Q 1.
The five different characteristics of the project that helps in differentiating projects from different other functions carried out in the daily operations of the organization are as follows:
Defined life span: It is identified that the life span of the project elaborates the number of days that is needed for completing the entire project. It is very much different from other functions that are carried out in daily operations.
Well-defined objective: The project objective depicts the significance of the project and it is found that the project objectives are quite different from other functions.
Involve people from different departments: It is found that there are number of stakeholders from different departments who are involved in the project and their functions are quite different from daily operations.
Project life cycle: The entire life cycle of the project must include the entire period of project execution from initiation.
Specific cost, time as well as performance requirements: The cost, time as well as various performance requirements that are required in the project is very much different from other functions that are carried out in daily operations.
It is identified that implementation of project is important to strategic planning because strategic plans are generally implemented with the help of projects that is new product product, new plant or new information system. On the other hand, implementation of project is advantageous to project managers because project manager is the key person who is mainly responsible for executing the entire project on budget, time as well as within specifications so that the customer of the project is satisfied. It is identified that is the project is not linked to strategic plan of the organization then the resources which are assigned to the project are wasted and as a result the requirements of the projects are not met.
The technical as well as sociocultural dimensions are considered as two side of a single coin as project managers are the person who is very much experienced as well as skilful in both the areas that are technical as well as sociocultural dimension. It is identified that successful project managers found themselves comfortable with the both areas of project management and works properly for making project successful in both aspects.
Advantages |
||
Functional |
Matrix |
Dedicated |
It is a radical alteration in basic structure of the parent organization |
It utilizes resources across functional as well as project duties |
It do not disrupt the structure of the parent organization. |
It helps in providing maximum flexibility within different functional units |
The project mainly focuses on the designated project manager |
It mainly focuses on the project. |
Disadvantages |
||
Functional |
Matrix |
Dedicated |
Lack of appropriate project focus |
Stress can be easily induced by various superiors |
Technical expertise are generally limited to the people of the team. |
It is identified that projects are mainly linked with the strategic planning as projects helps in representing the method through which the strategy is mainly implemented. It is found that as project are quite important, the best way of maximizing the scare resources of the project is by using proper as well as effective priority scheme which helps in allocating various types of resources within the portfolio of the project that helps in balancing risk and contributes properly within the strategic plan.
The various elements of typical scope statement are elaborated below:
Project objectives: The project objective elaborates the need as well as significance of thee project that will be developed.
Deliverables: The deliverables of the project illustrates the elements which are delivered by the project.
Milestones: The milestones are considered as a tool that is mainly utilized for marking specific points along a project timeline.
Technical requirements: The various technical needs as well as requirements of the project are mainly elaborated.
Limits and exclusions: The limits or risks that obstruct the project progress are also illustrated with the help of limits and exclusions.
Reviews with customer: The reviews of the customer are also incorporated with the scope statement of the project.
The project objective helps in answering the various deliverables of the project for which the project us implemented. In addition to this, it also elaborates the time as well as budget that are mainly required for executing the entire project successfully.
It is identified that a good project objective helps in elaborating the time as well as budget which is required for making the project successful.
It mainly means that the project must be completed on the date that is assumed by the project manager. It is found that the entire scope of the project must be scaled properly for meeting costs as well as time objectives and also helps in providing number of opportunities for reducing the entire cost of the project.
The three types of information which are included within the work package are elaborated below:
It is quite appropriate to create proper responsibility matrix rather than full blown WBS when is project is quite small. It is identified that when the project have very much limited scope then it is analyzed that work breakdown package enhances both the time as well as cost of the entire project. It is found that full-blown WBs is generally designed to be utilized in large projects.
