Maersk Doha stacked at the Portsmouth Marine Terminal in Norfolk on October 1 leading to the shutdown of the main engine. This was around 0630. This particular vessel was actually scheduled travel or sail at 2100 but there was postponement from the early evening until evening so that changes could be made on the plan of stowage. The staff of engineers actually took advantage of this time to carry out some repairs and maintenance on the engine while it was in a shutdown state. During this period the auxiliary boiler was running throughout the time contribution g to the process of heating heavy fuel oil to serve other domestic functions. The feed water from the auxiliary boiler was kept circulating through the Exhaust Gas Economizer knew as EGE to keep in warm condition to be used for sailing(Garcia et al.2015).
When it was about 2300, 1c hour notice was given by the bridge for sailing to the control room of the engine. The duty engineer then started to prepare the main engine for the sail. The third engineer who was on duty was however new to the vessel and was under the supervision of the chief engineer who could assist where necessary(Daboussi et al. 2014). The preparation of the main engine was as per the checklist. It is interesting to note that during the preparation, the third engineer experienced difficulties in staring one of the generators and sort the assistance of the second engineer(Liu, Zhao & Bai 2013). Although the second engineer was on off duty, he came down to assist. He managed to repair the problem and he was later requested by the chief engineer to stay in the engineering room beside the duty engineer. The first movement of the engine was made shortly after midnight which was at 0004 as the vessel came astern to depart from the berth. After a few minutes, the chief engineer noticed that there was a problem with the reversing mechanism of the main engine. The pneumatic actuators were used in the reversing of the engine to go astern through alteration of the timing of the individual cylinder.
At around 0030 there was an alarm from the machinery control room which was indicating that the pressure in the system of the steam was relatively low. This particular alarm was actually not considered uncommon since it was as a result of the failing system of the auxiliary boiler to ignite. The trickiest part was that there were no other related alarms to indicate that the kind of failure was the case. The third engineer therefore just continues to check the steam pressure in the control, a room of the machinery(Rajakumar, Balasubramanian & Balakrishnan 2016). The indication was that it was steadily falling/. This concerned was communicated to the first engineer for assistance. All the third, second and first engineers went to the generator and boiler compartment within the engine so that they could investigate the auxiliary boiler. The water level was reported to be still normal and the flame was still alight although there was escaping steam from the inlet of the furnace air. The fuel pump was shut down by the third engineer so as to extinguish the flame before opening the burner door to properly examine the furnace(Zhang Li, Bartlett & Xiao 2015).
The steam started entering the surrounding compartment and the noise of the No1 generator was actually destructing. The No2 and No 3 generators were therefore used on the other side of the room of the nine so as to shut down No1 generator. It was anticipated by the engineers that there was a probability of losing the steam to heat heavy fuel oil and this could stop the generators from working. The generator fuel supply was therefore changed to the diesel oil. The viscosity oil of the diesel started to leak from the generator joints and the leaks were repaired. This led to the emergence of fire.
After the fire incident had been managed effectively, the auxiliary boiler was cooled down for the inspection purposes(Basurko & Mesbahi 2014). There was the discovery of a very big bulge with the dimensions of about 1m long. This extended to about 0.6m into the tube of the furnace. There was also a circumferential crack of about 0.3m long at the cross point of the bulge peak. There were however no reported defects with the control mechanism of the auxiliary boiler or system of surveillance. There were proper damages on the EGE with nearly half of the tubes melted. The molten metals gathered after solidification with slag and ash at the base of the exhaust. The structure of the EGE together with the casing was affected by heat and they properly buckled. This component also radiated and burnt the paintwork, light fittings, cables and the detectors of fire around the same place. The debris together with water that originated from the firefighting fell down the main engine exhaust trunk towards the section of the turbochargers(Ulrich, Leonardi & Rung 2013). The water that had collected in the bilge actually leaked through the seal into the tank of the main engine oil below the sump. This actually led to the contamination of the engine oil. This water was later pumped into the ballast that was empty to prevent the possibility of pollution later on.
Figure 1: Auxiliary boiler with the distorted tube of the furnace( Zhang & Jin 2013).
Damaged tubes of EGE(Bacay, Dotong & Laguador 2015).
