Rank |
Factor |
Description |
Metrics |
Measurable value |
Time frame |
1 |
Operational |
The operations in the project are very important aspects for measurement of the online management system that is to be managed. |
Plan for management of the project |
8% decrease |
1.5 months |
2 |
Financial |
The investment made for the project. |
Calculation of the profit |
10% increment |
2 months |
3 |
Strategy |
Effective strategy is to be developed for the project |
Analysis matrix |
7% decrement |
3 months |
4 |
Customer |
With the increase in the number of customers the efficiency in the sales would increase. |
Customer Feedback |
10% increment |
1 month |
The value delivered by the project:
Faster: The procedures of the organization should have a reduced response time.
Better: The system implemented should provide a better service to the customers in comparison to the manual system.
The scope of the project
Out of Scope
The out scope of the project is as follows:
Assumptions
Assumptions are as follows:
Constraints
Scope Management Plan
The scope of the task can be overseen by using methods that are as per the following:
Seeing needs of the task: Understanding needs and additionally requests of the venture is very noteworthy in dealing with the extent of the undertaking effectively.
Distinguishing indications of venture creep: It is very essential to decide the indications of the task crawl appropriately with the goal that the conditions of undertaking killjoy can be overseen altogether.
Record for the progressions inside the extension fiscally: It is the obligation of the undertaking administrator to remain get ready about the upgrade in spending plan if the venture scope crawl changed spending plan.
Resource Name |
Std. Rate |
Project Manager |
$50.00/hr |
Financial Officer |
$25.00/hr |
Developer |
$20.00/hr |
Operational Manager |
$25.00/hr |
Project Planner |
$15.00/hr |
Project Sponsor |
$15.00/hr |
System Analyst |
$15.00/hr |
Trainer |
$18.00/hr |
IT Manager |
$25.00/hr |
Tester |
$30.00/hr |
Designer |
$26.00/hr |
HR Manager |
$12.00/hr |
Risk Manager |
$18.00/hr |
Business Analyst |
$15.00/hr |
IT Consultant |
$15.00/hr |
hardware cost |
$10,000.00 |
software cost |
$2,000.00 |
additional cost |
$1,000.00 |
Hardware |
RAM, hardware, desktop |
Software |
Server, Operating system, Java and more. |
Network |
Application firewall |
High speed internet connection is provided for the project team members.
Food facility |
Lunch are provided for the project team members. |
Gym Facility |
Workout facility is provided for the project team members so that they can reduce the project trace. |
Project Milestones
WBS |
Task Name |
Date of completion |
1.6 |
Milestone 1: Completion of Project Planning Phase |
Wed 5/30/18 |
2.9 |
Milestone 2: Completion of Project Preparation Phase |
Mon 6/25/18 |
3.6 |
Milestone 3: Completion of Project Design Phase |
Thu 7/5/18 |
4.10 |
Milestone 4: Completion of Project execution Phase |
Tue 10/2/18 |
5.6 |
Milestone 5: Completion of Testing Phase |
Fri 10/19/18 |
6.5 |
Milestone 6: Completion of Project Closing Phase |
Thu 11/22/18 |
WBS |
Task Name |
0 |
Online Management System Stud Farm |
1 |
Planning of Project |
1.1 |
Survey on Existing System |
1.2 |
Identify Problems Hampering the System |
1.3 |
Consider Possible Solutions |
1.4 |
Suggest New Information System |
1.5 |
Receive Approval to Proceed |
1.6 |
Milestone 1: Completion of Project Planning Phase |
2 |
Preparation for Project |
2.1 |
Determine Project Scope |
2.2 |
Determine Project Goals and Objectives |
2.3 |
Create an Appropriate Time Schedule |
2.4 |
Develop and Appropriate Project Charter |
2.5 |
Conduct Cost Benefit Analysis |
2.6 |
Allocation of Roles and Duties to Stakeholders and Team Members |
2.7 |
Procure Budget and Resources |
2.8 |
