This report depicts the necessity of implementing strategic Management Information System (MIS) in the “Dairy Farm Group of Companies” for increasing the overall revenue structure (Lee et al. 2015). Due to lack of strategic alignment the company was facing major challenges and basically in order to combat that situation the company is willing to implement and advanced Information System for the overall organizational improvement.
The scope of the project including its objectives and constraints are also elaborated in this report. Apart from the project constraints the project overview the report also demonstrates the statement of project. In order to complete the project proper time scheduling and cost estimation is required to be done and for this implementation the whole project should be divided into small segments (Krajewski, Ritzman and Malhotra 2013). If all the employees play exact role then only the project will be executed appropriately.
The project statement includes the overall professional representation of the project. The statement for the project is given below:
In order to execute the project successfully, proper selection of project team members are required to be done by the executives of Dairy Farm Group of Companies. The members of the project team are as follows:
In order to complete the project successfully and to reduce the work burden from every individual the project manager is required to divide the work load equally among the project team members. It will help the project manager to complete the project, within allotted time phase. The RACI matrix for re-implementing the MIS for Dairy Farm Group of Companies is as follows:
WBS |
Task Name |
Project manager |
System analyst |
Business analyst |
Quality analyzer |
Application programmer |
Information system expert |
Executive system associate |
1 |
Schedule development for Dairy firm group and companies |
I |
R |
R |
R |
R |
R |
I |
1.1 |
Project initiation phase |
I |
R/A |
C |
C |
R/A |
C |
I |
1.1.1 |
Requirement gathering |
I |
R |
I |
R |
I |
R |
I |
1.1.2 |
Loophole analysis |
I |
R |
R |
R |
R |
R |
I |
1.1.3 |
Current situation analysis |
I |
R/A |
R/A |
R/A |
R/A |
C |
I |
1.1.4 |
Analysis of the requirement of the consumers of Dairy Farm Group of Companies |
R/A |
R/A |
R/A |
R/A |
R/A |
R/A |
I |
1.1.5 |
Analyzing the currently used information for the development of the Information system |
I |
R/A |
R/A |
R/A |
R/A |
R/A |
I |
1.1.6 |
Meeting with the stakeholders |
C |
C |
C |
C |
– |
R |
– |
1.2 |
Phase 1: For project documentation |
– |
– |
– |
– |
– |
R |
– |
1.2.1 |
Developing project scope statement |
– |
– |
– |
– |
– |
R |
– |
1.2.2 |
Evaluation of the functional requirement of the MIS system |
C |
I |
C |
I |
I |
R |
C |
1.2.3 |
Evaluation of the non-functional requirement of MIS system |
C |
C |
C |
I |
I |
R |
R/A |
1.2.4 |
Analyzing the documents needed to implement the MIS system |
R |
R |
R |
R |
R |
R |
R |
1.2.5 |
Documentation submission to the project manager |
R/A |
C |
R/A |
C |
R/A |
R |
C |
1.2.6 |
Proposal acceptance by the project manager |
R |
I |
R |
I |
R |
R |
I |
1.2.7 |
Acceptance of the required changes |
I |
I |
– |
I |
– |
R |
I |
1.2.8 |
Project time scheduling |
R |
– |
R |
– |
– |
R |
– |
