Task Name |
Completion time |
Start |
Finish |
Early Start |
Early Finish |
Late Start |
Late Finish |
Free Slack |
Predecessors |
Activity |
19 wks |
Thu 3/8/18 |
Wed 7/18/18 |
Thu 3/8/18 |
Wed 7/18/18 |
Thu 3/8/18 |
Wed 7/18/18 |
0 wks |
|
A |
3 wks |
Thu 3/8/18 |
Wed 3/28/18 |
Thu 3/8/18 |
Wed 3/28/18 |
Thu 3/8/18 |
Wed 3/28/18 |
0 wks |
|
B |
4 wks |
Thu 3/8/18 |
Wed 4/4/18 |
Thu 3/8/18 |
Wed 4/4/18 |
Thu 3/15/18 |
Wed 4/11/18 |
0 wks |
|
C |
4 wks |
Thu 3/8/18 |
Wed 4/4/18 |
Thu 3/8/18 |
Wed 4/4/18 |
Thu 3/15/18 |
Wed 4/11/18 |
0 wks |
|
D |
4 wks |
Thu 3/29/18 |
Wed 4/25/18 |
Thu 3/29/18 |
Wed 4/25/18 |
Thu 3/29/18 |
Wed 4/25/18 |
0 wks |
1 |
E |
4 wks |
Thu 3/29/18 |
Wed 4/25/18 |
Thu 3/29/18 |
Wed 4/25/18 |
Thu 5/31/18 |
Wed 6/27/18 |
9 wks |
1 |
F |
2 wks |
Thu 4/5/18 |
Wed 4/18/18 |
Thu 4/5/18 |
Wed 4/18/18 |
Thu 4/12/18 |
Wed 4/25/18 |
1 wk |
2 |
G |
3 wks |
Thu 4/5/18 |
Wed 4/25/18 |
Thu 4/5/18 |
Wed 4/25/18 |
Thu 5/3/18 |
Wed 5/23/18 |
4 wks |
2 |
H |
4 wks |
Thu 4/5/18 |
Wed 5/2/18 |
Thu 4/5/18 |
Wed 5/2/18 |
Thu 4/26/18 |
Wed 5/23/18 |
2 wks |
2 |
I |
6 wks |
Thu 4/5/18 |
Wed 5/16/18 |
Thu 4/5/18 |
Wed 5/16/18 |
Thu 4/12/18 |
Wed 5/23/18 |
0 wks |
3 |
J |
4 wks |
Thu 4/5/18 |
Wed 5/2/18 |
Thu 4/5/18 |
Wed 5/2/18 |
Thu 5/3/18 |
Wed 5/30/18 |
0 wks |
3 |
K |
4 wks |
Thu 4/26/18 |
Wed 5/23/18 |
Thu 4/26/18 |
Wed 5/23/18 |
Thu 4/26/18 |
Wed 5/23/18 |
0 wks |
4,6 |
L |
5 wks |
Thu 5/24/18 |
Wed 6/27/18 |
Thu 5/24/18 |
Wed 6/27/18 |
Thu 5/24/18 |
Wed 6/27/18 |
0 wks |
7,11 |
M |
5 wks |
Thu 5/17/18 |
Wed 6/20/18 |
Thu 5/17/18 |
Wed 6/20/18 |
Thu 5/24/18 |
Wed 6/27/18 |
1 wk |
8,9 |
N |
4 wks |
Thu 5/3/18 |
Wed 5/30/18 |
Thu 5/3/18 |
Wed 5/30/18 |
Thu 5/31/18 |
Wed 6/27/18 |
4 wks |
10 |
O |
3 wks |
Thu 6/28/18 |
Wed 7/18/18 |
Thu 6/28/18 |
Wed 7/18/18 |
Thu 6/28/18 |
Wed 7/18/18 |
0 wks |
5,12,13,14 |
2.1 Task D gets delayed to 2 weeks. So, overall project completion time changes from 19 weeks to 21 weeks.
Task Name |
Completion time |
Start |
Finish |
Early Start |
Early Finish |
Late Start |
Late Finish |
Free Slack |
Predecessors |
