Discuss about the Case Study of Implementing IS at BilbioZ.
Gantt chart is usually utilized within the project management approach. This technique is one of the most effective ways of representing the activities of the project that is visualized against the time period. On the left of the Gantt chart, the activities are visualized and on the right side and on the left side, the appropriate time schedule is shown (Dayani and Gelbard 2015). The Gantt chart is beneficial to track the project progress against the predefined deadline of the project activities. The Gantt chart is able to visualize the start and finish date of individual activities within the project. This technique can be used for small and complex, both the projects but the use of the tool for different projects is based on the complexity (Baker and Trietsch 2013). Taken as an example, for simple project, the spreadsheet can be used but for complex and big projects project management software is the suitable choice.
The Gantt chart is able to provide clarity regarding the tasks of the project. This is possible because the chart holds the activities of the project as well as time within the same document. The stakeholders are able to recognize which part of the project is in progress and the resources allocated to it. Various project management software is able to represent the recourses that are associated with the task (Schwalbe 2015). The Gantt chart is also serves as an internal motivation to the project team members. The chart allows the team members of the project to concentrate on the project activities more as it allows tracking the tasks.
The selected organization is specialist in selling the collectible and rare books. These books are collected from the different market places from the whole world. The organization was created in 2000 (Biblio.com, 2017). The organization is currently managing the internal tasks manually. Maintain the business operations is very critical for the organization staff. Because of the existing manual operations, the error in the business operation is very high.
BiblioZ is currently considering implementing an information system within the organization in order to making the business processes automatic. The system will be implemented through the SDLC approach. A project manager will be employed for managing tasks. The project manager will be responsible for creating the Gantt chart of the project. The project manager will provide the Gantt chart to the stakeholders of the project.
The Gantt chart of the information system implementation at BiblioZ has been presented in the table 1. The Gantt chart consists of activities, time frame (starting and ending time of the project activities), and predecessor of each activity, resource name and cost of the project.
WBS |
Task Name |
Duration |
Start |
Finish |
Predecessors |
Resource Names |
Cost |
0 |
Information System Implementation at BiblioZ |
148 days |
Mon 9/4/17 |
Wed 3/28/18 |
$107,400.00 |
||
1 |
Project Planning |
53 days |
Mon 9/4/17 |
Wed 11/15/17 |
$24,600.00 |
||
1.1 |
Project Charter Creating |
2 days |
Sat 9/9/17 |
Tue 9/12/17 |
Project manager |
$1,200.00 |
|
1.2 |
Defining Scope of the Project |
2 days |
Sat 9/9/17 |
Tue 9/12/17 |
2 |
Project manager |
$1,200.00 |
1.3 |
Identifying the Potential Team Members |
2 days |
Sat 9/9/17 |
Tue 9/12/17 |
3 |
Project manager, Administration officer |
$1,920.00 |
1.4 |
Defining Responsibility and Role |
2 days |
Sat 9/9/17 |
Tue 9/12/17 |
4 |
Administration officer, Project manager |
$1,920.00 |
1.5 |
Scheduling Kickoff Meeting |
2 days |
Sun 9/10/17 |
Tue 9/12/17 |
5 |
Administration officer |
$720.00 |
1.6 |
Distributing Project Plan |
3 days |
Mon 9/11/17 |
Wed 9/13/17 |
5 |
Administration officer |
$1,080.00 |
1.7 |
Signing Contract with the Third Party System Vendor |
1 day |
Mon 9/11/17 |
Mon 9/11/17 |
4,5 |
Administration officer |
$360.00 |
1.8 |
Generating Baseline of Scope |
3 days |
Tue 9/12/17 |
Thu 9/14/17 |
8 |
Project manager |
$1,800.00 |
1.9 |
Generating Cost Baseline and Schedule |
3 days |
Tue 9/12/17 |
Thu 9/14/17 |
9 |
Project manager |
$1,800.00 |
1.10 |
Recognition of Risks Associated with Project |
4 days |
Mon 9/4/17 |
Thu 9/7/17 |
10 |
Project manager |
$2,400.00 |
1.11 |
Development of Strategies regarding Risk Management |
5 days |
Fri 10/13/17 |
Tue 10/24/17 |
11 |
Project manager |
$3,000.00 |
1.12 |
Development of Time Management Approach |
3 days |
Tue 10/31/17 |
Thu 11/2/17 |
12 |
Project manager |
$1,800.00 |
1.13 |
Development Resource Management Approach |
2 days |
Fri 11/3/17 |
Mon 11/6/17 |
13 |
Project manager |
$1,200.00 |
1.14 |
Project Schedule Development |
2 days |
Tue 11/7/17 |
Wed 11/8/17 |
14 |
Project manager |
$1,200.00 |
1.15 |
Project Budget Estimation |
5 days |
Thu 11/9/17 |
Wed 11/15/17 |
15 |