1.2.9 |
Project budget estimation |
– |
I |
I |
I |
I |
R |
I |
1.2.10 |
Specification of the financial and time requirement of the project |
R |
R |
R |
R |
R |
R |
R |
1.2.11 |
Time and budget approval by the project management authority |
R |
R |
I |
– |
– |
– |
– |
1.2.12 |
Proposal approved by the project management authority of Dairy Farm Group of Companies |
R |
R |
R |
R |
R |
R |
C |
1.3 |
Phase 2:Team management |
I |
R |
R |
R |
C |
– |
C |
1.3.1 |
Decision making |
I |
R |
R |
R |
C |
– |
C |
1.3.1.1 |
Selection of project leader |
I |
I |
R |
I |
C |
R |
I |
1.3.1.2 |
Selection of project team members |
I |
A |
R |
A |
R |
A |
R |
1.3.1.3 |
Identifying project mission, vision and goal |
A |
A |
R |
A |
R |
R |
A |
1.3.1.4 |
Identification of team rules and regulation |
C |
A |
C |
C |
A |
C |
A |
1.3.1.5 |
Team member’s skills and knowledge identification |
– |
– |
R |
– |
– |
R |
– |
1.3.2 |
Decision on training |
R |
C |
R |
C |
R |
C |
R/A |
1.3.2.1 |
Source gathering for the MIS implementation |
R |
R/A |
C |
R |
C |
R |
C |
1.3.2.2 |
Identification of roles of the project team members |
C |
C |
R |
C |
R |
C |
R |
1.3.2.3 |
Training program development |
I |
R |
C |
R |
C |
R |
C |
1.4 |
Phase 3 : MIS system development |
I |
I |
I |
C |
I |
R |
R |
1.4.1 |
Approval for the system requirement |
R |
A |
R |
A |
R |
R |
A |
1.4.1.1 |
Prototype design |
I |
A |
A |
A |
A |
A |
A |
1.4.1.2 |
Development of project blueprint |
R |
I |
R |
I |
R |
R |
I |
1.4.1.3 |
Checking for the project blueprint |
– |
R |
– |
R |
R |
– |
– |
1.4.1.4 |
Feedback gathering for the required changes |
I |
R |
R |
I |
I |
I |
R |
1.4.1.5 |
Development of optional changes required for developing the system |
– |
– |
– |
– |
R |
– |
– |
1.4.1.6 |
Design approval by the management |
– |
– |
– |
R |
R |
R |
– |
1.4.2 |
Development of the information system |
R/I |
– |
– |
– |
– |
– |
– |
1.4.2.1 |
Final design implementation |
I |
A |
C |
R |
C |
R |
I |
1.4.2.2 |
Coding for the decision making approaches |
I |
I |
I |
R |
R |
R |
I |
1.4.2.3 |
System unit testing |
R/A |
I |
I |
I |
C |
C |
C |
1.4.2.4 |
System integrated testing |
I |
R/A |
– |
– |
– |
– |
C |
1.4.2.5 |
System installation |
I |
R |
– |
R |
C |
– |
R |
1.4.2.6 |
MIS implementation process |
I |
– |
– |
– |
C |
C |
R |
1.4.2.7 |
Preparation of the contingency planning |
I |
– |
– |
I |
R |
R |
R |
1.5 |
Phase 4: Developing training for the employees |
R |
C |
C |
R/A |
R |
R |
R |
1.5.1 |
User manual management illustration |
R/A |
– |
– |
– |
R/A |
– |
R/A |
1.5.2 |
Storage of relevant training materials |
R/A |
– |
– |
– |
– |
– |
|
1.5.3 |
Conduction of the training program |
I |
– |
– |
– |
– |
– |
– |
1.6 |
Phase 5: project closure phase |
R |
I |
I |
R |
I |
R |
I |
1.6.1 |
Review of the post implementation |
R |
R |
I |
R |
I |
R |
I |
1.6.2 |
Stakeholder’s signoff |
|
|
|
||||
1.6.3 |
Documentation of the resource requirements |
R/A |
I |
C |
I |
C |
I |
C |
1.6.4 |
Budget evaluation |
R/A |
R |
I |
R |
I |
|
I |
1.6.5 |
Project completion |
R/A |
– |
– |
– |
– |
– |
– |
1.4.2.4 |
System integrated testing |
– |
– |
R |
– |
– |
– |
– |
1.4.2.5 |
System installation |
I |
– |
– |
– |
– |
– |
– |
1.4.2.6 |
MIS implementation process |
I |
R |
C |
R |