Proceed to Execution of Project |
2.9 |
Milestone 2: Completion of Project Preparation Phase |
3 |
Designing phase |
3.1 |
Proper design selection |
3.2 |
Create screen mockups for the system |
3.3 |
Outline the design |
3.4 |
Review the user design |
3.5 |
Approval of design phase |
3.6 |
Milestone 3: Completion of Project Design Phase |
4 |
Execution of Project |
4.1 |
Hire System Developer and System Trainer |
4.2 |
Create a System Prototype |
4.3 |
Develop Website along with User Portal |
4.4 |
Create Database for the system |
4.5 |
Add Other Features |
4.6 |
Test the Prototype |
4.7 |
Risk Assessment and Management |
4.8 |
Develop Complete Version |
4.9 |
Test and Handover |
4.10 |
Milestone 4: Completion of Project execution Phase |
5 |
Testing Phase |
5.1 |
Identify and mitigate the project risk |
5.2 |
user interface testing |
5.3 |
System Testing |
5.4 |
Manage project changes |
5.5 |
Approval of implementation phase |
5.6 |
Milestone 5: Completion of Testing Phase |
6 |
Sign Off and Closing of Project |
6.1 |
Training of Employees |
6.2 |
Review and Documentation |
6.3 |
Sign Off by Stakeholders |
6.4 |
Closing of Project by Project Manager |
6.5 |
Milestone 6: Completion of Project Closing Phase |
WBS |
Task Name |
Resource Names |
0 |
Online Management System Stud Farm |
|
1 |
Planning of Project |
|
1.1 |
Survey on Existing System |
Business Analyst, Operational Manager, Project Manager |
1.2 |
Identify Problems Hampering the System |
Risk Manager, System Analyst |
1.3 |
Consider Possible Solutions |
Business Analyst, IT Consultant |
1.4 |
Suggest New Information System |
IT Consultant, IT Manager |
1.5 |
Receive Approval to Proceed |
Financial Officer, HR Manager |
1.6 |
Milestone 1: Completion of Project Planning Phase |
|
2 |
Preparation for Project |
|
2.1 |
Determine Project Scope |
Operational Manager |
2.2 |
Determine Project Goals and Objectives |
Business Analyst, Project Manager |
2.3 |
Create an Appropriate Time Schedule |
Project Planner |
2.4 |
Develop and Appropriate Project Charter |
Project Manager |
2.5 |
Conduct Cost Benefit Analysis |
Financial Officer |
2.6 |
Allocation of Roles and Duties to Stakeholders and Team Members |
Operational Manager, Project Manager |
2.7 |
Procure Budget and Resources |
Financial Officer, HR Manager, Project Sponsor |
2.8 |
Proceed to Execution of Project |
Project Manager |
2.9 |
Milestone 2: Completion of Project Preparation Phase |
|
3 |
Designing phase |
|
3.1 |
Proper design selection |
Designer, Project Sponsor |
3.2 |
Create screen mockups for the system |
Designer |
3.3 |
Outline the design |
Designer, Developer |
3.4 |
Review the user design |
System Analyst, Tester |
3.5 |
Approval of design phase |
Project Manager |
3.6 |
Milestone 3: Completion of Project Design Phase |
|
4 |
Execution of Project |
|
4.1 |
Hire System Developer and System Trainer |
HR Manager |
4.2 |
Create a System Prototype |
Designer, Developer |
4.3 |
Develop Website along with User Portal |
Developer, System Analyst, hardware cost[1],software cost[1] |
4.4 |
Create Database for the system |
Designer, Developer |
4.5 |
Add Other Features |
Developer, IT Manager |
4.6 |
Test the Prototype |
System Analyst, Tester |
4.7 |
Risk Assessment and Management |
System Analyst |
4.8 |
Develop Complete Version |
IT Manager |
4.9 |
Test and Handover |
Tester, Trainer |
4.10 |
Milestone 4: Completion of Project execution Phase |
|
5 |
Testing Phase |
|
5.1 |
Identify and mitigate the project risk |
Risk Manager |
5.2 |
user interface testing |
Tester |
5.3 |
System Testing |
Tester |
5.4 |
Manage project changes |
IT Manager, Project Manager |
5.5 |
Approval of implementation phase |
Project Sponsor |
5.6 |
Milestone 5: Completion of Testing Phase |
|
6 |
Sign Off and Closing of Project |
|
6.1 |