The most likely cause of the cracking and distortion of the furnace of the auxiliary boiler furnace was the sustained overheating which was due to the operation of the low water level. This was most likely caused by the failure of the automatic boiler control system. The loss of the feed water in the boiler of the auxiliary system led to the failure of the circulation of water through the EGE. This led to a rise in temperature. There is need to have at least two systems for monitoring the level of water so that in case one of the systems fails, the issue can still be detected in advance to avoid similar accidents that result from the failure of the boiler.
Conclusion
There are several factors that usually contribute to the accidents of ships. Some of these factors are considered the main actors. The auxiliary factors are meant to fuel or facilitate the process of breakdown. While addressing the issue of safety and functionality of the components of the ship, all the factors must be treated equally. For the case of this ship, the burner was shut down before opening the door of the furnace. There was the escape of the seam and close analysis indicated a furnace tube with a severe distortion and cracks. This allowed the burner to continue firing while there was little water in the boiler.
The investigation established that boiler is one of the crucial components of the ship. This possibly was the reason why its failure resulted in an accident. The radiant heat from the EGE will always attack cables, paints and light fittings. This fire, however, should be contained by the use of water hoses. This implies that the operator of any ship must always be on the watch besides being competent. The probable cause of the fire was the malfunction of the auxiliary boiler control mechanism. This allowed the burner to continue firing while there was little water in the boiler. Safety systems must, therefore, be put in place to have such problems addressed in advanced.
References
Bacay, T. E., Dotong, C. I., & Laguador, J. M. (2015). The attitude of Marine Engineering Students on Some School-Related Factors and their Academic Performance in Electro Technology 1 and 2. Studies in Social Sciences and Humanities, 2(4), 239-249.
Basurko, O. C., & Mesbahi, E. (2014). Methodology for the sustainability assessment of marine technologies. Journal of cleaner production, 68, 155-164.
Daboussi, F., Leduc, S., Maréchal, A., Dubois, G., Guyot, V., Perez-Michaut, C., … & Voytas, D. F. (2014). Genome engineering empowers the diatom Phaeodactylum tricornutum for biotechnology. Nature Communications, 5, 3831.
Garcia-Espinel, J. D., Castro-Fresno, D., Gayo, P. P., & Ballester-Muñoz, F. (2015). Effects of seawater environment on glass fiber reinforced plastic materials used for marine civil engineering constructions. Materials & Design (1980-2015), 66, 46-50.
Liu, Z., Zhao, X., & Bai, F. (2013). Production of xylanase by an alkaline-tolerant marine-derived Streptomyces viridochromogenes strain and improvement by ribosome engineering. Applied microbiology and biotechnology, 97(10), 4361-4368.
Rajakumar, S., Balasubramanian, V., & Balakrishnan, M. (2016). Friction surfacing for enhanced surface protection of marine engineering components: erosion-corrosion study. Journal of the Mechanical Behavior of Materials, 25(3-4), 111-119.
Ulrich, C., Leonardi, M., & Rung, T. (2013). Multi-physics SPH simulation of complex marine-engineering hydrodynamic problems. Ocean Engineering, 64, 109-121.
Zhang, J. H., & Jin, J. Y. (2013). Marine delimitation method based on earth ellipsoid model. The science of Surveying and Mapping, 38(3), 16-17.
Zhang, Y., Li, X., Bartlett, D. H., & Xiao, X. (2015). Current developments in marine microbiology: high-pressure biotechnology and the genetic engineering of piezophiles. Current opinion in biotechnology, 33, 157-164.
Essay Writing Service Features
Our Experience
No matter how complex your assignment is, we can find the right professional for your specific task. Contact Essay is an essay writing company that hires only the smartest minds to help you with your projects. Our expertise allows us to provide students with high-quality academic writing, editing & proofreading services.Free Features
Free revision policy
$10Free bibliography & reference
$8Free title page
$8Free formatting
$8How Our Essay Writing Service Works
First, you will need to complete an order form. It's not difficult but, in case there is anything you find not to be clear, you may always call us so that we can guide you through it. On the order form, you will need to include some basic information concerning your order: subject, topic, number of pages, etc. We also encourage our clients to upload any relevant information or sources that will help.
Complete the order formOnce we have all the information and instructions that we need, we select the most suitable writer for your assignment. While everything seems to be clear, the writer, who has complete knowledge of the subject, may need clarification from you. It is at that point that you would receive a call or email from us.
Writer’s assignmentAs soon as the writer has finished, it will be delivered both to the website and to your email address so that you will not miss it. If your deadline is close at hand, we will place a call to you to make sure that you receive the paper on time.
Completing the order and download