C |
C |
R |
1.4.2.7 |
Preparation of the contingency planning |
I |
C R |
C |
R |
R |
R |
C |
1.5 |
Phase 4: Developing training for the employees |
I |
C |
I |
C |
I |
I |
I |
1.5.1 |
User manual management illustration |
I |
– |
R |
– |
R- |
– |
R |
1.5.2 |
Storage of relevant training materials |
I |
R |
R |
R |
R |
R |
R |
1.5.3 |
Conduction of the training program |
I |
C |
C |
C |
C |
C |
|
1.6 |
Phase 5: project closure phase |
I |
R/A |
R/A |
R/A |
R/A |
C |
C |
1.6.1 |
Review of the post implementation |
R |
R |
R |
R |
R |
R |
R |
1.6.2 |
Stakeholder’s signoff |
– |
– |
– |
– |
– |
– |
– |
1.6.3 |
Documentation of the resource requirements |
I |
I |
I |
I |
I |
I |
I |
1.6.4 |
Budget evaluation |
R/A |
R |
R |
R |
C |
R |
C |
1.6.5 |
Project completion |
I |
C |
R |
C |
C |
C |
R |
1.5.3 |
Conduction of the training program |
I |
R |
R |
– |
R |
R |
– |
1.6 |
Phase 5: project closure phase |
I |
– |
– |
– |
– |
– |
– |
1.6.1 |
Review of the post implementation |
I |
R/A |
R/A |
R |
R |
R |
R/A |
1.6.4 |
Budget evaluation |
I |
R/A |
– |
– |
R/A |
– |
R/A |
1.6.5 |
Project completion |
I |
R |
R |
R |
R |
R |
R |
WBS |
Task Name |
Duration |
Start |
Finish |
1 |
Schedule development for Dairy firm group and companies |
161 days |
Fri 4/28/17 |
Fri 12/8/17 |
1.1 |
Project initiation phase |
44 days |
Fri 4/28/17 |
Wed 6/28/17 |
1.1.1 |
Requirement gathering |
30 days |
Fri 4/28/17 |
Thu 6/8/17 |
1.1.2 |
Loophole analysis |
2 days |
Fri 6/9/17 |
Mon 6/12/17 |
1.1.3 |
Current situation analysis |
4 days |
Tue 6/13/17 |
Fri 6/16/17 |
1.1.4 |
Analysis of the requirement of the consumers of Dairy Farm Group of Companies |
2 days |
Mon 6/19/17 |
Tue 6/20/17 |
1.1.5 |
Analyzing the currently used information for the development of the Information system |
3 days |
Wed 6/21/17 |
Fri 6/23/17 |
1.1.6 |
Meeting with the stakeholders |
3 days |
Mon 6/26/17 |
Wed 6/28/17 |
1.2 |
Phase 1: For project documentation |
12 days |
Thu 6/29/17 |
Fri 7/14/17 |
1.2.1 |
Developing project scope statement |
1 day |
Thu 6/29/17 |
Thu 6/29/17 |
1.2.2 |
Evaluation of the functional requirement of the MIS system |
1 day |
Fri 6/30/17 |
Fri 6/30/17 |
1.2.3 |
Evaluation of the non-functional requirement of MIS system |
1 day |
Mon 7/3/17 |
Mon 7/3/17 |
1.2.4 |
Analyzing the documents needed to implement the MIS system |
1 day |
Tue 7/4/17 |
Tue 7/4/17 |
1.2.5 |
Documentation submission to the project manager |
1 day |
Wed 7/5/17 |
Wed 7/5/17 |
1.2.6 |
Proposal acceptance by the project manager |
1 day |
Thu 7/6/17 |
Thu 7/6/17 |
1.2.7 |
Acceptance of the required changes |
1 day |
Fri 7/7/17 |
Fri 7/7/17 |
1.2.8 |
Project time scheduling |
1 day |
Mon 7/10/17 |
Mon 7/10/17 |
1.2.9 |
Project budget estimation |
1 day |
Tue 7/11/17 |
Tue 7/11/17 |
1.2.10 |
Specification of the financial and time requirement of the project |
1 day |
Wed 7/12/17 |
Wed 7/12/17 |
1.2.11 |
Time and budget approval by the project management authority |
1 day |
Thu 7/13/17 |
Thu 7/13/17 |
1.2.12 |
Proposal approved by the project management authority of Dairy Farm Group of Companies |
1 day |
Fri 7/14/17 |
Fri 7/14/17 |
1.3 |
Phase 2:Team management |
35 days |
Tue 7/11/17 |
Mon 8/28/17 |
1.3.1 |
Decision making |
16 days |
Tue 7/11/17 |
Tue 8/1/17 |
1.3.1.1 |
