Identification of the Area of Impact
Factor |
Description |
Ranking |
Customer |
The focus of the customer is high on the project as Globex wants the application for its customers only |
1 |
Financial |
Economical impact on operations would be effective for the development of the successful execution of the activities. |
2 |
Operational |
Operations of the organization is a must as the application is supposed to make it more effective |
3 |
Strategy |
Strategies of implementing the development factors would be eased with the consideration of the factors and development. |
4 |
Social |
Social influence of operations would be implied with the involvement of the successive development factor. |
5 |
Value |
Metrics |
Time Frame |
Better |
Number of operations |
3 months |
Faster |
Delivery time |
2 months |
Cheaper |
Cost Incurred |
5 months |
Do More |
Effectiveness |
8 months |
In Scope
Resource Name |
Roles |
Financial manager |
Management of the Cash Application |
Project manager |
Management of the project activities |
Project planner |
Project Scheduling |
Developer |
Development of Application |
System engineer |
Integration of system functions |
Designer |
Design development |
Tester |
Testing the system for functions |
System analyst |
Analyzing the system requirements |
Database administrator |
Management of the database |
Human resource manager |
Management of the human resources |
Risk analyst |
Analyzing the project risks |
Programmer |
Programming the application |
System administrator |
Managing system functions |
Software engineer |
Integration of system functions |
Hardware and Network Requirements
Computer System, Router, Switch, and NIC card
Software Requirements
Application UI, Programming, Designing, and Testing Software
Facilities
High Level Work Break Down Structure
The Gantt chart for the project is shown below,
WBS |
Task Name |
Duration |
Start |
Finish |
M1 |
Kick off |
0 days |
Mon 8/6/18 |
Mon 8/6/18 |
M2 |
Plan Approval |
0 days |
Mon 8/20/18 |
Mon 8/20/18 |
M3 |
Design Approval |
0 days |
Tue 8/28/18 |
Tue 8/28/18 |
M4 |
System Developed |
0 days |
Thu 9/27/18 |
Thu 9/27/18 |
M5 |
Test Documentation |
0 days |
Thu 10/11/18 |
Thu 10/11/18 |
M6 |
System Live |
0 days |
Thu 10/18/18 |
Thu 10/18/18 |
M7 |
Project Closed |
0 days |
Mon 10/22/18 |
Mon 10/22/18 |
Resource Name |
Work |
Standard Rate |
Cost |
Financial manager |
80 hrs |
$ 70.00/hr |
$ 5,600.00 |
Project manager |
80 hrs |
$ 80.00/hr |
$ 6,400.00 |
Project planner |
56 hrs |
$ 40.00/hr |
$ 2,240.00 |
Developer |
64 hrs |
$ 60.00/hr |
$ 3,840.00 |
System engineer |
96 hrs |
$ 75.00/hr |
$ 7,200.00 |
Designer |
32 hrs |
$ 50.00/hr |
$ 1,600.00 |
Tester |
104 hrs |
$ 50.00/hr |
$ 5,200.00 |
System analyst |
32 hrs |
$ 55.00/hr |
$ 1,760.00 |
Database administrator |
64 hrs |
$ 60.00/hr |
$ 3,840.00 |
Human resource manager |
88 hrs |
$ 70.00/hr |
$ 6,160.00 |
Risk analyst |
80 hrs |
$ 40.00/hr |
$ 3,200.00 |
Programmer |
48 hrs |
$ 65.00/hr |
$ 3,120.00 |
System administrator |
128 hrs |
$ 70.00/hr |
$ 8,960.00 |
Software engineer |
104 hrs |
$ 75.00/hr |
$ 7,800.00 |
Hardware and software requirements |
1 |
$ 5,000.00 |
$ 5,000.00 |
Additional cost |
1 |
$ 3,000.00 |
$ 3,000.00 |
Total Budget |
$74,920.00 |
Assumptions
Risk |
Probability (1-5) |
Impact (1-5) |
Rating P*I |
Over budget |
4 |
3 |
8 |
Delay of Schedule |
5 |
2 |
10 |
Performance Issues |
3 |
5 |
15 |
Programming Errors |
2 |
4 |
8 |
Missing Function |
4 |
5 |
20 |
The new cash application for Globex would ensure that the requirements of the client for easing their customer’s operations would be done by following the engineering activities.