Project manager |
$3,000.00 |
1.16 |
Completion of Project Plan |
0 days |
Sat 9/9/17 |
Sat 9/9/17 |
$0.00 |
||
2 |
Requirement Analysis |
28 days |
Mon 9/4/17 |
Wed 10/11/17 |
$17,160.00 |
||
2.1 |
Recognition of fact Finding Techniques |
2 days |
Fri 9/15/17 |
Mon 9/18/17 |
17 |
Business analyst |
$880.00 |
2.2 |
Collecting Information through fact Finding Approach |
10 days |
Mon 9/18/17 |
Fri 9/29/17 |
19 |
Business analyst |
$4,400.00 |
2.3 |
Analyzing the Gathered Data |
3 days |
Wed 9/20/17 |
Fri 9/22/17 |
20 |
Programmer |
$1,080.00 |
2.4 |
Recognizing the Requirements of the System |
8 days |
Mon 9/4/17 |
Wed 9/27/17 |
21 |
Programmer, Project manager |
$7,680.00 |
2.5 |
Investigating the System Requirements |
4 days |
Wed 10/4/17 |
Mon 10/9/17 |
22 |
Project manager |
$2,400.00 |
2.6 |
Documenting the System Requirements |
2 days |
Tue 10/10/17 |
Wed 10/11/17 |
23 |
Administration officer |
$720.00 |
2.7 |
Completion of Requirement Analysis |
0 days |
Wed 10/11/17 |
Wed 10/11/17 |
24 |
$0.00 |
|
3 |
Designing Phase |
33 days |
Thu 10/12/17 |
Mon 11/27/17 |
$17,880.00 |
||
3.1 |
Getting the Requirements of the System |
1 day |
Thu 10/12/17 |
Thu 10/12/17 |
25 |
Administration officer |
$360.00 |
3.2 |
System Requirement Investigation |
8 days |
Thu 10/26/17 |
Mon 11/6/17 |
27 |
Project manager |
$4,800.00 |
3.3 |
Generating the Functions of the System |
9 days |
Fri 10/13/17 |
Wed 10/25/17 |
25,27 |
Programmer |
$3,240.00 |
3.4 |
System Unit Designing |
7 days |
Thu 10/26/17 |
Fri 11/3/17 |
29 |
Programmer |
$2,520.00 |
3.5 |
Designing UI or User Interface |
5 days |
Mon 11/6/17 |
Fri 11/10/17 |
30 |
Graphical user interface developer |
$1,400.00 |
3.6 |
Architecture of the System |
6 days |
Mon 11/13/17 |
Mon 11/20/17 |
31 |
Programmer |
$2,160.00 |
3.7 |
Database Design |
4 days |
Tue 11/21/17 |
Fri 11/24/17 |
32 |
Database developer |
$1,600.00 |
3.8 |
Network Design |
5 days |
Tue 11/21/17 |
Mon 11/27/17 |
31,32 |
Programmer |
$1,800.00 |
3.9 |
Completion of Design Phase |
0 days |
Mon 11/27/17 |
Mon 11/27/17 |
34 |
$0.00 |
|
4 |
Development Phase |
87 days |
Tue 11/28/17 |
Wed 3/28/18 |
$44,960.00 |
||
4.1 |
Starts Creating the Program |
25 days |
Tue 11/28/17 |
Mon 1/1/18 |
35 |
Programmer |
$9,000.00 |
4.2 |
Development of System |
25 days |
Tue 1/2/18 |
Mon 2/5/18 |
35,37 |
Graphical user interface developer, Programmer |
$16,000.00 |
4.3 |
Creating the Database |
15 days |
Tue 2/6/18 |
Mon 2/26/18 |
38 |
Database developer |
$6,000.00 |
4.4 |
Implementation System Network |
17 days |
Wed 2/28/18 |
Wed 3/28/18 |
39 |
Programmer |
$6,120.00 |
4.5 |
Developing User Interface |
12 days |
Tue 2/6/18 |
Wed 2/21/18 |
37 |
Graphical user interface developer |
$3,360.00 |
4.6 |
Establishing Connection between System and Database |
7 days |
Thu 2/22/18 |
Fri 3/2/18 |
41 |
Database developer, Programmer |
$3,040.00 |
4.7 |
Establishing Connection between System and Website |
3 days |
Mon 3/5/18 |
Wed 3/7/18 |
42 |
$0.00 |
|
4.8 |
Establishing Connection between System and Network |
4 days |
Mon 3/5/18 |
Thu 3/8/18 |
42 |
Programmer |
$1,440.00 |
4.9 |
Completion of Development Phase |
0 days |
Thu 3/8/18 |
Thu 3/8/18 |
44 |
$0.00 |
|
5 |
Testing Phase |
6 days |
Fri 3/9/18 |
Fri 3/16/18 |
$2,400.00 |
||
5.1 |
Design/Requirements Review |
1 day |
Fri 3/9/18 |
Fri 3/9/18 |
45 |
Tester |
$400.00 |
5.2 |
Test Planning |
1 day |
Mon 3/12/18 |
Mon 3/12/18 |
47 |
Tester |
$400.00 |
5.3 |
Test Design |
1 day |
Tue 3/13/18 |
Tue 3/13/18 |
48 |
Tester |
$400.00 |
5.4 |
Test Environment Setup |
1 day |
Wed 3/14/18 |
Wed 3/14/18 |
49 |
Tester |
$400.00 |
5.5 |
Test Execution |
1 day |
Thu 3/15/18 |
Thu 3/15/18 |
50 |
Tester |
$400.00 |
5.6 |
Test Reporting |
1 day |
Fri 3/16/18 |
Fri 3/16/18 |
51 |
Tester |
$400.00 |
5.7 |
Testing Phase Complete |
0 days |
Fri 3/16/18 |
Fri 3/16/18 |
52 |
$0.00 |
|
6 |
Deployment Phase |
1 day |
Mon 3/19/18 |
Mon 3/19/18 |
$400.00 |
||
6.1 |
Deploying System in Bilblio Environment |
1 day |
Mon 3/19/18 |
Mon 3/19/18 |
53 |
Tester |
$400.00 |
6.2 |
Deployment Complete |
0 days |
Mon 3/19/18 |
Mon 3/19/18 |
55 |
$0.00 |
Table 1: Schedule of the Proposed Project
(Source: Created by Author)
The project schedule of the proposed project management visualizes five phases. This phases are also consisting of different sub-tasks. The chart shows the time frame for each of the tasks including the phases. The predecessor implies the task after which the project task will be carried out. This schedule will be provided to all of the project team members so that all the members can identify its job related data accurately. Within the Gantt chart, the resources (only the human resources) has been considered. Some of the tasks are carried out by single member and some are done collaboratively. The project is consisting of more than 50 activities.
