In order to upgrade the archive website of the company, the project manager is required to develop a project budgetary plan. It is the responsibility of the project manager to complete the project within the estimated budget and allotted time. Budget variance is referred to as the difference between budget and baseline amount of the revenue, expense and the actual amount. In order to upgrade the website, different activities are considered by the project manager. For each of the project activities varied cost amount is also allotted. The project manager of this long-term project has considered various resources also.
WBS for upgrading the website of National Archives of Australia
The lists of resources allotted for the project include needful equipments, facilities, fees and charges, human resources, materials, statutory cost and services as well. In order to reduce workload from the project team members and project manager as well work break down structure is also developed. For this particular project, five different phases are designed in terms of initiation phase, planning phase, design phase, design phase, development phase, testing phase and closure phase.
Contingency budget plan is a kind of fund that is set aside by the company to deal with the unpredicted conditions. It also helps to ensure the successful completion of the project program. On the other hand, tolerance is percentages estimated for the total budgeting that can be spend without any kind of return program.
For this particular project, overheads or indirect costs have been estimated. In order to upgrade the website of the company the indirect cost estimated for the below factors such as management, general administration, utilities, security, insurance, legal, building rentals, advertisement etc. For different activities, the total budget estimated is as follows:
For upgrading, the website units of measure are considered as it helps to define the perquisite inventory setup for the units of measure. For this project, the project measures and metrics are related to each other. The metrics serve values, thresholds, constraints, scope and duration of the project. According to the developed Service Level Agreement (SLA) of the company, it is found that the project needs 3 years for its successful completion. The additional components that are to be incorporated include API compatibility, accessibility, privacy of the intellectual properties and hosting.
With the help precision, the values for the repeating measurements are clustered because it is all about the project exactness. After 12 weeks from the starting of the project, it s found that the project is progressing n the correct track. The actual cost for all the activities and the estimated cost do not vary a lot.
In order to measure the direct costs to provide proper services to the consumers it is necessary to use certain cost analysis tools by the project manager. The cost analysis tool incorporated in the site administrator helps to simplify the project. Due to various reasons, the cost analysis tools are widely used by the project managers. The two different types of cost analysis methods used by the project manager in this particular project include investment cost analysis and cost allocation analysis.
Investment cost analysis: With the investment cost analysis, all expenses involved to the activities are operated and estimated by the finance manager. The finance manager is responsible to include all the investment cost for the different activities.
Cost allocation analysis: With the help of this particular method, the project manager will be able to allot actual cost for different project activities. However, for accomplishing the cost allocation, the finance manager considers the budget information and service details.
Budget Variance |
||||||||||
Current Budget Variance |
Projected Budget Variance at Completion |
|||||||||
Project |
Report as of Date |
Actual Expenditures |
Planned Expenditures |
Variance Amount |
Variance Percentage |
Date Baseline Occurred |
Baseline Budget |
Estimate At Complete |
Variance Amount |
Variance Percentage |
project planning phase |
4/10/2018 |
$63,320 |
$ 60,000 |
$ 3,320 |
6% |
Mar-18 |
$60,000 |
$ 65,000 |
$ 5,000 |
8.3% |
project design phase |
5/11/2018 |
$ 39,680 |
$ 35,000 |
$ 4,680 |
13% |
Apr-18 |
$35,000 |
$ 45,000 |
$ 10,000 |
28.6% |
Project development phase |
6/20/2018 |
$ 68,240 |
$65,000 |
$ 3,240 |
5% |
May-18 |
$65,000 |
$ 68,000 |
$ 3,000 |
4.6% |
testing phase |
7/20/2018 |
$ 48,800 |
$ 45,550 |
$ 3,250 |
7% |
Jun-18 |
$45,550 |
$ 50,000 |
$ 4,450 |
9.8% |
Budget Variance Key |
||||||||||
At or under Original or Re-baselined Cost Estimate |
||||||||||
Within 0-15% of Original or Re-baselined Cost Estimate |
||||||||||
More than 15% of Original or Re-baselined Cost Estimate |
In order to avoid all the extra expenses and cost overruns the project manager should maintain certain procedures. Replanning of the project will bring back the project to its origin budget. The steps to be followed for the maintenance are as follows:
Dealing with the faulty planning: The finance manager should try to reduce all the project risks through proper planning.
