1. Introduction
1.1. In this report I will calculate the exact amount of materials required to produce 1m3 of concrete, designed to the Department of Environment (DoE) method. This method of concrete design was first introduced in 1950, under the name “Road Note No 4”, which was later replaced by “Design of Normal Concrete Mixes” in 1975 by the British Department of Environment (DoE). The design guidance was updated in 1988 to account for changes in the then current British Standards and is still used today, often being referred to as the British Standard concrete mix design.
1.2. The DoE method for concrete mix design works by calculating the values of 8 fundamental processes:
Mean target compressive strength
Water/Cement ratio
Water content using required slump value and aggregate size
Cement content
Concrete density
Aggregate content
Proportion of fine & course aggregate
Course aggregate
2.1. Below is a list of design requirements/assumptions that have been used for the concrete mix design:
– A slump of 10mm to 30mm.
– A characteristic 28-day compressive strength of 30 N/mm2 (5% failures permitted).
– The standard deviation of the tests is σ = 6.1 N/mm2.
– Ordinary Portland cement (42.5 N).
– Crushed sand of 2.7 density and 60% passing through a 600 µm sieve.
– Crushed coarse aggregate 2.6 density and 20mm are used.
3. Mean Compressive Strength
3.1. The target mean compressive strength
(fm)
can be calculated by:
characteristic strength (fc)+(risk factor k x standard deviation(σ))
Table 1. Risk factor values used in statistical control (G.D.Taylor, 2000)
Percentage failure permitted
Risk factor value
16
1.00
10
1.28
5
1.64
2.5
1.96
2
2.05
1
2.33
fm= fc+(1.64 x σ)
fm=30+1.64 x 8=40N/mm2
4. Water / Cement Ratio
4.1. The water / cement ratio is determined by using data from table 2.
Table 2. Approximate compressive strength of concrete made with a free Water/Cement ratio of 0.50 (G.D.Taylor, 2000)
Type of cement
Type of coarse aggregate
Compressive Strength (N/mm2)
Age (days)
3
7
28
91
Ordinary Portland Cement (OPC)
Or
Sulphate-resisting Portland (SRPC)
Uncrushed
22
30
42
49
Crushed
27
36
49
56
Rapid-hardening Portland (RHPC)
Uncrushed
29
37
48
54
Crushed
34
43
55
61
1 N/mm2 = 1 MN/m2 = 1 MPa
4.2. One of the requirements of the design mix stated that the mix will use ordinary Portland cement, with crushed aggregate, therefore, the 28-day strength value of 49 N/mm2 from the above table can be used to calculate the water / cement ratio:
0.5 is used for the free-water/cement axis as this value is used in table 2.
At the point of intersection of compressive strength value of 49 N/mm2 with the free-water / cement value 0.5 (orange), the nearest curve is offset parallel to the point of intersection (blue).
A horizontal line is drawn starting at the desired compressive strength of 40 N/mm2, until it intersects with the parallel curve, with a vertical line drawn from this point of intersection to find the desired free-water / cement ratio of 0.57 (red).
Figure 1. Desired free-water / cement ratio (G.D.Taylor, 2000)
5. Water Content
5.1. To calculate the required water content to achieve a suitable concrete workability, the following factors are used:
– Slump value (10 mm – 30 mm)
– Aggregate size (20 mm)
The values of these factors have been provided in the design requirements and can be found in table 3.
5.2. Using the information provided in Table 3 (below), we can determine that the required water content is 190 kg/m3by intersecting the value at 20 mm aggregate size and 10 mm – 30 mm slump value for crushed aggregate.