Conclusion:
From the above study it can be concluded that the Gantt chart is a very special technique of making the project schedule. As it can be seen the project is a very lengthy project. For this reason the project management software has been used for developing the system instead of spread sheet. The project management software allowed to auto calculate the timing of the project based on the task duration and predecessor. Project schedule will serve as a great source of managing the project tasks for the Bilbio Information System project. A lot of a supervisor’s workday is spent putting out flames. There appear to be such a large number of crises that you and no one but you can react to. Bunch’s notable time administration grid shows the four classifications of time consumption, including that notorious “fire” classification. As the human resources required for the project has been bee represented through the chart, the project manager now can concentrate on the project core activities without having any second thoughts about the resource allocation. In the field of time administration, lumping enables you to arrange your undertakings such that you deal with comparable exercises at a specific time.
Baker, K.R. and Trietsch, D., 2013. Principles of sequencing and scheduling. John Wiley & Sons.
Biblio.com. (2017). Biblio.com | Used Books and Rare Books from Antiquarian Booksellers. [online] Available at: https://www.biblio.com/ [Accessed 9 Sep. 2017].
Browning, T.R., 2014. Managing complex project process models with a process architecture framework. International Journal of Project Management, 32(2), pp.229-241.
Dayani, M. and Gelbard, R., 2015. Automatic Conversion of Software Specification into a Gantt-chart subject to Organization’s Constraints. Procedia Computer Science, 64, pp.73-78.
Fleming, Q.W. and Koppelman, J.M., 2016. Earned value project management. Project Management Institute.
Golini, R., Kalchschmidt, M. and Landoni, P., 2015. Adoption of project management practices: the impact on international development projects of non-governmental organizations. International Journal of Project Management, 33(3), pp.650-663.
Heizer, J., 2016. Operations Management, 11/e. Pearson Education India.
Kerzner, H., 2013. Project management: a systems approach to planning, scheduling, and controlling. John Wiley & Sons.
Landry, J.P. and McDaniel, R., 2015. Agile Preparation Within a Traditional Project Management Course. In Proceedings of the EDSIG Conference (p. n3429).
Riol, H. and Thuillier, D., 2015. Project management for academic research projects: balancing structure and flexibility. International Journal of Project Organisation and Management, 7(3), pp.251-269.
Schillemans, K. and Robinson, L., 2015. Team and project management skills. OPTIMAX 2015, p.15.
Schwalbe, K., 2015. Information technology project management. Cengage Learning.
Essay Writing Service Features
Our Experience
No matter how complex your assignment is, we can find the right professional for your specific task. Contact Essay is an essay writing company that hires only the smartest minds to help you with your projects. Our expertise allows us to provide students with high-quality academic writing, editing & proofreading services.Free Features
Free revision policy
$10Free bibliography & reference
$8Free title page
$8Free formatting
$8How Our Essay Writing Service Works
First, you will need to complete an order form. It's not difficult but, in case there is anything you find not to be clear, you may always call us so that we can guide you through it. On the order form, you will need to include some basic information concerning your order: subject, topic, number of pages, etc. We also encourage our clients to upload any relevant information or sources that will help.
Complete the order formOnce we have all the information and instructions that we need, we select the most suitable writer for your assignment. While everything seems to be clear, the writer, who has complete knowledge of the subject, may need clarification from you. It is at that point that you would receive a call or email from us.
Writer’s assignmentAs soon as the writer has finished, it will be delivered both to the website and to your email address so that you will not miss it. If your deadline is close at hand, we will place a call to you to make sure that you receive the paper on time.
Completing the order and download