue 26/06/18 |
22 |
Wood Machinist |
$800.00 |
Installation of Plywood Wall Sheathing on Framed Back Wall |
4 days |
Wed 27/06/18 |
Mon 02/07/18 |
24 |
Wood Machinist |
$640.00 |
Assembly Raised |
4 days |
Tue 03/07/18 |
Fri 06/07/18 |
25 |
Builder,Wood Machinist |
$1,216.00 |
Framing and Raising Remaining Walls Without Sheathing |
4 days |
Mon 09/07/18 |
Thu 12/07/18 |
26 |
Builder |
$576.00 |
Adding Remaining Plywood Sheathing while Framing is in Place and Assembly is Plumb and Square |
5 days |
Fri 13/07/18 |
Thu 19/07/18 |
27 |
Builder,Wood Machinist |
$1,520.00 |
Framing Roof |
24 days |
Fri 20/07/18 |
Wed 22/08/18 |
$5,296.00 |
||
Setting Up Worktable with Outline of Rafter Assembly Marked |
5 days |
Fri 20/07/18 |
Thu 26/07/18 |
28 |
Builder,Wood Machinist |
$1,520.00 |
Joining Rafter Pairs with Plywood Gusset |
6 days |
Fri 27/07/18 |
Fri 03/08/18 |
30 |
Builder,Wood Machinist |
$1,824.00 |
Installation of Plywood Roof Deck |
5 days |
Mon 06/08/18 |
Fri 10/08/18 |
31 |
Wood Machinist |
$800.00 |
Nailing Aluminium Drip Edge to Eaves |
4 days |
Mon 13/08/18 |
Thu 16/08/18 |
32 |
Builder |
$576.00 |
Installation of Drip Edge along Rake Edges |
4 days |
Fri 17/08/18 |
Wed 22/08/18 |
33 |
Builder |
$576.00 |
Roofing and Siding |
21 days |
Thu 23/08/18 |
Thu 20/09/18 |
$3,360.00 |
||
Using Plywood for Roof Deck |
5 days |
Thu 23/08/18 |
Wed 29/08/18 |
34 |
Wood Machinist |
$800.00 |
Covering Roof Deck with Roofing Felt |
5 days |
Thu 30/08/18 |
Wed 05/09/18 |
36 |
Wood Machinist |
$800.00 |
Installation of Shingles |
6 days |
Thu 06/09/18 |
Thu 13/09/18 |
37 |
Wood Machinist |
$960.00 |
Nail Tongue-and-grove Cedar Siding in Place |
5 days |
Fri 14/09/18 |
Thu 20/09/18 |
38 |
Wood Machinist |
$800.00 |
Installation of Doors |
22 days |
Fri 21/09/18 |
Mon 22/10/18 |
$3,824.00 |
||
Cutting Stock for Doorjambs |
6 days |
Fri 21/09/18 |
Fri 28/09/18 |
39 |
Wood Machinist |
$960.00 |
Positioning the Door in its opening at the Top and Sides |
5 days |
Mon 01/10/18 |
Fri 05/10/18 |
41 |
Wood Machinist |
$800.00 |
Bore Pilot Holes for Hinge Screws |
4 days |
Mon 08/10/18 |
Thu 11/10/18 |
42 |
Builder |
$576.00 |
Installation of Door Pull and Hasp |
4 days |
Fri 12/10/18 |
Wed 17/10/18 |
43 |
Builder |
$576.00 |
Securing Hinges |
3 days |
Thu 18/10/18 |
Mon 22/10/18 |
44 |
Builder,Subcontractor |
$912.00 |
Installation of Windows |
9 days |
Fri 21/09/18 |
Wed 03/10/18 |
$1,776.00 |
||
Installation of Angled Still Piece |
3 days |
Fri 21/09/18 |
Tue 25/09/18 |
39 |
Builder,Wood Machinist |
$912.00 |
Installation of Top Jamb |
3 days |
Wed 26/09/18 |
Fri 28/09/18 |
47 |
Builder |
$432.00 |
Installation of Side Jambs |
3 days |
Mon 01/10/18 |
Wed 03/10/18 |
48 |
Builder |
$432.00 |
Painting |
4 days |
Thu 18/10/18 |
Tue 23/10/18 |
$576.00 |
||
Painting of Shed Walls |
2 days |
Thu 18/10/18 |
Fri 19/10/18 |
44,48 |
Painter and Decorator |
$288.00 |
Painting of Doors and Windows |
2 days |
Mon 22/10/18 |
Tue 23/10/18 |
51 |
Painter and Decorator |
$288.00 |
Cleaning |
1 day |
Wed 24/10/18 |
Wed 24/10/18 |
$96.00 |
||
Final Cleaning |
1 day |
Wed 24/10/18 |
Wed 24/10/18 |
52 |
Cleaning Staff |
$96.00 |
Project Closure |
5 days |
Thu 25/10/18 |
Wed 31/10/18 |
$720.00 |
||
Project Handover |
2 days |
Thu 25/10/18 |
Fri 26/10/18 |
54 |
Project Manager |
$400.00 |
94WBR-Shed Project Sponsor Agreement |
2 days |
Mon 29/10/18 |
Tue 30/10/18 |
56 |
94WBR-Shed Project Sponsor |
$0.00 |
Documentation |
1 day |
Wed 31/10/18 |
Wed 31/10/18 |
57 |
Content Writer |
$120.00 |
Resource Release |
1 day |
Wed 31/10/18 |
Wed 31/10/18 |
57 |
Project Manager |
$200.00 |
Draft Version of 94WBR-Shed Project Management Plan