Training of Employees |
Trainer, additional cost[1] |
6.2 |
Review and Documentation |
Project Sponsor, Project Planner |
6.3 |
Sign Off by Stakeholders |
Project Sponsor |
6.4 |
Closing of Project by Project Manager |
Business Analyst, Financial Officer, HR Manager |
6.5 |
Milestone 6: Completion of Project Closing Phase |
Task Name |
Duration |
Start |
Finish |
Online Management System Stud Farm |
134 days |
Mon 5/21/18 |
Thu 11/22/18 |
Planning of Project |
8 days |
Mon 5/21/18 |
Wed 5/30/18 |
Survey on Existing System |
5 days |
Mon 5/21/18 |
Fri 5/25/18 |
Identify Problems Hampering the System |
1 day |
Mon 5/28/18 |
Mon 5/28/18 |
Consider Possible Solutions |
1 day |
Tue 5/29/18 |
Tue 5/29/18 |
Suggest New Information System |
1 day |
Wed 5/30/18 |
Wed 5/30/18 |
Receive Approval to Proceed |
0 days |
Wed 5/30/18 |
Wed 5/30/18 |
Milestone 1: Completion of Project Planning Phase |
0 days |
Wed 5/30/18 |
Wed 5/30/18 |
Preparation for Project |
18 days |
Thu 5/31/18 |
Mon 6/25/18 |
Determine Project Scope |
1 day |
Thu 5/31/18 |
Thu 5/31/18 |
Determine Project Goals and Objectives |
1 day |
Fri 6/1/18 |
Fri 6/1/18 |
Create an Appropriate Time Schedule |
2 days |
Mon 6/4/18 |
Tue 6/5/18 |
Develop and Appropriate Project Charter |
2 days |
Wed 6/6/18 |
Thu 6/7/18 |
Conduct Cost Benefit Analysis |
5 days |
Fri 6/8/18 |
Thu 6/14/18 |
Allocation of Roles and Duties to Stakeholders and Team Members |
2 days |
Fri 6/15/18 |
Mon 6/18/18 |
Procure Budget and Resources |
5 days |
Tue 6/19/18 |
Mon 6/25/18 |
Proceed to Execution of Project |
0 days |
Mon 6/25/18 |
Mon 6/25/18 |
Milestone 2: Completion of Project Preparation Phase |
0 days |
Mon 6/25/18 |
Mon 6/25/18 |
Designing phase |
9 days |
Tue 6/26/18 |
Fri 7/6/18 |
Proper design selection |
3 days |
Tue 6/26/18 |
Thu 6/28/18 |
Create screen mockups for the system |
2 days |
Fri 6/29/18 |
Mon 7/2/18 |
Outline the design |
2 days |
Tue 7/3/18 |
Wed 7/4/18 |
Review the user design |
1 day |
Thu 7/5/18 |
Thu 7/5/18 |
Approval of design phase |
1 day |
Fri 7/6/18 |
Fri 7/6/18 |
Milestone 3: Completion of Project Design Phase |
0 days |
Thu 7/5/18 |
Thu 7/5/18 |
Execution of Project |
67 days |
Mon 7/9/18 |
Tue 10/9/18 |
Hire System Developer and System Trainer |
5 days |
Mon 7/9/18 |
Fri 7/13/18 |
Create a System Prototype |
15 days |
Mon 7/16/18 |
Fri 8/3/18 |
Develop Website along with User Portal |
5 days |
Mon 8/6/18 |
Fri 8/10/18 |
Create Database for the system |
2 days |
Mon 8/13/18 |
Tue 8/14/18 |
Add Other Features |
2 days |
Wed 8/15/18 |
Thu 8/16/18 |
Test the Prototype |
5 days |
Fri 8/17/18 |
Thu 8/23/18 |
Risk Assessment and Management |
3 days |
Fri 8/24/18 |
Tue 8/28/18 |
Develop Complete Version |
25 days |
Wed 8/29/18 |
Tue 10/2/18 |
Test and Handover |
5 days |
Wed 10/3/18 |
Tue 10/9/18 |
Milestone 4: Completion of Project execution Phase |
0 days |
Tue 10/2/18 |
Tue 10/2/18 |
Testing Phase |
11 days |
Wed 10/10/18 |
Wed 10/24/18 |
Identify and mitigate the project risk |
2 days |
Wed 10/10/18 |
Thu 10/11/18 |
user interface testing |
2 days |
Fri 10/12/18 |
Mon 10/15/18 |
System Testing |
2 days |
Tue 10/16/18 |
Wed 10/17/18 |
Manage project changes |
2 days |
Thu 10/18/18 |
Fri 10/19/18 |
Approval of implementation phase |
3 days |
Mon 10/22/18 |
Wed 10/24/18 |
Milestone 5: Completion of Testing Phase |
0 days |
Fri 10/19/18 |
Fri 10/19/18 |
Sign Off and Closing of Project |
21 days |
Thu 10/25/18 |
Thu 11/22/18 |
Training of Employees |
15 days |
Thu 10/25/18 |
Wed 11/14/18 |
Review and Documentation |
5 days |
Thu 11/15/18 |
Wed 11/21/18 |
Sign Off by Stakeholders |
1 day |
Thu 11/22/18 |
Thu 11/22/18 |
Closing of Project by Project Manager |
0 days |
Thu 11/22/18 |
Thu 11/22/18 |
Milestone 6: Completion of Project Closing Phase |
0 days |
Thu 11/22/18 |
Thu 11/22/18 |
WBS |