Selection of project leader |
5 days |
Mon 7/17/17 |
Fri 7/21/17 |
1.3.1.2 |
Selection of project team members |
3 days |
Mon 7/24/17 |
Wed 7/26/17 |
1.3.1.3 |
Identifying project mission, vision and goal |
4 days |
Thu 7/27/17 |
Tue 8/1/17 |
1.3.1.4 |
Identification of team rules and regulation |
2 days |
Tue 7/11/17 |
Wed 7/12/17 |
1.3.1.5 |
Team member’s skills and knowledge identification |
3 days |
Thu 7/13/17 |
Mon 7/17/17 |
1.3.2 |
Decision on training |
30 days |
Tue 7/18/17 |
Mon 8/28/17 |
1.3.2.1 |
Source gathering for the MIS implementation |
10 days |
Tue 7/18/17 |
Mon 7/31/17 |
1.3.2.2 |
Identification of roles of the project team members |
10 days |
Tue 8/1/17 |
Mon 8/14/17 |
1.3.2.3 |
Training program development |
10 days |
Tue 8/15/17 |
Mon 8/28/17 |
1.4 |
Phase 3 : MIS system development |
29 days |
Tue 8/29/17 |
Fri 10/6/17 |
1.4.1 |
Approval for the system requirement |
14 days |
Tue 8/29/17 |
Fri 9/15/17 |
1.4.1.1 |
Prototype design |
9 days |
Tue 8/29/17 |
Fri 9/8/17 |
1.4.1.2 |
Development of project blueprint |
1 day |
Mon 9/11/17 |
Mon 9/11/17 |
1.4.1.3 |
Checking for the project blueprint |
1 day |
Tue 9/12/17 |
Tue 9/12/17 |
1.4.1.4 |
Feedback gathering for the required changes |
1 day |
Wed 9/13/17 |
Wed 9/13/17 |
1.4.1.5 |
Development of optional changes required for developing the system |
1 day |
Wed 9/13/17 |
Wed 9/13/17 |
1.4.1.6 |
Design approval by the management |
2 days |
Thu 9/14/17 |
Fri 9/15/17 |
1.4.2 |
Development of the information system |
15 days |
Mon 9/18/17 |
Fri 10/6/17 |
1.4.2.1 |
Final design implementation |
2 days |
Mon 9/18/17 |
Tue 9/19/17 |
1.4.2.2 |
Coding for the decision making approaches |
3 days |
Wed 9/20/17 |
Fri 9/22/17 |
1.4.2.3 |
System unit testing |
3 days |
Mon 9/25/17 |
Wed 9/27/17 |
1.4.2.4 |
System integrated testing |
2 days |
Thu 9/28/17 |
Fri 9/29/17 |
1.4.2.5 |
System installation |
2 days |
Mon 10/2/17 |
Tue 10/3/17 |
1.4.2.6 |
MIS implementation process |
2 days |
Wed 10/4/17 |
Thu 10/5/17 |
1.4.2.7 |
Preparation of the contingency planning |
1 day |
Fri 10/6/17 |
Fri 10/6/17 |
1.5 |
Phase 4: Developing training for the employees |
30 days |
Mon 10/9/17 |
Fri 11/17/17 |
1.5.1 |
User manual management illustration |
10 days |
Mon 10/9/17 |
Fri 10/20/17 |
1.5.2 |
Storage of relevant training materials |
10 days |
Mon 10/23/17 |
Fri 11/3/17 |
1.5.3 |
Conduction of the training program |
10 days |
Mon 11/6/17 |
Fri 11/17/17 |
1.6 |
Phase 5: project closure phase |
15 days |
Mon 11/20/17 |
Fri 12/8/17 |
1.6.1 |
Review of the post implementation |
3 days |
Mon 11/20/17 |
Wed 11/22/17 |
1.6.2 |
Stakeholder’s signoff |
1 day |
Thu 11/23/17 |
Thu 11/23/17 |
1.6.3 |
Documentation of the resource requirements |
5 days |
Fri 11/24/17 |
Thu 11/30/17 |
1.6.4 |
Budget evaluation |
2 days |
Fri 12/1/17 |
Mon 12/4/17 |
1.6.5 |
Project completion |
4 days |
Tue 12/5/17 |
Fri 12/8/17 |
In order to gain measurable success after the real time implementation of the project, the project manager must create secure relationship between the project development activities and the structure of Dairy firm and companies (Martinsuo and Killen 2014). For establishing this alignment the project manager is required to understand certain terms and condition accordingly.