Testing methods of White Box, Black Box, User Interface. Prototyping, and Simulation would be used as verification activities.
Quality Control, Evaluation Checklist, and Feasible Project Plan analysis would be used as the validation activities.
Annotated Bibliography
Article: A computerized method for delay risk assessment based on fuzzy set theory using MS Project™
Journal: KSCE Journal of Civil Engineering
Authors: Budayan, C., Dikmen, I., Birgonul, M. T., and Ghaziani, A.
Year of Publication: 2018
Synopsis: According to Budayan, Dikmen, Birgonul and Ghaziani (2018), the Ms-Project software can be helpful for defining the influence of the risk management. The analysis of the fuzzy set theory would align with the development of the successive management of the activities and implying the innovative and improved functional management using successful development of project schedule using Ms-Project. The risk assessment is helpful for enduring the analysis of the factors for developing the successful integration and alignment of the cohesive project integration. The analysis would also be helpful for taking care of the risk assessment and development of the factors for the integration management. The integration would be aligned for the management of the successful formation and introducing the utilization and formation.
Article: How does risk management influence production decisions? Evidence from a field experiment
Journal: The Review of Financial Studies (Vol. 30; Issue no. 6)
Authors: Cole, S., Giné, X., and Vickery, J.
Year of Publication: 2017
Synopsis: According to Cole, Gine and Vickery (2017), risk management holds an integral role in defining the management of the successful management and integration of the factors. The production decisions for the project can be effectively dealt with the innovative and improved analysis model. The risk management operations would be helpful for taking care of the factors for the implementation and utilization factors. The innovation would be more effective for the formation of the impressive management and development. The analysis of the factors for the development and alignment of the factors has been largely helpful for integrating the listing of the factors taking care of the improved analysis and development. The easing of the management model would be implied with the consideration and utilization of the successive development model.
Article: Between cost and benefit: investigating effects of cost management control systems on cost efficiency and organisational performance
Journal: Journal of Management Control (Vol. 29; Issue no. 1)
Authors: Diefenbach, U., Wald, A., and Gleich, R.
Year of Publication: 2018
Synopsis: According to Diefenbach, Wald and Gleich (2018), the consideration of the factorial representation of the development model would align with the consideration to the formation and listing the innovative management of the factors. The successful management of the factors would help the organization in taking care of the innovation and development. The cost analysis and the management of the resources act as a major factor for integrating the utilization and development. The completion of the successful project completion would be aligned with the management of the successful cost factors. The consideration for the efficiency analysis of the costing factor for the project is aligned with the utilization of the improved functional development.
Is required information and resources for the project comprehensive? |
þ |
Is the project plan feasible? |
þ |
Has the design being approved by the client? |
þ |
Are all the factors for the risk assessment being considered? |
þ |
Is it possible for the actualization of the project? |
þ |
Has the project be approved by the client? |
þ |
Almeida, H., Hankins, K. W., & Williams, R. (2017). Risk management with supply contracts. The Review of Financial Studies, 30(12), 4179-4215.
Andersen, K., Thorsteinsson, S. E., Thorbergsson, H., & Gudmundsson, K. S. (2017, July). Developing the academic-industrial partnership through student research and projects: Case studies from Iceland. In Professional Communication Conference (ProComm), 2017 IEEE International (pp. 1-5). IEEE.
Budayan, C., Dikmen, I., Birgonul, M. T., & Ghaziani, A. (2018). A computerized method for delay risk assessment based on fuzzy set theory using MS Project™. KSCE Journal of Civil Engineering, 1-12.
Burtonshaw-Gunn, S. A. (2017). Risk and financial management in construction. Routledge.
Christian, D. (2018). Building Cost Management: Case Study Using Costing Methods. IJAME.