Task Name |
Cost |
0 |
Online Management System Stud Farm |
$50,584.00 |
1 |
Planning of Project |
$4,424.00 |
1.1 |
Survey on Existing System |
$3,600.00 |
1.2 |
Identify Problems Hampering the System |
$264.00 |
1.3 |
Consider Possible Solutions |
$240.00 |
1.4 |
Suggest New Information System |
$320.00 |
1.5 |
Receive Approval to Proceed |
$0.00 |
1.6 |
Milestone 1: Completion of Project Planning Phase |
$0.00 |
2 |
Preparation for Project |
$6,040.00 |
2.1 |
Determine Project Scope |
$200.00 |
2.2 |
Determine Project Goals and Objectives |
$520.00 |
2.3 |
Create an Appropriate Time Schedule |
$240.00 |
2.4 |
Develop and Appropriate Project Charter |
$800.00 |
2.5 |
Conduct Cost Benefit Analysis |
$1,000.00 |
2.6 |
Allocation of Roles and Duties to Stakeholders and Team Members |
$1,200.00 |
2.7 |
Procure Budget and Resources |
$2,080.00 |
2.8 |
Proceed to Execution of Project |
$0.00 |
2.9 |
Milestone 2: Completion of Project Preparation Phase |
$0.00 |
3 |
Designing phase |
$2,896.00 |
3.1 |
Proper design selection |
$984.00 |
3.2 |
Create screen mockups for the system |
$416.00 |
3.3 |
Outline the design |
$736.00 |
3.4 |
Review the user design |
$360.00 |
3.5 |
Approval of design phase |
$400.00 |
3.6 |
Milestone 3: Completion of Project Design Phase |
$0.00 |
4 |
Execution of Project |
$29,936.00 |
4.1 |
Hire System Developer and System Trainer |
$480.00 |
4.2 |
Create a System Prototype |
$5,520.00 |
4.3 |
Develop Website along with User Portal |
$13,400.00 |
4.4 |
Create Database for the system |
$736.00 |
4.5 |
Add Other Features |
$720.00 |
4.6 |
Test the Prototype |
$1,800.00 |
4.7 |
Risk Assessment and Management |
$360.00 |
4.8 |
Develop Complete Version |
$5,000.00 |
4.9 |
Test and Handover |
$1,920.00 |
4.10 |
Milestone 4: Completion of Project execution Phase |
$0.00 |
5 |
Testing Phase |
$2,808.00 |
5.1 |
Identify and mitigate the project risk |
$288.00 |
5.2 |
user interface testing |
$480.00 |
5.3 |
System Testing |
$480.00 |
5.4 |
Manage project changes |
$1,200.00 |
5.5 |
Approval of implementation phase |
$360.00 |
5.6 |
Milestone 5: Completion of Testing Phase |
$0.00 |
6 |
Sign Off and Closing of Project |
$4,480.00 |
6.1 |
Training of Employees |
$3,160.00 |
6.2 |
Review and Documentation |
$1,200.00 |
6.3 |
Sign Off by Stakeholders |
$120.00 |
6.4 |
Closing of Project by Project Manager |
$0.00 |
6.5 |
Milestone 6: Completion of Project Closing Phase |
$0.00 |
Figure 5: Time-phase budget
(Source: Created by Author)
Assumption
For the development of the project the following assumptions are mad:
Risk ID |
Description |
Probability |
Threat |
Rate |
Assigned To |
Response strategy |
Threat/Opportunity |
1 |
Cost forecast inaccurate |
20% |
Exceeding allocated budget |
3 |
Financial Manager |
Put more focus in the project design phase |
Threat |
2 |
Change management overloaded |
10% |
Uncontrolled development |
5 |
Project manager |
Develop effective change management plan |
Threat |
3 |
Miscommunication |
10% |
This can create errors in the system |
4 |
Project manager |
Arrangement of weekly meeting |
Threat |
4 |
Exceeding budget for improvement of project |
5% |
This would increase the efficiency of the project. |
3 |
Financial Manager |
This risk is accepted and worked on to improve the efficiency of the company |
Opportunity |
5 |
Schedule mismatch |
25% |
The task are not completed on time |
4 |
Project manager |
The milestone and the dates are to be maintained. |
Threat |
Statement on project quality
The Stud Farm project has been developed for the providing quality breeding services. This would not only effect the ales of the organization but also increase the customer satisfaction towards the organization. The proper documentation and training would also help in increasing the benefits of the organization.
