The goals of the ‘Formation of IOT based Healthcare Mobile Application’ project are,
Formation of Mobile Application: The mobile application was developed for easing the functions of the organization. The ‘Formation of IOT based Healthcare Mobile Application’ project would result in forming the mobile application supporting the healthcare facilities to the patients and doctors.
Support for Improvement of the functions: The existing functions was improved using the technology innovation and faster delivery of the services. The improvement of the technology for easing the supportive functions was a major benefit from the organization.
Completion of the project: The successful completion of the project was based on the support and formation implying the IT formation functions. The improvement of the project was based on the simplification of the functions so that the mobile application was developed in the estimated time and budget.
The project of ‘Formation of IOT based Healthcare Mobile Application’ is developed aligning the simplification of the functions. The project was based on the use of the IT project formation. The IT project management principles were executed for forming the mobile application. The mobile application was developed for easing the functions of the organization. The improvement of the technology for easing the supportive functions was a major benefit from the organization.
Project Functions
The project of ‘Formation of IOT based Healthcare Mobile Application’ is developed for easing the formation and formation of the functions favourable for the formation and installation of the healthcare application was helpful for easing the simplification of the factors defining the processes of the functions. The support and formation using the formation of effective and smart improvement methods was successively deployed using specific work packages. The following diagram would show the work packages required for the execution of the project,
The project functions was divided into the five phases of initial phase, planning phase, design phase, execution phase, and closure phase. These phases was completed successfully for developing the final project execution. The explanation of the phases is shown below,
Initial Phase: The initial phase of the project was based on the initialization of the project functions and defining of the successful formation. The initial phase would comprise of identification of requirements, making list of resources required, accumulation of resources, charter documentation, and kick off. In this phase the functions of the project was initiated by the use of the resource identification and the formation of the initiation documents.
Plan Formation Phase: The planning phase would comprise of developing the successful activity scheduling and forming the simplification of the project functions. The plan formation was implied for easing the utilization of the formation process. It would include outline of the plan, review of plan, complete plan formation, and plan approval. The plan formation phase was formed for easing the simplification of the functions defining the support and formation management.
Design Phase: The design phase would involve the formation of the effective design and formation of the successful utilization process. The design of the application was designed in this phase making is suitable to develop the IOT based healthcare mobile application as the final deliverable. The design phase would include the following functions interface design is developed, complete design is formed, design simulation, and design approved.
Execution: The execution phase is developed forming the improvement of the improved operation formation for ensuring that the project would result in forming the completion of the IOT based healthcare mobile application. The phase would involve the functions of interface is formed, functions are aligned, programming is done, functions are defined, system is developed, and system approved.
Closure: The closure is the final phase of the project and it would involve the functions of the final documents are made, inspection of the system, sign off, and project closed. It is the end point of the project functions.
Skills Required
The skills required for the project functions are given below,
Project Members |
Skills |
Analyst |
Deep analysis, Use of information, analytical |
Project Manager |
Management of the functions, leadership, effective communication, |
Documenter |
Writing, Documenting |
Planner |
Planning tools, activity recognition, |
Designer |
Designing capability, skills |
Tester |
Testing, |
Engineer |
Skills, Knowledge, and communicator |
Programmer |
Programming, Communication |
Anticipated Outcomes
The anticipated outcomes of the ‘Formation of IOT based Healthcare Mobile Application project are,
The probable features of the Formation of IOT based Healthcare Mobile Application are given below,
Patient Records: the application would serve the purpose of keeping the records of the patients so that it can be accessed easily in time of need.
Doctor Records: the application would serve the purpose of keeping the records of the doctors so that it can be accessed easily in time of need.
Staff Records: the application would serve the purpose of keeping the records of the staffs so that it can be accessed easily in time of need.
Payment Information: The payment information by the patients can be stored in the application so that the doctors and patients would get the access to the payment records easily.
Wireless Connectivity: The wireless connectivity would allow the benefit of accessing the information from any place and at any time.
Doctor Feedback: The feedback by the doctors would help in keeping track of the patients health condition or any specific advice.
