Sub Sea Adventures is a local scuba diving program organization that has three shops. The three shops are located in Portsea, Queenscliff and Phillip Island. These shops usually serve as the booking points for the various services provided by the organization but this is not an efficient method because of the errors associated with double booking as well student tracking errors. All this leads to a redundancy in the provision of services by the organization which lead to poor customer relations as well as profitability issues.
Besides providing training programs and classes to the students, the organization has a fleet of six boats that are used in excursion as well as tours. Students and divers are common customers but the booking is one of the major bottlenecks of the organosation.Regardless, there is a certified diver who ensures the safety as well as the training is managed in an efficient manner. Furthermore, the three shops are points from where customers can purchase scuba equipment. All these are some of the factors that require the implementation of an electronic system and as such, the proper call for training as well as the management of such a system.
Sub Sea adventures is upgrading to an electronic system from the manual one. The upgrade is aimed at increasing the efficiency of the organization as well as decrease the errors that are associated with the manual systems. However, the employees as well as the customers are not well conversant with the automatic system and as such, need to be trained and provided with the necessary knowledge regarding the use of such a system.
The project is aimed at ensuring that the electronic system can be used by all the 40 sales members across the three stores and the founder, Shane. Furthermore, the electronic system will be integrated with the organizational website so that the tours as well as the training can be provided online. All these are some of the aspects that will be considered in this project initiation document with the emphasis on the training that may be required to ensure that the staff as well as the customers are in a good position to use the system. The process will be divided into 25 tasks with milestones and deliverables observed throughout the whole process.
The objectives of the project are:
The upgrade of the system plays a fundamental role in stakeholder management. There are three stakeholders in this project; VUISC, the customers and the management body. The management considers all the 40 staff working across the three stores as well as the founder of the organization while the customers are the students and divers who seek training as well as tour services.
The manual system has been ineffective on management and has led to losses when the number is not good enough for tours as well as training. Furthermore, this system has led to a loss in customer confidence because of double booking. Double booking means that one of the customers does not get a spot on the boat and this has the effect of reducing the number that books. Therefore, all these lead to losses on the organizational part. However, the electronic system will bypass all these flaws and ensure that the number of people booking is sufficient and there is no double booking. In effect, there will be an increase in customer base which will increase the profitability.
As indicated prior, the whole training process will be divided into 25 tasks with milestones in between the start and the finish. However, the project will have to be in line with the deliverables as well as the objectives of the project (Project management Institute, 2013). One of the methodologies that may be used in ensuring that the scope as well as the project objectives are attained within the proper timeframe is the agile methodology. Agile methodology was developed in the software industry and as such, it is very flexible (Westland, 2017).The methodology, however, will be focused on ensuring that the resources of the project are properly used with the main aim at keeping them at a minimal and the project will be completed within the timeframe allocated.
The first phase is the planning phase. In this, the various stakeholders come to a consensus on the best approach to be used in delivering the project objectives (Eskerod & Huemann, 2013). Consultations as well as the delivery of the relevant personnel and equipment will be organized in this stage. The total number of people to be trained will be noted which will determine the number of personnel and equipment required.
The second phase is the execution phase (Buehring, 2018). All the training that is relevant for the company will be conducted at this point. The customers as well as the management of the organization will be provided on the skills and knowledge necessary to navigate them through the daily use of the electronic system.It will be the most intense phase of the project and as such, collaboration will be necessary in this phase
Finally, there is the closure phase of the project (Aramo-Immonen & Vanharanta, 2009). When all the necessary knowledge and training has been provided to the customers as well as the staff, it is important to note any challenges as well as answer questions regarding the trainng.Furthermore, Sub Sea Adventures may require the implementation of other systems and programs.
The three phases of the training schedule will be used in the development of the program schedule.by using the Microsoft project 2010 software, the following program schedule will be developed.
Task |
Duration in days |
Consultation with the stakeholders |
3 |
certification |
2 |
Determination of program requirements |
7 |
Project scope and deliverables |
5 |
Review of implementation strategies |
4 |
Sign off with the stakeholders |
2 |
Risk analysis and contingency management |
7 |
Budget and schedule preparation |
7 |
Review of the training program |
5 |
Analysis of customer study and training plan |
4 |
Analysis of management study and plan requirements |
5 |
Purchase of the equipment such as laptops |
14 |
Assembly of the workforce as well as equipment |
14 |
System introduction and interface management |
7 |
Program coding requirements |
7 |
Diagnostics and program analysis |
7 |
Analysis of the project specific requirements |
5 |
Extra tutor program analysis |
6 |
Assessment of training outcomes |
14 |
Analysis of training outcomes |
7 |
Feedback response and analysis |
5 |
Response implementation |
3 |
Sign off with the stakeholders |
5 |
Preparation of project documentation |
7 |
However, considering that the upgrade of the system should start on June 2nd, the training should be provided as early as possible so as to ensure that all the staff and the customers are well conversant with the requirements prior to the actual implementarion.This will require an early start and provide a window ( Kerzner & kerzner, 2017) through which the system may be implemented as effectively as possible.