Background A Project manager has been appointed in charge of a construction project team who are currently working at 94 Western Beach Road in Geelong, Victoria 3220. CPB Contractors team will carry out the demolition-construction work for the 94WBR-shed project. Minor demolition work will be conducted in the backyard, and afterwards, the construction of shed will start. The Project Manager has been given the responsibility. He will prepare the project plan. The project plan will contain the list of project activities that need to be carried out. The project plan will explain the project dependencies. The project will illustrate the project schedule as well as the project budget. The CPB Contractors will follow the plan and will complete the project accordingly. Objectives · To construct a shed · To finish the 94WBR-shed project within scheduled deadline and budget · To maintain efficiency and sustainability throughout the project lifecycle that is why the project manager has been appointed Scope Key Stakeholders
Project Milestones
Project Budget
Approval Signatures
|
References
Dumbili, E.W., 2015. ‘What a man can do, a woman can do better’: gendered alcohol consumption and (de) construction of social identity among young Nigerians. BMC public health, 15(1), p.167.
Fellows, R.F. and Liu, A.M., 2015. Research methods for construction. John Wiley & Sons.
Forsythe, P.J., 2015. Rethinking Industrial Shed Construction-Consider Timber.
Hughes, W., Champion, R. and Murdoch, J., 2015. Construction contracts: law and management. Routledge.
Jardine, L., 2015. Erasmus, man of letters: the construction of charisma in print. Princeton University Press.
Jenkins, P., 2017. Using murder: The social construction of serial homicide. Routledge.
Kim, S.H. and Choi, J.S., 2015. A Study on the Design Concepts and Main Construction Processes of the Coal Shed at Thermal Power Plant. Journal of the Korea Academia-Industrial cooperation Society, 16(5), pp.3619-3626.
Lou, X., Zhou, Y., Yang, J. and Chen, Z., 2014. Study on the Calculation Method of Light Shed on Rockfall Impact Protection. Advanced Materials Research.
McNally, L., 2016. A semantics for the English existential construction. Routledge.
Qin, Z., Zhou, Z., Li, H., Lin, J., Tang, Y., Gu, H., Yang, J., Huan, H., Zhang, X. and Yu, G., 2014. Design and Construction of Removable Deep-Litter Breeding Shed. Agricultural Science & Technology, 15(12), p.2240.
Tomkins, M.D., Huck, J.J., Dortch, J.M., Hughes, P.D., Kirbride, M.P. and Barr, I.D., 2018. Schmidt Hammer exposure dating (SHED): Calibration procedures, new exposure age data and an online calculator. Quaternary Geochronology, 44, pp.55-62.
Yafeng, C., Fuyong, H., Shihua, Z., Cheng, W., Feng, W. and Yishi, Y., 2016, September. Study on natural pollution accumulating characteristics of cap and pin suspension ceramic insulator with composite shed of DC 500kV transmission line in central China. In High Voltage Engineering and Application (ICHVE), 2016 IEEE International Conference on (pp. 1-4). IEEE.
Essay Writing Service Features
Our Experience
No matter how complex your assignment is, we can find the right professional for your specific task. Contact Essay is an essay writing company that hires only the smartest minds to help you with your projects. Our expertise allows us to provide students with high-quality academic writing, editing & proofreading services.Free Features
Free revision policy
$10Free bibliography & reference
$8Free title page
$8Free formatting
$8How Our Essay Writing Service Works
First, you will need to complete an order form. It's not difficult but, in case there is anything you find not to be clear, you may always call us so that we can guide you through it. On the order form, you will need to include some basic information concerning your order: subject, topic, number of pages, etc. We also encourage our clients to upload any relevant information or sources that will help.
Complete the order formOnce we have all the information and instructions that we need, we select the most suitable writer for your assignment. While everything seems to be clear, the writer, who has complete knowledge of the subject, may need clarification from you. It is at that point that you would receive a call or email from us.
Writer’s assignmentAs soon as the writer has finished, it will be delivered both to the website and to your email address so that you will not miss it. If your deadline is close at hand, we will place a call to you to make sure that you receive the paper on time.
Completing the order and download