Verification activities
Verification activities |
When? |
System testing |
After the system has been implemented. |
Evaluation of source code |
After the back end coding is completed. |
Review of document |
After the documentation is completed. |
Validation activities
Verification activities |
When? |
Regular Audits |
During the development of the project |
Supply Audits |
After the raw materials are supplied. |
Control Management Audit |
After the project has been implemented. |
Developing closure checklist
Activities |
Status |
Has the testing been completed? |
Yes |
Checking of the traceability matrix |
Yes |
Completion of documentation |
Yes |
Completion of project handover |
Yes |
Training complete ? |
Yes |
Feedbacks from clients received ? |
No |
For the evaluation of the project the measureable organizational value is to be referred. The following steps are to be followed:
Identification of the MOV
Gurney, G. G., Cinner, J., Ban, N. C., Pressey, R. L., Pollnac, R., Campbell, S. J., … & Setiawan, F. (2014). Poverty and protected areas: an evaluation of a marine integrated conservation and development project in Indonesia. Global Environmental Change, 26, 98-107.
Hwang, B. G., & Ng, W. J. (2013). Project management knowledge and skills for green construction: Overcoming challenges. International Journal of Project Management, 31(2), 272-284.
Jones, H., Moura, F., & Domingos, T. (2014). Transport infrastructure project evaluation using cost-benefit analysis. Procedia-Social and Behavioral Sciences, 111, 400-409.
Kendrick, T. (2015). Identifying and managing project risk: essential tools for failure-proofing your project. AMACOM Div American Mgmt Assn.
Kerzner, H. (2013). Project management: a systems approach to planning, scheduling, and controlling. John Wiley & Sons.
Larson, E. W., &Gray, C. (2013). Project Management: The Managerial Process with MS Project. McGraw-Hill.
Mir, F. A., &Pinnington, A. H. (2014).Exploring the value of project management: linking project management performance and project success. International journal of project management, 32(2), 202-217.
Nyborg, K. (2014). Project evaluation with democratic decision-making: What does cost–benefit analysis really measure ?. Ecological economics, 106, 124-131.
Pemsel, S., &Wiewiora, A. (2013).Project management office a knowledge broker in project-based organisations. International Journal of Project Management, 31(1), 31-42.
Stark, J. (2015). Product lifecycle management.In Product Lifecycle Management (pp. 1-29).Springer International Publishing.
Todorovi?, M. L., Petrovi?, D. ?., Mihi?, M. M., Obradovi?, V. L., &Bushuyev, S. D. (2015). Project success analysis framework: A knowledge-based approach in project management. International Journal of Project Management, 33(4), 772-783.
Tornabene, C., Hussain, M. M., Crowe, T., Cohen, N., & Panzer, J. (2012).U.S. Patent No. 8,103,729. Washington, DC: U.S. Patent and Trademark Office.
Verburg, R. M., Bosch-Sijtsema, P., &Vartiainen, M. (2013).Getting it done: Critical success factors for project managers in virtual work settings.International Journal of Project Management, 31(1), 68-7
Essay Writing Service Features
Our Experience
No matter how complex your assignment is, we can find the right professional for your specific task. Contact Essay is an essay writing company that hires only the smartest minds to help you with your projects. Our expertise allows us to provide students with high-quality academic writing, editing & proofreading services.Free Features
Free revision policy
$10Free bibliography & reference
$8Free title page
$8Free formatting
$8How Our Essay Writing Service Works
First, you will need to complete an order form. It's not difficult but, in case there is anything you find not to be clear, you may always call us so that we can guide you through it. On the order form, you will need to include some basic information concerning your order: subject, topic, number of pages, etc. We also encourage our clients to upload any relevant information or sources that will help.
Complete the order formOnce we have all the information and instructions that we need, we select the most suitable writer for your assignment. While everything seems to be clear, the writer, who has complete knowledge of the subject, may need clarification from you. It is at that point that you would receive a call or email from us.
Writer’s assignmentAs soon as the writer has finished, it will be delivered both to the website and to your email address so that you will not miss it. If your deadline is close at hand, we will place a call to you to make sure that you receive the paper on time.
Completing the order and download