The following screenshots from Microsoft project demonstrate the schedule of the training program and have indicated the various milestones that mark the rate of progress of training.
The critical path is the path through which critical activities attain the project deliverables and it has the effect of affecting the overall time required for project completion (Filwv, 2017). There are two types of activities that are involved in project management: float and critical activities. Float activities which have no effect on the overall completion time and as such, may rescheduled to other dates in case there is a shortcoming in the project scope and resource allocation.However,reschedule of critical activities lead to a delay in the overall completion time and this leads to a wastage of resources as well as money (Aaltonen, 2011).
Microsoft project has been used extensively in the determination of the critical path and provides a platform through which project managers can easily monitor the progress of the project (Aston , 2017).
The above is an indication of the precedence and provides a description of the task dependence
In this analysis, the budget mainly considers the training requirements. There are a number of personnel involved in the project and have different rates at which they will work on the project. Furthermore, there are a number of equipment as well as facilities that will be required to attain the project deliverables. All these have been indicated in the project budget. The resources are as per the table below.
The Gantt chart for the activities and resource allocation
Upgrade of the system will be fundamental in the establishment of the organization as one of the best service providers in the country. However, it is the importance of the training program that needs to be considered in the development of the electronic platform.
To begin with, the user will be conveniently placed to make bookings for tours as well as training. It will therefore expand the market for the organization and therefore increase the profitability.
Secondly, the training offered to the staff will reduce the redundancy associated with management of the reservations. Increase in awareness of the system ensures that all the staff can handle the bookings in a more convenient way.
References
Kerzner, H., & kerzner, H. R. (2017). Project management: a systems approach to planning, scheduling, and controlling.
Aaltonen, k. (2011). Project stakeholder analysis as an environmenatl interpretation process. International journal of project management.
Aramo-Immonen, H., & Vanharanta, H. (2009). Project Management: The Task of Holistic. Human Factors and Ergonomics in Manufacturing, 19.
Aston , b. (2017, 02 03). 9 Project Management Methodologies Made Simple. Retrieved from https://thedigitalprojectmanager.com/project-management-methodologies-made-simple/
Buehring, S. (2018, may 31). The benefits of adopting a structured project management method. Retrieved from https://www.knowledgetrain.co.uk/resources/practice/adopting-a-project-management-method
Eskerod, P., & Huemann, m. (2013). Sustainable development and project stakeholder management:What standards say. Internationa;l journal of management.
Filwv, A. (2017). Critical path method in project maanagement is as eqasy as 1,2,3. Retrieved 11 30, 2017, from www.wrike.com/blog/critical-path-is-as-easy-as-123/
Project management Institute. (2013). A guide to the project management body of knowledge(PMBOK giuide).
Westland, j. (2017, April 24). Project Management Methodology – An Overview. Retrieved from https://www.projectmanager.com/blog/project-management-methodology
Essay Writing Service Features
Our Experience
No matter how complex your assignment is, we can find the right professional for your specific task. Contact Essay is an essay writing company that hires only the smartest minds to help you with your projects. Our expertise allows us to provide students with high-quality academic writing, editing & proofreading services.Free Features
Free revision policy
$10Free bibliography & reference
$8Free title page
$8Free formatting
$8How Our Essay Writing Service Works
First, you will need to complete an order form. It's not difficult but, in case there is anything you find not to be clear, you may always call us so that we can guide you through it. On the order form, you will need to include some basic information concerning your order: subject, topic, number of pages, etc. We also encourage our clients to upload any relevant information or sources that will help.
Complete the order formOnce we have all the information and instructions that we need, we select the most suitable writer for your assignment. While everything seems to be clear, the writer, who has complete knowledge of the subject, may need clarification from you. It is at that point that you would receive a call or email from us.
Writer’s assignmentAs soon as the writer has finished, it will be delivered both to the website and to your email address so that you will not miss it. If your deadline is close at hand, we will place a call to you to make sure that you receive the paper on time.
Completing the order and download