Cole, S., Giné, X., & Vickery, J. (2017). How does risk management influence production decisions? Evidence from a field experiment. The Review of Financial Studies, 30(6), 1935-1970.
Cooper, R. (2017). Supply chain development for the lean enterprise: interorganizational cost management. Routledge.
da Silva, R. F., Filgueira, R., Pietri, I., Jiang, M., Sakellariou, R., & Deelman, E. (2017). A characterization of workflow management systems for extreme-scale applications. Future Generation Computer Systems, 75, 228-238.
Diefenbach, U., Wald, A., & Gleich, R. (2018). Between cost and benefit: investigating effects of cost management control systems on cost efficiency and organisational performance. Journal of Management Control, 29(1), 63-89.
Fuller, M. A., Valacich, J. S., George, J. F., & Schneider, C. (2017). Information Systems Project Management: A Process and Team Approach, Edition 1.1. Prospect Press.
Harris, E. (2017). Strategic project risk appraisal and management. Routledge.
Harrison, F., & Lock, D. (2017). Advanced project management: a structured approach. Routledge.
Heldman, K. (2018). PMP: project management professional exam study guide. John Wiley & Sons.
Hopkin, P. (2018). Fundamentals of risk management: understanding, evaluating and implementing effective risk management. Kogan Page Publishers.
Husin, S., & Malahayati, N. (2018, May). Identifying inaccuracy of MS Project using system analysis. In IOP Conference Series: Materials Science and Engineering (Vol. 352, No. 1, p. 012036). IOP Publishing.
Kerzner, H. (2017). Project management metrics, KPIs, and dashboards: a guide to measuring and monitoring project performance. John Wiley & Sons.
Kerzner, H. (2018). Project management best practices: Achieving global excellence. John Wiley & Sons.
Kerzner, H., & Kerzner, H. R. (2017). Project management: a systems approach to planning, scheduling, and controlling. John Wiley & Sons.
Markou, C., Koulinas, G. K., & Vavatsikos, A. P. (2017). Project resources scheduling and leveling using Multi-Attribute Decision Models: Models implementation and case study. Expert Systems with Applications, 77, 160-169.
Nicholas, J. M., & Steyn, H. (2017). Project management for engineering, business and technology. Routledge.
Papke-Shields, K. E., & Boyer-Wright, K. M. (2017). Strategic planning characteristics applied to project management. International Journal of Project Management, 35(2), 169-179.
Shakeri, M., Shayestegan, M., Abunima, H., Reza, S. S., Akhtaruzzaman, M., Alamoud, A. R. M., … & Amin, N. (2017). An intelligent system architecture in home energy management systems (HEMS) for efficient demand response in smart grid. Energy and Buildings, 138, 154-164.
Stair, R., & Reynolds, G. (2017). Fundamentals of information systems. Cengage Learning.
Wager, K. A., Lee, F. W., & Glaser, J. P. (2017). Health care information systems: a practical approach for health care management. John Wiley & Sons.
Essay Writing Service Features
Our Experience
No matter how complex your assignment is, we can find the right professional for your specific task. Contact Essay is an essay writing company that hires only the smartest minds to help you with your projects. Our expertise allows us to provide students with high-quality academic writing, editing & proofreading services.Free Features
Free revision policy
$10Free bibliography & reference
$8Free title page
$8Free formatting
$8How Our Essay Writing Service Works
First, you will need to complete an order form. It's not difficult but, in case there is anything you find not to be clear, you may always call us so that we can guide you through it. On the order form, you will need to include some basic information concerning your order: subject, topic, number of pages, etc. We also encourage our clients to upload any relevant information or sources that will help.
Complete the order formOnce we have all the information and instructions that we need, we select the most suitable writer for your assignment. While everything seems to be clear, the writer, who has complete knowledge of the subject, may need clarification from you. It is at that point that you would receive a call or email from us.
Writer’s assignmentAs soon as the writer has finished, it will be delivered both to the website and to your email address so that you will not miss it. If your deadline is close at hand, we will place a call to you to make sure that you receive the paper on time.
Completing the order and download