Correcting poor management: Accurate project management tools and techniques should be implemented.
Hiring financial experts: In order to avoid the cost level risks experienced financial experts should be hired.
Task Name |
Duration |
Start |
Finish |
Predecessors |
Resource Names |
Cost |
Schedule for upgrading website |
118 days |
Tue 2/20/18 |
Thu 8/2/18 |
$267,520.00 |
||
Initiation phase |
16 days |
Tue 2/20/18 |
Tue 3/13/18 |
$21,680.00 |
||
Developing business case |
4 days |
Tue 2/20/18 |
Fri 2/23/18 |
Project manager, Project planner |
$8,000.00 |
|
Undertaking feasibility study |
3 days |
Mon 2/26/18 |
Wed 2/28/18 |
2 |
Financial manager |
$2,880.00 |
Establishing project charter |
4 days |
Thu 3/1/18 |
Tue 3/6/18 |
3 |
Project manager, equipment [1],service |
$4,800.00 |
Appointing project team members |
5 days |
Wed 3/7/18 |
Tue 3/13/18 |
4 |
Project manager |
$6,000.00 |
Milestone 1: Completion of initiation phase |
0 days |
Tue 3/13/18 |
Tue 3/13/18 |
5 |
$0.00 |
|
Planning phase |
20 days |
Wed 3/14/18 |
Tue 4/10/18 |
$68,320.00 |
||
Creating project plan |
5 days |
Wed 3/14/18 |
Tue 3/20/18 |
5 |
Developer, Project manager, Supervisor, equipment [1],Project planner |
$17,600.00 |
Creating resource plan |
4 days |
Wed 3/21/18 |
Mon 3/26/18 |
6 |
Project manager, Project planner |
$8,000.00 |
Development of finanacial plan |
5 days |
Wed 3/21/18 |
Tue 3/27/18 |
8 |
Technical engineer |
$3,600.00 |
Development of quality plan |
6 days |
Tue 3/27/18 |
Tue 4/3/18 |
9 |
Developer, statutory cost ,System analyst |
$11,520.00 |
Creating risk plan |
4 days |
Wed 3/28/18 |
Mon 4/2/18 |
10 |
Project manager, materials [1],Risk analyst |
$8,640.00 |
Development of acceptance plan |
5 days |
Wed 4/4/18 |
Tue 4/10/18 |
11 |
Project manager, Supervisor, Project planner, service |
$13,200.00 |
Development of communication plan |
6 days |
Tue 4/3/18 |
Tue 4/10/18 |
12 |
Risk analyst, statutory cost |
$5,760.00 |
Milestone 2: Completion of planning phase |
0 days |
Tue 4/10/18 |
Tue 4/10/18 |
13 |
$0.00 |
|
Design Phase |
15 days |
Wed 4/11/18 |
Tue 5/1/18 |
$39,680.00 |
||
Wireframe Design |
5 days |
Wed 4/11/18 |
Tue 4/17/18 |
14 |
Developer, equipment [1],materials [1],Technical engineer |
$8,000.00 |
Visual design |
4 days |
Wed 4/18/18 |
Mon 4/23/18 |
17 |
Developer, Financial manager, Project planner, Technical engineer |
$13,440.00 |
Prototype design |
6 days |
Tue 4/24/18 |
Tue 5/1/18 |
18 |
Project manager, equipment [1],Project planner, System analyst |
$18,240.00 |
Milestone 3: Completion of design phase |
0 days |
Tue 5/1/18 |
Tue 5/1/18 |
19 |
$0.00 |
|
Development phase |
36 days |
Wed 5/2/18 |
Wed 6/20/18 |
$68,240.00 |
||
CMS implementation |
7 days |
Wed 5/2/18 |
Thu 5/10/18 |
19 |
materials [1],Project planner, Risk analyst |
$12,320.00 |
Front-end development |
8 days |
Fri 5/11/18 |
Tue 5/22/18 |
22 |
Developer, Financial manager, System analyst |
$23,040.00 |
Back-end development |
9 days |
Wed 5/23/18 |
Mon 6/4/18 |
23 |
Developer, equipment [1],materials [1],service |
$7,920.00 |
Database development |
12 days |
Tue 6/5/18 |
Wed 6/20/18 |
24 |
Developer, Project manager |
$24,960.00 |
Milestone 4: Completion of development phase |
0 days |
Wed 6/20/18 |
Wed 6/20/18 |
25 |
$0.00 |
|
Testing phase |
22 days |
Thu 6/21/18 |
Fri 7/20/18 |
$48,800.00 |
||
Black box testing |
5 days |
Thu 6/21/18 |
Wed 6/27/18 |
26 |
Project manager, Project planner, service |
$10,000.00 |
User acceptance testing |
8 days |