Required Resources
The project of ‘Formation of IOT based Healthcare Mobile Application’ is formed supporting the improvement of the effective and improved formation process. The improvement of the successive management of the processes was applied for easing the successful formation of the application. Various resources were required for the improvement of the functions. The utilization of the resources is given below,
Resource Name |
Type |
Work/Units |
Standard Rate |
Cost |
Analyst |
Human |
24 |
$85.00 |
$2,040.00 |
Project Manager |
Human |
56 |
$150.00 |
$8,400.00 |
Documenter |
Human |
40 |
$90.00 |
$3,600.00 |
Planner |
Human |
48 |
$95.00 |
$4,560.00 |
Designer |
Human |
72 |
$110.00 |
$7,920.00 |
Tester |
Human |
40 |
$100.00 |
$4,000.00 |
Engineer |
Human |
72 |
$140.00 |
$10,080.00 |
Programmer |
Human |
72 |
$125.00 |
$9,000.00 |
Documents |
Material |
2 |
$100.00 |
$200.00 |
Design Tools |
Material |
2 |
$900.00 |
$1,800.00 |
System |
Material |
1 |
$1,500.00 |
$1,500.00 |
Program Software |
Material |
1 |
$1,000.00 |
$1,000.00 |
Testing Tools |
Material |
2 |
$450.00 |
$900.00 |
Total Budget |
$55,000.00 |
The project was successfully implied with the help of easing the formation of the effective resources accumulated for defining the formation. The project resources comprised of both human and material resources defining the successful formation of the functions. The analysis of the functions was successfully formed for easing the formation of the improved formation. The following is the time phased diagram,
Possible Limitations
The possible limitations of the project are,
Anticipated Timeline
The project of ‘Formation of IOT based Healthcare Mobile Application’ is developed forming the improvement of the effective and smart inclusion of the processing. The project schedule is shown below,
WBS |
Task Name |
Duration |
Start |
Finish |
0 |
Formation of IOT based Healthcare Mobile Application |
53 days |
Wed 8/1/18 |
Fri 10/12/18 |
1 |
Initial Phase |
9 days |
Wed 8/1/18 |
Mon 8/13/18 |
1.1 |
Identification of requirements |
2 days |
Wed 8/1/18 |
Thu 8/2/18 |
1.2 |
Making List of resources required |
1 day |
Fri 8/3/18 |
Fri 8/3/18 |
1.3 |
Accumulation of resources |
4 days |
Mon 8/6/18 |
Thu 8/9/18 |
1.4 |
Charter Documentation |
2 days |
Fri 8/10/18 |
Mon 8/13/18 |
1.5 |
Kick off |
0 days |
Mon 8/13/18 |
Mon 8/13/18 |
2 |
Planning Phase |
8 days |
Tue 8/14/18 |
Thu 8/23/18 |
2.1 |
Outline of the Plan |
1 day |
Tue 8/14/18 |
Tue 8/14/18 |
2.2 |
Review of Plan |
2 days |
Wed 8/15/18 |
Thu 8/16/18 |
2.3 |
Complete Plan Formation |
5 days |
Fri 8/17/18 |
Thu 8/23/18 |
2.4 |
Plan Approval |
0 days |
Thu 8/23/18 |
Thu 8/23/18 |
3 |
Design Phase |
12 days |
Fri 8/24/18 |
Mon 9/10/18 |
3.1 |
Interface Design is developed |
2 days |
Fri 8/24/18 |
Mon 8/27/18 |
3.2 |
Complete Design is formed |
7 days |
Tue 8/28/18 |
Wed 9/5/18 |
3.3 |
Design Simulation |
3 days |
Thu 9/6/18 |
Mon 9/10/18 |
3.4 |
Design Approved |
0 days |
Mon 9/10/18 |
Mon 9/10/18 |
4 |
Execution |
18 days |
Tue 9/11/18 |
Thu 10/4/18 |
4.1 |
Interface is formed |
2 days |
Tue 9/11/18 |
Wed 9/12/18 |
4.2 |
Functions are aligned |
3 days |
Thu 9/13/18 |
Mon 9/17/18 |
4.3 |
Programming is done |
6 days |
Tue 9/18/18 |
Tue 9/25/18 |
4.4 |
Functions are defined |
3 days |
Wed 9/26/18 |
Fri 9/28/18 |
4.5 |
System is developed |
4 days |
Mon 10/1/18 |
Thu 10/4/18 |
4.6 |
System Approved |
0 days |
Thu 10/4/18 |
Thu 10/4/18 |
5 |
Closure |
6 days |
Fri 10/5/18 |
Fri 10/12/18 |
5.1 |
Final documents are made |
3 days |
Fri 10/5/18 |
Tue 10/9/18 |
5.2 |
Inspection of the system |
2 days |
Wed 10/10/18 |
Thu 10/11/18 |
5.3 |
Sign off |
1 day |
Fri 10/12/18 |
Fri 10/12/18 |
5.4 |
Project Closed |
0 days |
Fri 10/12/18 |
Fri 10/12/18 |
The project schedule has been developed using the Ms-Project software for aligning the simplification of the improved communication and formation. The complete project can be shown in the following Gantt chart diagram,
The anticipated issues of the project would include the data being misused, hacking issues, and improvement/compatibility issues.