Activity |
21 wks |
Thu 08-03-18 |
Wed 01-08-18 |
Thu 08-03-18 |
Wed 01-08-18 |
Thu 08-03-18 |
Wed 01-08-18 |
0 wks |
|
A |
3 wks |
Thu 08-03-18 |
Wed 28-03-18 |
Thu 08-03-18 |
Wed 28-03-18 |
Thu 08-03-18 |
Wed 28-03-18 |
0 wks |
|
B |
4 wks |
Thu 08-03-18 |
Wed 04-04-18 |
Thu 08-03-18 |
Wed 04-04-18 |
Thu 29-03-18 |
Wed 25-04-18 |
0 wks |
|
C |
4 wks |
Thu 08-03-18 |
Wed 04-04-18 |
Thu 08-03-18 |
Wed 04-04-18 |
Thu 29-03-18 |
Wed 25-04-18 |
0 wks |
|
D |
6 wks |
Thu 29-03-18 |
Wed 09-05-18 |
Thu 29-03-18 |
Wed 09-05-18 |
Thu 29-03-18 |
Wed 09-05-18 |
0 wks |
1 |
E |
4 wks |
Thu 29-03-18 |
Wed 25-04-18 |
Thu 29-03-18 |
Wed 25-04-18 |
Thu 14-06-18 |
Wed 11-07-18 |
11 wks |
1 |
F |
2 wks |
Thu 05-04-18 |
Wed 18-04-18 |
Thu 05-04-18 |
Wed 18-04-18 |
Thu 26-04-18 |
Wed 09-05-18 |
3 wks |
2 |
G |
3 wks |
Thu 05-04-18 |
Wed 25-04-18 |
Thu 05-04-18 |
Wed 25-04-18 |
Thu 17-05-18 |
Wed 06-06-18 |
6 wks |
2 |
H |
4 wks |
Thu 05-04-18 |
Wed 02-05-18 |
Thu 05-04-18 |
Wed 02-05-18 |
Thu 10-05-18 |
Wed 06-06-18 |
2 wks |
2 |
I |
6 wks |
Thu 05-04-18 |
Wed 16-05-18 |
Thu 05-04-18 |
Wed 16-05-18 |
Thu 26-04-18 |
Wed 06-06-18 |
0 wks |
3 |
J |
4 wks |
Thu 05-04-18 |
Wed 02-05-18 |
Thu 05-04-18 |
Wed 02-05-18 |
Thu 17-05-18 |
Wed 13-06-18 |
0 wks |
3 |
K |
4 wks |
Thu 10-05-18 |
Wed 06-06-18 |
Thu 10-05-18 |
Wed 06-06-18 |
Thu 10-05-18 |
Wed 06-06-18 |
0 wks |
4,6 |
L |
5 wks |
Thu 07-06-18 |
Wed 11-07-18 |
Thu 07-06-18 |
Wed 11-07-18 |
Thu 07-06-18 |
Wed 11-07-18 |
0 wks |
7,11 |
M |
5 wks |
Thu 17-05-18 |
Wed 20-06-18 |
Thu 17-05-18 |
Wed 20-06-18 |
Thu 07-06-18 |
Wed 11-07-18 |
3 wks |
8,9 |
N |
4 wks |
Thu 03-05-18 |
Wed 30-05-18 |
Thu 03-05-18 |
Wed 30-05-18 |
Thu 14-06-18 |
Wed 11-07-18 |
6 wks |
10 |
O |
3 wks |
Thu 12-07-18 |
Wed 01-08-18 |
Thu 12-07-18 |
Wed 01-08-18 |
Thu 12-07-18 |
Wed 01-08-18 |
0 wks |
5,12,13,14 |
2.2 Task G gets completed in 8 weeks. So, overall project completion time changes from 19 weeks to 20 weeks.
Task Name |
Completion time |
Start |
Finish |
Early Start |
Early Finish |
Late Start |
Late Finish |
Free Slack |