Thu 6/28/18 |
Mon 7/9/18 |
28 |
Developer, Project planner, Risk analyst, statutory cost ,System analyst |
$29,440.00 |
Compatibility testing |
9 days |
Tue 7/10/18 |
Fri 7/20/18 |
29 |
statutory cost ,System analyst |
$9,360.00 |
Milestone 5: Completion of testing phase |
0 days |
Fri 7/20/18 |
Fri 7/20/18 |
30 |
$0.00 |
|
Closure phase |
9 days |
Mon 7/23/18 |
Thu 8/2/18 |
$20,800.00 |
||
Hosting of the website |
3 days |
Mon 7/23/18 |
Wed 7/25/18 |
30 |
Project manager, Fees and charges ,Project planner, Technical engineer |
$8,160.00 |
Post-project review |
2 days |
Thu 7/26/18 |
Fri 7/27/18 |
33 |
Project manager, Project planner |
$4,000.00 |
Stakeholder analysis |
2 days |
Mon 7/30/18 |
Tue 7/31/18 |
34 |
Developer, Fees and charges ,Project planner, statutory cost |
$3,360.00 |
Documentation |
2 days |
Wed 8/1/18 |
Thu 8/2/18 |
35 |
Developer, Fees and charges ,System analyst, Technical engineer |
$5,280.00 |
Milestone 6: Completion of closure phase |
0 days |
Thu 8/2/18 |
Thu 8/2/18 |
36 |
$0.00 |
Review of the project performance in terms of cost management
The effectiveness of the estimated cost or cost management plan for the project can be measured by evaluation through performance measurement. The components analyzed for reviewing the project performance and progress are as follows:
In order to improve the issues those might have occurs during the implementation of the project, are as shown in the below table:
Date |
Description of the problem or opportunity |
Recommended action for the next time/project |
lesson learned raised by |
22/02/2018 |
Wrong assumptions in cost emerge |
In order to avoid the issues of cost emerge the project manager is required to make an activity feasibility study. It is expected that with the help of proper feasibility study the project manager will get to know about whether the project outcome is beneficial or not. |
|
26/02/2018 |
Incorrect cost forecast |
In order to reduce the issues of incorrect project forecast, the project manager is needed to consider additional budget and resources as well so that those can be used whenever required. |
|
01/03/2018 |
Incorrect contract formulation |
Proper policy and guidelines are required to set by the project manager before formulating the contract. If any contractor is found breaking the rules then, penalty policy should be incorporated. |
|
5/04/2018 |
Pinpoint improvement opportunity failure |
Any project should be developed based upon the benefits could be obtained from it. It is the responsibility of the project manager. If it is found that from the strength of the project no such opportunity could be gained then the pinpoint of the project should be implemented. |
|
24/6/2018 |
Issues in over budget |
For some of the activities it has been found that the estimated budget is exceeding. Therefore, at the project planning phase based on the details of the activities, budget the project manager and the finance manager should estimate the budget |
The existing website of the company does not hold all the necessary components therefore the website should be improved with different essential technical functions and operations. The recommendations needed to be followed by the website developer and analysts are as follows:
Using attractive photos of the product and services: In order to attract and grab more number of consumers the project manager should use attractive photos of both the products and services to be served by the company.
