The following table shows the assignment the costs to the activity centres using the resource driver consumption patterns shown in Schedules 1 and 2:
{For new Editor.}
|
(Amounts in $) |
|
||||||
Cost category |
Wages |
Building costs |
Depreciation |
Consumables |
Energy |
Other |
Total |
|
New product development |
1,44,000.00 |
25,000.00 |
– |
992.06 |
– |
1,500.00 |
1,71,492.06 |
|
3.00 |
200.00 |
– |
10.00 |
– |
3.00 |
|||
Sales and dispatch |
5,76,000.00 |
62,500.00 |
– |
1,984.13 |
– |
6,000.00 |
6,46,484.13 |
|
12.00 |
500.00 |
– |
20.00 |
– |
12.00 |
|||
Inspecting |
96,000.00 |
62,500.00 |
– |
– |
– |
1,000.00 |
1,59,500.00 |
|
2.00 |
500.00 |
– |
– |
– |
2.00 |
|||
Pasteurizing |
14,88,000.00 |
1,25,000.00 |
5,00,000.00 |
18,849.21 |
74,573.86 |
15,500.00 |
22,21,923.07 |
|
31.00 |
1,000.00 |
4,000.00 |
190.00 |
2,50,000.00 |
31.00 |
|||
Culturing |
14,88,000.00 |
1,25,000.00 |
6,25,000.00 |
12,896.83 |
1,13,352.27 |
15,500.00 |
23,79,749.10 |
|
31.00 |
1,000.00 |
5,000.00 |
130.00 |
3,80,000.00 |
31.00 |
|||
Curing |
12,00,000.00 |
1,25,000.00 |
1,25,000.00 |
18,849.21 |
74,573.86 |
12,500.00 |
15,55,923.07 |
|
25.00 |
1,000.00 |
1,000.00 |
190.00 |
2,50,000.00 |
25.00 |
|||
Administration |
5,76,000.00 |
62,500.00 |
– |
5,952.38 |
– |
6,000.00 |
6,50,452.38 |
|
12.00 |
500.00 |
– |
60.00 |
– |
12.00 |
|||
Corporate management |
4,32,000.00 |
37,500.00 |
– |
2,976.19 |
– |
4,500.00 |
4,76,976.19 |
|
9.00 |
300.00 |
– |
30.00 |
– |
9.00 |
|||
Total |
60,00,000.00 |
6,25,000.00 |
12,50,000.00 |
62,500.00 |
2,62,500.00 |
62,500.00 |
82,62,500.00 |
|
125.00 |
5,000.00 |
10,000.00 |
630.00 |
8,80,000.00 |
125.00 |
The following table shows the calculation of the cost of each activity performed in the relevant (to your allocated case) activity cost centre, using the information provided in item 1 above and in Schedule 3:
{For new Editor.}
(Amounts in $) |
||||||||
Particulars |
Set up pasterurizer |
Load pasteurizer |
Operate pasteurizer |
Unload pasteurizer |
Clean pasteurizer |
Move to culturing room |
Total |
|
Wages |
6,00,000.00 |
6,00,000.00 |
24,00,000.00 |
12,00,000.00 |
6,00,000.00 |
6,00,000.00 |
60,00,000.00 |
|
Building costs |
31,250.00 |
31,250.00 |
4,37,500.00 |
31,250.00 |
31,250.00 |
62,500.00 |
6,25,000.00 |
|
Depreciation |
12,50,000.00 |
12,50,000.00 |
||||||
Consumables |
62,500.00 |
62,500.00 |
||||||
Energy |
2,62,500.00 |
2,62,500.00 |
||||||
Other |
6,250.00 |
6,250.00 |
25,000.00 |
12,500.00 |
6,250.00 |
6,250.00 |
62,500.00 |
|
Total |
6,37,500.00 |
6,37,500.00 |
44,37,500.00 |
12,43,750.00 |
6,37,500.00 |
6,68,750.00 |
|
|
A list of the activities performed and their annual costs is provided in Schedule 4 (some costs will need to be calculated as indicated in item 2 above). In addition the schedule provides an activity driver for each activity and the annual quantity of each activity driver. Calculate the cost per unit of activity driver for the activities listed:
The following table shows the desired calculations:
{For new Editor.}
|
(Amounts in $) |
|
||
Activity |
Cost |
Base |
Cost per activity |
|
Corporate management |
4,76,976.0000 |
|||
Process receivables |
2,60,181.0000 |
6,300.0000 |
41.2986 |
|
Process payables |
2,53,931.0000 |
3,100.0000 |
81.9132 |
|
Production planning |
1,36,340.0000 |
1,250.0000 |
109.0720 |
|
Reports to Health Dept |