Project vision: In this phase the project manager should understand the vision of the organization. In order to meet the vision the long term management plan is required to be considered.
Project mission: The mission of the company is to deliver quality milk products to the consumers with affordable price range (Mir and Pinnington 2014).
Organizational goal: In this phase the ultimate shared goal of the business firm is required to be set by the project manager.
Strategy development: In order to meet the requirement of the consumers the project manager is needed to develop certain business strategy so that the company will be able to reach the preliminary defied goal (Rahmana et al. 2014).
The diagram above elaborates the strategic execution stack of Dairy firm and companies. It helps the project manager and project executive team to understand the actual relationship among the different components of the project.
Security is one of the major concerns that are associated to the existing Managing Information System (MIS) used by the business organization (Silvius and Schipper 2014). Due to lack of security in the IS the external attackers can easily hijack information from the server, even without accurate authentication.
For this particular project triple constraints such as time scheduling, budget and scope have been considered. It has been found that, in order to re-implement the managing information system for Dairy firm and companies, the project that is developing required 8 months and AUD $800,000.
Different tools are there those are used by the Dairy firm and companies, to manage their stakeholders efficiently. In order to win support from others the stakeholder management acts as an important disciplinary tool (Takey and de Carvalho 2015). The project success can be effectively ensured by the stakeholder analysis and management. In order to shape the project accurately, idea from the important stakeholders are very much helpful. Certain steps are required to be maintained by the project manager to ensure that the proposed stakeholder analysis and management system is very effectives. The steps are as follows:
Step 1: Identification of the stakeholders
Name of the stakeholders |
Roles of the stakeholder |
Project Manager |
Monitoring project progress |
Systems Analyst |
Analyze both old and new MIS system |
Senior Associate |
Control the project |
Associate |
Control the project |
Application Programmer |
Develop the system by designing and coding |
Information System Expert |
Verify and validate the MIS |
Financial Analyst |
Estimate project budget |
Based on the roles and responsibilities of the project stakeholders the priorities will be provided (Walker 2015). After analysis it has been found that, the project manager plays the leading role in the project development period.
Conclusion
From the overall discussion it can be concluded that in order to reduce the issues of manual data management approach, Dairy firm and companies has planned to re-implement rather develop their existing Management Information System (MIS). The report elaborated the project objectives, project scope and project goal. Apart from this, the project also elaborated the stakeholder analysis and management and also described the current situation of the system that is the issues. After identifying the issues accurately the project manager will be able to understand the required changes that must be incorporated along with the existing managing information system of Dairy firm and companies. In this report the project schedule, roles and responsibility of the stakeholders are also demonstrated.
Almgren, K., 2014. Information technology project management processes and practices: A comprehensive study for successful implementation of IT projects. International Journal of Business and Social Science, 5(11).
Bentahar, O. and Cameron, R.A., 2015. Design and implementation of a mixed method research study in project management. Electronic Journal of Business Research Methods, 13(2).
Browning, T.R. and Ramasesh, R.V., 2015. Reducing unwelcome surprises in project management. MIT Sloan Management Review, 56(3), p.53.
Burke, R., 2013. Project management: planning and control techniques. New Jersey, USA.