Merchandize the products and services: Around 2/3 of the total sales of the company is depends upon merchandizing. In order to keep the things consistent the services and products of the company is needed to be well categorized. Besides this, the detail information of the services and products are also needed to be categorized in the website.
Easy website navigation: The project manager must ensure that the structure of the website is well organized and designed in such a way so that the visitors can browse the search engine very easily.
References
Alotaibi, A. B., and Mafimisebi, O. P. 2016. Project Management Practice: Redefining Theoretical Challenges in the 21st Century. Project Management, 7(1).
Beringer, C., Jonas, D. and Kock, A., 2013. Behavior of internal stakeholders in project portfolio management and its impact on success. International Journal of Project Management, 31(6), pp.830-846.
Burke, R., 2013. Project management: planning and control techniques. New Jersey, USA.
Chia, R. 2013. Paradigms and perspectives in organizational project management research: implications for knowledge creation. Novel Approaches to Organizational Project Management Research: Translational and Transformational. Copenhagen Business School Press, Copenhagen, 33-55.
Fitzsimmons, J., and Fitzsimmons, M. 2013. Service management: Operations, strategy, information technology. McGraw-Hill Higher Education.
Fleming, Q.W. and Koppelman, J.M., 2016, December. Earned value project management. Project Management Institute.
Fleming, Q.W. and Koppelman, J.M., 2016, December. Earned value project management. Project Management Institute.
Kerzner, H. and Kerzner, H.R., 2017. Project management: a systems approach to planning, scheduling, and controlling. John Wiley & Sons.
Martinsuo, M. 2013. Project portfolio management in practice and in context. International Journal of Project Management, 31(6), 794-803.
Mir, F.A. and Pinnington, A.H., 2014. Exploring the value of project management: linking project management performance and project success. International journal of project management, 32(2), pp.202-217.
Pemsel, S., and Wiewiora, A. 2013. Project management office a knowledge broker in project-based organisations. International Journal of Project Management, 31(1), 31-42.
Phillips, J. 2013. PMP, Project Management Professional (Certification Study Guides). McGraw-Hill Osborne Media.
Pinto, J.K., 2015. Project management: achieving competitive advantage. Prentice Hall.
Schumann, C. A., Gerischer, H., Tittmann, C., Orth, H., Xiao, F., Schwarz, B., and Schumann, M. A. 2014. Development of International Educational Systems by Competence Networking based on Project Management. Procedia-Social and Behavioral Sciences, 119, 192-201.
Sears, S. K., Sears, G. A., Clough, R. H., Rounds, J. L., and Segner, R. O. 2015. Construction project management. John Wiley & Sons.
Snyder, C.S., 2014. A guide to the project management body of knowledge: PMBOK (®) guide. Project Management Institute: Newtown Square, PA, USA.
Essay Writing Service Features
Our Experience
No matter how complex your assignment is, we can find the right professional for your specific task. Contact Essay is an essay writing company that hires only the smartest minds to help you with your projects. Our expertise allows us to provide students with high-quality academic writing, editing & proofreading services.Free Features
Free revision policy
$10Free bibliography & reference
$8Free title page
$8Free formatting
$8How Our Essay Writing Service Works
First, you will need to complete an order form. It's not difficult but, in case there is anything you find not to be clear, you may always call us so that we can guide you through it. On the order form, you will need to include some basic information concerning your order: subject, topic, number of pages, etc. We also encourage our clients to upload any relevant information or sources that will help.
Complete the order formOnce we have all the information and instructions that we need, we select the most suitable writer for your assignment. While everything seems to be clear, the writer, who has complete knowledge of the subject, may need clarification from you. It is at that point that you would receive a call or email from us.
Writer’s assignmentAs soon as the writer has finished, it will be delivered both to the website and to your email address so that you will not miss it. If your deadline is close at hand, we will place a call to you to make sure that you receive the paper on time.
Completing the order and download