15,950.0000 |
1,250.0000 |
12.7600 |
|
Process sales order |
4,00,390.0000 |
5,000.0000 |
80.0780 |
|
Dispatch sales order |
2,46,094.0000 |
3,100.0000 |
79.3852 |
|
New Product Development |
1,71,492.0000 |
#DIV/0! |
||
Inspect milk |
60,350.0000 |
1,250.0000 |
48.2800 |
|
Disposal of substandard milk |
15,950.0000 |
1,250.0000 |
12.7600 |
|
Move to pasteurizing room |
15,950.0000 |
1,250.0000 |
12.7600 |
|
Set up pasteurizer |
6,37,500.0000 |
1,250.0000 |
510.0000 |
|
Load pasteurizer |
6,37,500.0000 |
1,250.0000 |
510.0000 |
|
Operate pasteurizer |
42,37,500.0000 |
2,50,000.0000 |
16.9500 |
|
Unload pasteurizer |
12,43,750.0000 |
1,250.0000 |
995.0000 |
|
Clean pasteurizer |
6,37,500.0000 |
1,250.0000 |
510.0000 |
|
Move to culturing room |
6,68,750.0000 |
1,250.0000 |
535.0000 |
|
Set up scales |
81,425.0000 |
1,250.0000 |
65.1400 |
|
Weigh ingredients |
1,56,600.0000 |
1,250.0000 |
125.2800 |
|
Load culturing vats |
3,13,200.0000 |
1,250.0000 |
250.5600 |
|
Coagulation, Drain and Scalding |
15,77,999.0000 |
2,50,000.0000 |
6.3120 |
|
Drain and clean vats |
1,62,850.0000 |
1,250.0000 |
130.2800 |
|
Move to curing room |
87,675.0000 |
2,50,000.0000 |
0.3507 |
|
Pack and pressing |
3,34,375.0000 |
10,00,000.0000 |
0.3344 |
|
Setup curing room |
1,27,500.0000 |
20,000.0000 |
6.3750 |
|
Move to curing room |
66,875.0000 |
20,000.0000 |
3.3438 |
|
Cure products |
8,87,173.0000 |
20,000.0000 |
44.3587 |
|
Unload curing room |
66,875.0000 |
20,000.0000 |
3.3438 |
|
Inspect finished products |
35,350.0000 |
20,000.0000 |
1.7675 |
|
Disposal of substandard product |
15,950.0000 |
20,000.0000 |
0.7975 |
|
Move to truck |
73,125.0000 |
19,000.0000 |
3.8487 |
|
Based on the information calculated in item 3 above and in Schedules 5 and 6, prepare a bill of activities and determine the cost per unit for each of the two product items identified:
The following table shows the calculation of cost per unit:
{For new Editor.}
(Amounts in $) |
||
Cheddar |
Activity driver |
Cost |
Corporate management |
95,395.0000 |
95,395.0000 |
Process receivables |
600.0000 |
24,779.1429 |
Process payables |
300.0000 |
24,573.9677 |
Production planning |
100.0000 |
10,907.2000 |
Reports to Health Dept |
100.0000 |
1,276.0000 |
Process sales order |
630.0000 |
50,449.1400 |
Dispatch sales order |
500.0000 |
39,692.5806 |
New Product Development |
– |
– |
Inspect milk |
100.0000 |
4,828.0000 |
Disposal of substandard milk |
100.0000 |
1,276.0000 |
Move to pasteurizing room |
100.0000 |
1,276.0000 |
Set up pasteurizer |
100.0000 |
51,000.0000 |
Load pasteurizer |
100.0000 |
51,000.0000 |
Operate pasteurizer |
50,000.0000 |
8,47,500.0000 |
Unload pasteurizer |
100.0000 |
99,500.0000 |
Clean pasteurizer |
100.0000 |
51,000.0000 |
Move to culturing room |
100.0000 |
53,500.0000 |
Set up scales |
100.0000 |
6,514.0000 |
Weigh ingredients |
100.0000 |
12,528.0000 |
Load culturing vats |
100.0000 |
25,056.0000 |
Coagulation, Drain and Scalding |
50,000.0000 |
3,15,599.8000 |
Drain and clean vats |
100.0000 |
13,028.0000 |
Move to curing room |
50,000.0000 |
17,535.0000 |
Pack and pressing |
2,00,000.0000 |
66,875.0000 |
Setup curing room |
2,000.0000 |
12,750.0000 |
Move to curing room |
2,000.0000 |
6,687.5000 |
Cure products |
2,000.0000 |
88,717.3000 |
Unload curing room |
2,000.0000 |
6,687.5000 |