Project background and description
The project focuses on the “Manchester United Soccer Club” which is located with Manchester, New Hampshire. It is identified that the organization was formed in the year 1992 for bringing various recreational players to proper level of competition so that they can prepare themselves for the Olympic development program. It is identified that cub 24 boys and girls in team which is mainly affiliated in context to Hampshire Soccer Association as well as granite state girls Soccer league. The directors of the club broad have decided to sponsor one of the tournaments of summer for generating revenue. It is analyzed that hosting tournament of summer is considered as one of the popular method that helps in raising huge amount of funds. MUSC team generally assists in competing with various tournaments in each summer with different locales in New England. It is identified that this tournaments helps in raising funds up to $70,000 for the host club. MUSC requires additional revenue for refurbishing as well as for expanding the number of Soccer fields.
The project scope is divided into in scope as well as out scope:
In scope: The in scope of the project includes:
Out Scope of the project includes:
The high level project requirements include:
The project deliverables include:
Milestones
Task Name |
Expected date |
Completion of planning phase |
Wed 25-10-17 |
Completion of initiation phase |
Fri 10-11-17 |
Completion of execution phase |
Wed 20-12-17 |
Completion of closure phase |
Mon 08-01-18 |
The project stakeholders are listed below:
Stakeholders |
Responsibilities |
Project manager |
The project manager is the person who is responsible of initiating, planning, designing, executing, and monitoring as well as closing the entire project successfully. They have engaged in resource planning, cost estimation, documentation, risk analysis and many more. |
Project organizer |
The project organizer is the person who organizes the event and was responsible of making proper decisions. They also involve in analyzing the risk and identify proper strategies or methodologies that are helpful in making resolving the risks that are associated with the entire project. It is identified that every decision of the project organizer bring positive outcome on the objectives of the project. |
Sponsor |
Project sponsor is the person who is responsible of taking the entire project accountability. The project sponsor assists in providing proper business expertise as well as guidance to the project manager so that they can work properly for making the entire project successfully |
Financial manager |
Financial manager are the person who mainly engages in the project for managing the finance of the organization. The financial manager helps in preparing reports which is mainly needed by the law. They also helps in managing the Flow of cash as well as various financial instruments. |
Task Name |
Duration |
Start |
Finish |
Organizing tournament for Manchester United Soccer Club |
74 days |
Wed 27-09-17 |
Mon 08-01-18 |
Planning phase |
21 days |
Wed 27-09-17 |
Wed 25-10-17 |
Creating project plan |
4 days |
Wed 27-09-17 |
Mon 02-10-17 |
Creating resource plan |
3 days |
Tue 03-10-17 |
Thu 05-10-17 |
Creating financials plan |
3 days |
Fri 06-10-17 |
Tue 10-10-17 |
Creating quality plan |
4 days |
Wed 11-10-17 |
Mon 16-10-17 |
Creating risk plan |
3 days |
Tue 17-10-17 |
Thu 19-10-17 |
Creating communication plan |
4 days |
Fri 20-10-17 |
Wed 25-10-17 |
Milestone: Completion of planning phase |
0 days |
Wed 25-10-17 |
Wed 25-10-17 |
Initiation phase |
12 days |
Thu 26-10-17 |
Fri 10-11-17 |
Developing tournament case |
4 days |
Thu 26-10-17 |
Tue 31-10-17 |
Undertaking feasibility study |
3 days |
Wed 01-11-17 |
Fri 03-11-17 |
Establishing project charter |
2 days |
Mon 06-11-17 |
Tue 07-11-17 |
Appointing team members |
3 days |
Wed 08-11-17 |
Fri 10-11-17 |
Milestone: Completion of initiation phase |
0 days |
Fri 10-11-17 |
Fri 10-11-17 |
Execution phase |
28 days |
Mon 13-11-17 |
Wed 20-12-17 |
Documenting the significance of qualified referees |
4 days |
Mon 13-11-17 |
Thu 16-11-17 |
Contacting local colleges |
5 days |
Fri 17-11-17 |
Thu 23-11-17 |
Buying rewards |
6 days |
Fri 24-11-17 |
Fri 01-12-17 |
Procedure of charging entry fee |
5 days |
Mon 04-12-17 |
Fri 08-12-17 |
Sale of tournament t-shirts |
4 days |
Mon 11-12-17 |
Thu 14-12-17 |
Development of silk-screen design for the tournament |
4 days |
Fri 15-12-17 |
Wed 20-12-17 |
Milestone: completion of execution phase |
0 days |
Wed 20-12-17 |
Wed 20-12-17 |
Closure phase |
13 days |
Thu 21-12-17 |
Mon 08-01-18 |
Reviewing project |
11 days |
Thu 21-12-17 |
Thu 04-01-18 |
Stakeholder’s sign off |
1 day |
Fri 05-01-18 |
Fri 05-01-18 |
Documentation |
1 day |
Mon 08-01-18 |
Mon 08-01-18 |
Milestone: completion of closure phase |
0 days |
Mon 08-01-18 |
Mon 08-01-18 |
Burke, R. (2013). Project management: planning and control techniques. New Jersey, USA.