Predecessors |
Activity |
20 wks |
Thu 08-03-18 |
Wed 25-07-18 |
Thu 08-03-18 |
Wed 25-07-18 |
Thu 08-03-18 |
Wed 25-07-18 |
0 wks |
|
A |
3 wks |
Thu 08-03-18 |
Wed 28-03-18 |
Thu 08-03-18 |
Wed 28-03-18 |
Thu 15-03-18 |
Wed 04-04-18 |
0 wks |
|
B |
4 wks |
Thu 08-03-18 |
Wed 04-04-18 |
Thu 08-03-18 |
Wed 04-04-18 |
Thu 08-03-18 |
Wed 04-04-18 |
0 wks |
|
C |
4 wks |
Thu 08-03-18 |
Wed 04-04-18 |
Thu 08-03-18 |
Wed 04-04-18 |
Thu 22-03-18 |
Wed 18-04-18 |
0 wks |
|
D |
4 wks |
Thu 29-03-18 |
Wed 25-04-18 |
Thu 29-03-18 |
Wed 25-04-18 |
Thu 05-04-18 |
Wed 02-05-18 |
0 wks |
1 |
E |
4 wks |
Thu 29-03-18 |
Wed 25-04-18 |
Thu 29-03-18 |
Wed 25-04-18 |
Thu 07-06-18 |
Wed 04-07-18 |
10 wks |
1 |
F |
2 wks |
Thu 05-04-18 |
Wed 18-04-18 |
Thu 05-04-18 |
Wed 18-04-18 |
Thu 19-04-18 |
Wed 02-05-18 |
1 wk |
2 |
G |
8 wks |
Thu 05-04-18 |
Wed 30-05-18 |
Thu 05-04-18 |
Wed 30-05-18 |
Thu 05-04-18 |
Wed 30-05-18 |
0 wks |
2 |
H |
4 wks |
Thu 05-04-18 |
Wed 02-05-18 |
Thu 05-04-18 |
Wed 02-05-18 |
Thu 03-05-18 |
Wed 30-05-18 |
2 wks |
2 |
I |
6 wks |
Thu 05-04-18 |
Wed 16-05-18 |
Thu 05-04-18 |
Wed 16-05-18 |
Thu 19-04-18 |
Wed 30-05-18 |
0 wks |
3 |
J |
4 wks |
Thu 05-04-18 |
Wed 02-05-18 |
Thu 05-04-18 |
Wed 02-05-18 |
Thu 10-05-18 |
Wed 06-06-18 |
0 wks |
3 |
K |
4 wks |
Thu 26-04-18 |
Wed 23-05-18 |
Thu 26-04-18 |
Wed 23-05-18 |
Thu 03-05-18 |
Wed 30-05-18 |
1 wk |
4,6 |
L |
5 wks |
Thu 31-05-18 |
Wed 04-07-18 |
Thu 31-05-18 |
Wed 04-07-18 |
Thu 31-05-18 |
Wed 04-07-18 |
0 wks |
7,11 |
M |
5 wks |
Thu 17-05-18 |
Wed 20-06-18 |
Thu 17-05-18 |
Wed 20-06-18 |
Thu 31-05-18 |
Wed 04-07-18 |
2 wks |
8,9 |
N |
4 wks |
Thu 03-05-18 |
Wed 30-05-18 |
Thu 03-05-18 |
Wed 30-05-18 |
Thu 07-06-18 |
Wed 04-07-18 |
5 wks |
10 |
O |
3 wks |
Thu 05-07-18 |
Wed 25-07-18 |
Thu 05-07-18 |
Wed 25-07-18 |
Thu 05-07-18 |
Wed 25-07-18 |
0 wks |
5,12,13,14 |
The activity O cannot get started until at least 4 days after the activity M has finished. Therefore, the completion time for activity O is 5.4 weeks. The overall completion time of the project does not get affected.