Inspect finished products |
– |
– |
Disposal of substandard product |
– |
– |
Move to truck |
2,000.0000 |
7,697.3684 |
Direct material |
6.0000 |
12,00,000.0000 |
Selling price |
14.0000 |
28,00,000.0000 |
Batch size |
2,000.0000 |
|
Annual volume |
2,00,000.0000 |
|
Cost per unit |
|
15.9381 |
(Amounts in $) |
||
Mascarpone |
Activity driver |
Cost |
Corporate management |
11,447 |
11,447.0000 |
Process receivables |
200 |
8,259.7143 |
Process payables |
100 |
8,191.3226 |
Production planning |
60 |
6,544.3200 |
Reports to Health Dept |
60 |
765.6000 |
Process sales order |
190 |
15,214.8200 |
Dispatch sales order |
100 |
7,938.5161 |
New Product Development |
56,592 |
56,592.0000 |
Inspect milk |
60 |
2,896.8000 |
Disposal of substandard milk |
60 |
765.6000 |
Move to pasteurizing room |
60 |
765.6000 |
Set up pasteurizer |
60 |
30,600.0000 |
Load pasteurizer |
60 |
30,600.0000 |
Operate pasteurizer |
12,000 |
2,03,400.0000 |
Unload pasteurizer |
60 |
59,700.0000 |
Clean pasteurizer |
60 |
30,600.0000 |
Move to culturing room |
60 |
32,100.0000 |
Set up scales |
60 |
3,908.4000 |
Weigh ingredients |
60 |
7,516.8000 |
Load culturing vats |
60 |
15,033.6000 |
Coagulation, Drain and Scalding |
12,000 |
75,743.9520 |
Drain and clean vats |
60 |
7,816.8000 |
Move to curing room |
12,000 |
4,208.4000 |
Pack and pressing |
25,000 |
8,359.3750 |
Setup curing room |
500 |
3,187.5000 |
Move to curing room |
500 |
1,671.8750 |
Cure products |
500 |
22,179.3250 |
Unload curing room |
500 |
1,671.8750 |
Inspect finished products |
500 |
883.7500 |
Disposal of substandard product |
500 |
398.7500 |
Move to truck |
480 |
1,847.3684 |
Direct material |
8 |
1,92,000.0000 |
Selling price |
18 |
|
Batch size |
400 |
|
Annual volume |
24,000 |
The difference in the costs would not be reflected in the system of conventional costing since this method does not take into account the different activities that are involved in the manufacture of the product.
Do you think that the existing costing system understates or overstates the cost of the two products identified in item 4 above? Explain your answers in detail with reference to your calculations:
The existing system of costing being used is the traditional method which overstates the cost per unit. The traditional method of costing takes into account the total amount of overhead and then the same is divided by the total number of the direct labour hours and then the number of direct labour hours are multiplied by the overhead price per unit. Whereas, the ABC method divides the overheads on the basis of the number of the activities that are used for the manufacture of the product. For example, the total amount of overhead is $8262500, if the traditional method would have been used, then this amount would have been divided by equally but under ABC, this is divided on the basis of the number of employees for each product.
Consider and describe the changes in cost structure that are likely to have occurred at the Company over the last 15 to 20 years, and speculate on their causes:
The cost under the traditional method would have been more and since the company always charges the price at cost + mark up, so the selling price would have been more. In the case given, the cot per unit comes out to be higher than the selling price that has been charged by the company.