Statement of Ownership
The IOT based mobile application was the copyright issue of the developer and investing company/organization that cannot be used for personal or profitable works.
Dhar, S., & Bose, I. (2015, December). Framework for Using New Age Technology to Increase Effectiveness of Project Communication for Outsourced IT Projects Executed from Offshore. In Workshop on E-Business (pp. 207-211). Springer, Cham.
Fleming, Q. W., & Koppelman, J. M. (2016, December). Earned value project management. Project Management Institute.
Harrison, F., & Lock, D. (2017). Advanced project management: a structured approach. Routledge.
Heagney, J. (2016). Fundamentals of project management. Amacom.
Kerzner, H., & Kerzner, H. R. (2017). Project management: a systems approach to planning, scheduling, and controlling. John Wiley & Sons.
Larson, E. W., Gray, C. F., Danlin, U., Honig, B., & Bacarini, D. (2014). Project management: The managerial process (Vol. 6). Grandview Heights, OH: McGraw-Hill Education.
Lee, H. K., Keil, M., Smith, H. J., & Sarkar, S. (2017). The roles of mood and conscientiousness in reporting of self?committed errors on IT projects. Information Systems Journal, 27(5), 589-617.
Marchewka, J. T. (2014). Information technology project management. John Wiley & Sons.
Meredith, J. R., Mantel, S. J., Shafer, S. M., & Sutton, M. M. (2014). Project management in practice. Wiley.
Mir, F. A., & Pinnington, A. H. (2014). Exploring the value of project management: linking project management performance and project success. International journal of project management, 32(2), 202-217.
Nicholas, J. M., & Steyn, H. (2017). Project management for engineering, business and technology. Routledge.
Rodríguez, A., Ortega, F., & Concepción, R. (2016). A method for the evaluation of risk in IT projects. Expert Systems with Applications, 45, 273-285.
Schönberger, M., & ?irjevskis, A. (2017). Successful IT/IS Projects in Healthcare: Evaluation of Critical Success Factors.
Essay Writing Service Features
Our Experience
No matter how complex your assignment is, we can find the right professional for your specific task. Contact Essay is an essay writing company that hires only the smartest minds to help you with your projects. Our expertise allows us to provide students with high-quality academic writing, editing & proofreading services.Free Features
Free revision policy
$10Free bibliography & reference
$8Free title page
$8Free formatting
$8How Our Essay Writing Service Works
First, you will need to complete an order form. It's not difficult but, in case there is anything you find not to be clear, you may always call us so that we can guide you through it. On the order form, you will need to include some basic information concerning your order: subject, topic, number of pages, etc. We also encourage our clients to upload any relevant information or sources that will help.
Complete the order formOnce we have all the information and instructions that we need, we select the most suitable writer for your assignment. While everything seems to be clear, the writer, who has complete knowledge of the subject, may need clarification from you. It is at that point that you would receive a call or email from us.
Writer’s assignmentAs soon as the writer has finished, it will be delivered both to the website and to your email address so that you will not miss it. If your deadline is close at hand, we will place a call to you to make sure that you receive the paper on time.
Completing the order and download