Task Name |
Duration |
Start |
Finish |
Early Start |
Early Finish |
Late Start |
Late Finish |
Free Slack |
Predecessors |
Activity |
19 wks |
Thu 08-03-18 |
Wed 18-07-18 |
Thu 08-03-18 |
Wed 18-07-18 |
Thu 08-03-18 |
Wed 18-07-18 |
0 wks |
|
A |
3 wks |
Thu 08-03-18 |
Wed 28-03-18 |
Thu 08-03-18 |
Wed 28-03-18 |
Thu 08-03-18 |
Wed 28-03-18 |
0 wks |
|
B |
4 wks |
Thu 08-03-18 |
Wed 04-04-18 |
Thu 08-03-18 |
Wed 04-04-18 |
Thu 15-03-18 |
Wed 11-04-18 |
0 wks |
|
C |
4 wks |
Thu 08-03-18 |
Wed 04-04-18 |
Thu 08-03-18 |
Wed 04-04-18 |
Tue 13-03-18 |
Mon 09-04-18 |
0 wks |
|
D |
4 wks |
Thu 29-03-18 |
Wed 25-04-18 |
Thu 29-03-18 |
Wed 25-04-18 |
Thu 29-03-18 |
Wed 25-04-18 |
0 wks |
1 |
E |
4 wks |
Thu 29-03-18 |
Wed 25-04-18 |
Thu 29-03-18 |
Wed 25-04-18 |
Thu 31-05-18 |
Wed 27-06-18 |
9 wks |
1 |
F |
2 wks |
Thu 05-04-18 |
Wed 18-04-18 |
Thu 05-04-18 |
Wed 18-04-18 |
Thu 12-04-18 |
Wed 25-04-18 |
1 wk |
2 |
G |
3 wks |
Thu 05-04-18 |
Wed 25-04-18 |
Thu 05-04-18 |
Wed 25-04-18 |
Thu 03-05-18 |
Wed 23-05-18 |
4 wks |
2 |
H |
4 wks |
Thu 05-04-18 |
Wed 02-05-18 |
Thu 05-04-18 |
Wed 02-05-18 |
Tue 24-04-18 |
Mon 21-05-18 |
2 wks |
2 |
I |
6 wks |
Thu 05-04-18 |
Wed 16-05-18 |
Thu 05-04-18 |
Wed 16-05-18 |
Tue 10-04-18 |
Mon 21-05-18 |
0 wks |
3 |
J |
4 wks |
Thu 05-04-18 |
Wed 02-05-18 |
Thu 05-04-18 |
Wed 02-05-18 |
Thu 03-05-18 |
Wed 30-05-18 |
0 wks |
3 |
K |
4 wks |
Thu 26-04-18 |
Wed 23-05-18 |
Thu 26-04-18 |
Wed 23-05-18 |
Thu 26-04-18 |
Wed 23-05-18 |
0 wks |
4,6 |
L |
5 wks |
Thu 24-05-18 |
Wed 27-06-18 |
Thu 24-05-18 |
Wed 27-06-18 |
Thu 24-05-18 |
Wed 27-06-18 |
0 wks |
7,11 |
M |
5.4 wks |
Thu 17-05-18 |
Fri 22-06-18 |
Thu 17-05-18 |
Fri 22-06-18 |
Tue 22-05-18 |
Wed 27-06-18 |
0.6 wks |
8,9 |
N |
4 wks |
Thu 03-05-18 |
Wed 30-05-18 |
Thu 03-05-18 |
Wed 30-05-18 |
Thu 31-05-18 |
Wed 27-06-18 |
4 wks |
10 |
O |
3 wks |
Thu 28-06-18 |
Wed 18-07-18 |
Thu 28-06-18 |
Wed 18-07-18 |
Thu 28-06-18 |
Wed 18-07-18 |
0 wks |
5,12,13,14 |
Kerzner, H. and Kerzner, H.R., 2017. Project management: a systems approach to planning, scheduling, and controlling. John Wiley & Sons.
Pinto, J.K., 2015. Project management: achieving competitive advantage. Prentice Hall.
Essay Writing Service Features
Our Experience
No matter how complex your assignment is, we can find the right professional for your specific task. Contact Essay is an essay writing company that hires only the smartest minds to help you with your projects. Our expertise allows us to provide students with high-quality academic writing, editing & proofreading services.Free Features
Free revision policy
$10Free bibliography & reference
$8Free title page
$8Free formatting
$8How Our Essay Writing Service Works
First, you will need to complete an order form. It's not difficult but, in case there is anything you find not to be clear, you may always call us so that we can guide you through it. On the order form, you will need to include some basic information concerning your order: subject, topic, number of pages, etc. We also encourage our clients to upload any relevant information or sources that will help.
Complete the order formOnce we have all the information and instructions that we need, we select the most suitable writer for your assignment. While everything seems to be clear, the writer, who has complete knowledge of the subject, may need clarification from you. It is at that point that you would receive a call or email from us.
Writer’s assignmentAs soon as the writer has finished, it will be delivered both to the website and to your email address so that you will not miss it. If your deadline is close at hand, we will place a call to you to make sure that you receive the paper on time.
Completing the order and download