Table 3: Workability and approximate free-water content (G.D.Taylor, 2000)
Slump (mm)
Vebe (seconds)
Very Low
0 – 10
>12
Low
10 – 30
6 – 12
Medium
30 – 60
3 – 6
High
60 – 180
0 – 3
Water Content
Maximum size of aggregate (mm)
Type of aggregate
Water content (kg/m3)
10
Uncrushed
Crushed
150
180
280
205
205
230
225
250
20
Uncrushed
Crushed
135
170
160
190
180
210
195
225
40
Uncrushed
Crushed
115
155
140
175
160
190
175
205
Reduction in water content when fly ash is used
Percentage of fly ash in cementitious material
Reduction in water content (kg/m3)
10
5
5
5
10
20
10
10
10
15
30
15
15
20
20
40
20
20
25
25
50
25
25
30
30
6. Cement Content
6.1. To calculate the amount of cement required, the following formula is used
Cement content per m3= water content per m3free–water/cement ratio
The values for both water content and free-water / cement ratio are known, so it is easily calculated.
Cement content per m3= 1900.57= 333 kg/m3
7. Density of Concrete
7.1. The DoE method uses a graphical system for calculating the density of the fresh concrete, using the relative aggregate density and free-water content.
7.2. The relative aggregate density has been provided at 2.6, and the free-water content is 190 kg/m3, therefore the density can be calculated to be 2370 kg/m3, as shown in figure 2.
Figure 2. Fresh Concrete Density (G.D.Taylor, 2000)
8. Aggregate Content
8.1. Using the fresh concrete density of 2370 kg/m3, and the aggregate content can be calculated using the following formula:
Aggregate content=fresh density–(cement content+water content)
These values have already been calculated, therefore:
Aggregate content=2370–333+190Aggregate content=1847 kg/m3
9. Fine aggregate content
9.1. The proportion of fine aggregate in the concrete mix will depend on:
– The grading of the sand
– Maximum aggregate size
– Workability of the concrete
– Free-water / cement ratio
9.2. Figure 3 (below) shows the graphical method of calculating the proportion of fine aggregate, which gives a result of 30% by starting at 0.5 free-water/cement ratio and drawing a line vertically upwards to the percentage of fine aggregate passing through a 600 µm sieve (60%). A horizontal line is then drawn to find the proportion of fine aggregate.
Figure 3. Recommended proportions of sand according to percentage passing a 600 µm sieve (G.D.Taylor, 2000)
Using the total aggregate content 1847 kg/m3, the proportion of fine aggregate can be calculated.
1847 x 0.3=554 kg/m3
10. Coarse Aggregate Content
10.1. Once the fine aggregate content has been calculated, we can simply deduct this value from the total aggregate content to determine the amount of coarse aggregate required.
1847–554=1293 kg/m3
11. Summary
11.1. From the calculations above, it can be determined that for each m3 of concrete, the correct amounts for each component are as follows:
Table 4. Quantity of materials required to produce 1m3 of concrete with a 28-day compressive strength of 30 N/mm2, designed to the DoE method.
Material
Quantity (kg/m3)
Cement
333
Water
190
Fine Aggregate
554
Coarse Aggregate
1293
G.D.Taylor, 2000. Materials in Construction – An Introduction. 3rd ed. Essex: Pearson Education Limited.
Essay Writing Service Features
Our Experience
No matter how complex your assignment is, we can find the right professional for your specific task. Contact Essay is an essay writing company that hires only the smartest minds to help you with your projects. Our expertise allows us to provide students with high-quality academic writing, editing & proofreading services.Free Features
Free revision policy
$10Free bibliography & reference
$8Free title page
$8Free formatting
$8How Our Essay Writing Service Works
First, you will need to complete an order form. It's not difficult but, in case there is anything you find not to be clear, you may always call us so that we can guide you through it. On the order form, you will need to include some basic information concerning your order: subject, topic, number of pages, etc. We also encourage our clients to upload any relevant information or sources that will help.
Complete the order formOnce we have all the information and instructions that we need, we select the most suitable writer for your assignment. While everything seems to be clear, the writer, who has complete knowledge of the subject, may need clarification from you. It is at that point that you would receive a call or email from us.
Writer’s assignmentAs soon as the writer has finished, it will be delivered both to the website and to your email address so that you will not miss it. If your deadline is close at hand, we will place a call to you to make sure that you receive the paper on time.
Completing the order and download