Elbanna, S., 2015. Intuition in project management and missing links: Analyzing the predicating effects of environment and the mediating role of reflexivity. International Journal of Project Management, 33(6), pp.1236-1248.
Eskerod, P., Huemann, M. and Savage, G., 2015. Project stakeholder management—past and present. Project Management Journal, 46(6), pp.6-14.
Heagney, J., 2016. Fundamentals of project management. AMACOM Div American Mgmt Assn.
Heldman, K., 2015. PMP Project Management Professional Exam Deluxe Study Guide: Updated for the 2015 Exam. John Wiley & Sons.
Hwang, B.G. and Ng, W.J., 2013. Project management knowledge and skills for green construction: Overcoming challenges. International Journal of Project Management, 31(2), pp.272-284.
Katz, R., 2016. Challenges in doctoral research project management: A comparative study. International Journal of Doctoral Studies, 11.
Kerzner, H., 2013. Project management: a systems approach to planning, scheduling, and controlling. John Wiley & Sons.
Krajewski, L.J., Ritzman, L.P. and Malhotra, M.K., 2013. Operations management: Processes and supply chains (Vol. 1). New York: Pearson.
Lee, L., Reinicke, B., Sarkar, R. and Anderson, R., 2015. Learning through interactions: improving project management through communities of practice. Project Management Journal, 46(1), pp.40-52.
Marcelino-Sádaba, S., González-Jaen, L.F. and Pérez-Ezcurdia, A., 2015. Using project management as a way to sustainability. From a comprehensive review to a framework definition. Journal of cleaner production, 99, pp.1-16.
Martinsuo, M. and Killen, C.P., 2014. Value management in project portfolios: Identifying and assessing strategic value. Project Management Journal, 45(5), pp.56-70.
Mir, F.A. and Pinnington, A.H., 2014. Exploring the value of project management: linking project management performance and project success. International Journal of Project Management, 32(2), pp.202-217.
Rahmana, A., Kamil, M., Soemantri, E. and Olim, A., 2014. Integration of SERVQUAL and Kano model into QFD to improve quality of simulationbased training on project management. International Journal of Basic and Applied Science, 2(3), pp.59-72.
Shen, Y., Tuuli, M.M., Xia, B., Koh, T.Y. and Rowlinson, S., 2015. Toward a model for forming psychological safety climate in construction project management. International Journal of Project Management, 33(1), pp.223-235.
Silvius, A.G. and Schipper, R.P., 2014. Sustainability in project management competencies: analyzing the competence gap of project managers. Journal of Human Resource and Sustainability Studies, 2014.
Takey, S.M. and de Carvalho, M.M., 2015. Competency mapping in project management: An action research study in an engineering company. International Journal of Project Management, 33(4), pp.784-796.
Verzuh, E., 2015. The fast forward MBA in project management. John Wiley & Sons.
Walker, A., 2015. Project management in construction. John Wiley & Sons.
Essay Writing Service Features
Our Experience
No matter how complex your assignment is, we can find the right professional for your specific task. Contact Essay is an essay writing company that hires only the smartest minds to help you with your projects. Our expertise allows us to provide students with high-quality academic writing, editing & proofreading services.Free Features
Free revision policy
$10Free bibliography & reference
$8Free title page
$8Free formatting
$8How Our Essay Writing Service Works
First, you will need to complete an order form. It's not difficult but, in case there is anything you find not to be clear, you may always call us so that we can guide you through it. On the order form, you will need to include some basic information concerning your order: subject, topic, number of pages, etc. We also encourage our clients to upload any relevant information or sources that will help.
Complete the order formOnce we have all the information and instructions that we need, we select the most suitable writer for your assignment. While everything seems to be clear, the writer, who has complete knowledge of the subject, may need clarification from you. It is at that point that you would receive a call or email from us.
Writer’s assignmentAs soon as the writer has finished, it will be delivered both to the website and to your email address so that you will not miss it. If your deadline is close at hand, we will place a call to you to make sure that you receive the paper on time.
Completing the order and download