Cicmil, S., Cooke-Davies, T., Crawford, L., & Richardson, K. (2017, April). Exploring the complexity of projects: Implications of complexity theory for project management practice. Project Management Institute.
Hegazy, T. (2013). Computer-Based Construction Project Management: Pearson New International Edition. Pearson Higher Ed.
Heldman, K. (2015). PMP project management professional exam deluxe study guide: updated for the 2015 Exam. John Wiley & Sons.
Hwang, B. G., & Ng, W. J. (2013). Project management knowledge and skills for green construction: Overcoming challenges. International Journal of Project Management, 31(2), 272-284.
Kerzner, H. (2013). Project management: a systems approach to planning, scheduling, and controlling. John Wiley & Sons.
Kerzner, H. (2017). Project management metrics, KPIs, and dashboards: a guide to measuring and monitoring project performance. John Wiley & Sons.
Larson, E. W., & Gray, C. (2013). Project Management: The Managerial Process with MS Project. McGraw-Hill.
Mir, F. A., & Pinnington, A. H. (2014). Exploring the value of project management: linking project management performance and project success. International journal of project management, 32(2), 202-217.
Pemsel, S., & Wiewiora, A. (2013). Project management office a knowledge broker in project-based organisations. International Journal of Project Management, 31(1), 31-42.
Schwalbe, K. (2015). Information technology project management. Cengage Learning.
Todorovi?, M. L., Petrovi?, D. ?., Mihi?, M. M., Obradovi?, V. L., & Bushuyev, S. D. (2015). Project success analysis framework: A knowledge-based approach in project management. International Journal of Project Management, 33(4), 772-783.
Turner, R. (2016). Gower handbook of project management. Routledge.
Turner, R. (2016). Gower handbook of project management. Routledge.
Verzuh, E. (2015). The fast forward MBA in project management. John Wiley & Sons.
Walker, A. (2015). Project management in construction. John Wiley & Sons.
Essay Writing Service Features
Our Experience
No matter how complex your assignment is, we can find the right professional for your specific task. Contact Essay is an essay writing company that hires only the smartest minds to help you with your projects. Our expertise allows us to provide students with high-quality academic writing, editing & proofreading services.Free Features
Free revision policy
$10Free bibliography & reference
$8Free title page
$8Free formatting
$8How Our Essay Writing Service Works
First, you will need to complete an order form. It's not difficult but, in case there is anything you find not to be clear, you may always call us so that we can guide you through it. On the order form, you will need to include some basic information concerning your order: subject, topic, number of pages, etc. We also encourage our clients to upload any relevant information or sources that will help.
Complete the order formOnce we have all the information and instructions that we need, we select the most suitable writer for your assignment. While everything seems to be clear, the writer, who has complete knowledge of the subject, may need clarification from you. It is at that point that you would receive a call or email from us.
Writer’s assignmentAs soon as the writer has finished, it will be delivered both to the website and to your email address so that you will not miss it. If your deadline is close at hand, we will place a call to you to make sure that you receive the paper on time.
Completing the order and download