How complete your analysis and prepare your report. Your report should identify if there are any deficiencies inherent in the existing costing system and if so explain (using the outcomes from items 1 to 7 above) how activity-based costing could overcome these deficiencies. If, in your analysis, you determine there are no inherent deficiencies, explain (again using the outcomes from items 1 to 7 above) why not:
All of the inherent deficiencies could be reduced if the company opts for the activity based costing method for the purposes of calculating the cost per unit.
Include in your discussion, what factors the management accountant should consider when deciding whether to use an Activity-based system that includes both manufacturing overhead and non-manufacturing costs. And furthermore outline the benefits, costs and limitations of activity-based costing:
There are many of the factors that determine the success of the implementation of the activity based costing. These factors include the support from the top management, use of the suitable software, ensuring that all of the affected employees understand and participate in the implementation of the costing method (Eprints, 2017).
For the purposes of allocating the costs, there are many of the concepts that do not guarantee the fact that the indirect costs are directly attributable to the various products and the services due to the reason of approximation and estimation (Word press, 2014). For the purposes of allocating the costs based on the different concepts of the ABC, all of the indirect costs have to be implemented but the same is very costly and troublesome. This is due to the fact that the selection of the drivers and the defining of the activities is very tough. Each particular stage of the method is equally important when it comes to the motivating of the adaptations of the methods and the opinion of the various external experts really matters and the size of the firm also matters (The journal of business, 2017).
The following are the benefits of employing this method:
The following are the demerits of the method:
References:
Bayt.com. (2017). What are the limitations of ABC costing system?. [online] Available at: https://www.bayt.com/en/specialties/q/121869/what-are-the-limitations-of-abc-costing-system/ [Accessed 3 May 2017].
eprints.um.edu.my. (2017). Factors Influencing Activity-Based Costing Success: A Review. [online] Available at: https://eprints.um.edu.my/3118/1/ISBN_978.pdf [Accessed 3 May 2017].
quytrinh.files.wordpress.com. (2017). Factors influencing the implementation of Activity-Based Costing in Thailand: a case study of a Thai Telecommunications Company. [online] Available at: https://quytrinh.files.wordpress.com/2014/11/factors-influencing-the-implementation-of-activity-based-costing-in-thailand-16.pdf [Accessed 3 May 2017].
Smallbusiness.chron.com. (2017). The Disadvantages & Advantages of Activity-Based Costing. [online] Available at: https://smallbusiness.chron.com/disadvantages-advantages-activitybased-costing-45096.html [Accessed 3 May 2017].
Thejournalofbusiness.org. (2017). Activity based costing. [online] Available at: https://thejournalofbusiness.org/index.php/site/article/viewFile/259/255 [Accessed 3 May 2017].
YourArticleLibrary.com: The Next Generation Library. (2017). Advantages and Demerits of Activity Based Costing (ABC). [online] Available at: https://www.yourarticlelibrary.com/accounting/costing/advantages-and-demerits-of-activity-based-costing-abc/52617/ [Accessed 3 May 2017].
Essay Writing Service Features
Our Experience
No matter how complex your assignment is, we can find the right professional for your specific task. Contact Essay is an essay writing company that hires only the smartest minds to help you with your projects. Our expertise allows us to provide students with high-quality academic writing, editing & proofreading services.Free Features
Free revision policy
$10Free bibliography & reference
$8Free title page
$8Free formatting
$8How Our Essay Writing Service Works
First, you will need to complete an order form. It's not difficult but, in case there is anything you find not to be clear, you may always call us so that we can guide you through it. On the order form, you will need to include some basic information concerning your order: subject, topic, number of pages, etc. We also encourage our clients to upload any relevant information or sources that will help.
Complete the order formOnce we have all the information and instructions that we need, we select the most suitable writer for your assignment. While everything seems to be clear, the writer, who has complete knowledge of the subject, may need clarification from you. It is at that point that you would receive a call or email from us.
Writer’s assignmentAs soon as the writer has finished, it will be delivered both to the website and to your email address so that you will not miss it. If your deadline is close at hand, we will place a call to you to make sure that you receive the paper on time.
Completing the order and download