The project for the JKB Bloggins Ltd would include the development of a specific site building along with the required equipments. The type of the project is Market Driven as the construction of the building for JKB Bloggins Ltd. is inspired from the needs of the customer and to some extent the trend of the market.
The JKB Bloggins Ltd is employed for the development of their operations with the manufacturing of the new building for the construction and installing new equipments. The market driven project is implied for the formation of the effective employment (Fleming and Koppelman 2016). The integration of the deployed methods would be formed for the development of the operations of JKB Bloggins Ltd and it would form the management of the operations.
According to Devaux (2014), the scope management is a process of ensuring that all the required works in the project is include so that the project can be completed successfully along with controlling the project. The alignment of the project in scope items is formed for ensuring that the project is aligned successfully.
The scope management is deployed for ensuring that all crucial works of the projects is implied for the development of the improved functional analysis along with the integration of the operations (Schwalbe 2015). The management of the operations would be formed for the alignment of the project management principles for JKB Bloggins Ltd. The use of the WBS would be helpful for showing the sub divisions of the scope by the help of the work packages as the work packages are aligned with the scope of the project.
The full project Gantt chart is deployed for the development of the detailed project schedule development (Walker 2015). The use of the specific Gantt chart would be helpful for ensuring that the project schedule is developed successfully. The Gantt chart represents the complete list of the activities of the project and it would form the development of the complete analysis of the processes. However, the critical path helps in analysing the crucial and important activities of the project. A critical path may omit the activities that can run along a critical project activity or activities.
The project success evaluation can be done by analysing the activities of the project in terms of the success factors (Larson and Gray 2013). The deployment of the success criteria evaluation would be helpful for realizing the development of the project and evaluate the progress. The project must be completed in the expected cost and time for ensuring the success of the project.
The changes in the project can be managed by the help of the change management plan and implying it for the successful change implication (Devaux 2014). A project might require the modification of the operations, scope or activities and the change management plan helps in ensuring that the changes of the project are implied successfully. The change management plan is helpful for managing both internal and external changes. The activities of the change management are,
Some changes that would be included in the project of constructing the new manufacturing site for the JKB Blogging Ltd along with improved equipments and technology are relocation, data migration, handling of new equipments, and alignment of the operations at the new manufacturing site. The development of the change management plan would be helpful for overcoming the issues of the changes and implement it successfully.
The project evaluation, monitoring, and control are implied for ensuring that the project is completed in the estimated time duration (Kerzner 2013). The development of the project evaluation is done by evaluating the project in terms of cost and time. The Monitoring of the project is done with the help of the development of the project progress report for ensuring that the project is progressing as expected. The use of the project schedule and cost estimation plan would be helpful in ensuring that the project is completed in the estimated time and budget. The project progress report would help the operations of the project.
The project management unit has been playing a significant role in the development of the improved processes. The alignment of the profound development would be helpful for carrying out the development of the operations and forming the consideration of the operations. The following assignment is formed for the development of a report for the project of Construction of Manufacturing Site at JKB Bloggins Ltd. The report had covered the scope, objectives, deliverables, milestone, project schedule, network diagram, work breakdown structure, risk matrix, communication plan, and quality management. The alignment of the project would help the analysis of the project formation.
The project had been formed for constructing a new site for the JKB Bloggins Ltd for implementing their operations. The alignment of the project plan would help in forming the development of the improved operations for the construction activities.
The project is held responsible for the alignment of the operations and development of the effective management process. The formation of the activities would be helpful for forming the deployment of the effective project operations. The Construction of Manufacturing Site at JKB Bloggins Ltd is helpful for integrating the formation of the manufacturing of the site for the organization.
The task of Development of New Manufacturing Site for JKB Bloggins Ltd. takes after Agile (Adaptive) Lifecycle. The Agile undertaking lifecycle can be ordered into introductory stage, arranging stage, outlining stage, execution stage, testing stage, and conclusion stage (Martone et al. 2016). The underlying stage incorporates the improvement of the underlying documentation and asset advancement. The arranging stage would include choosing an undertaking design technique and building up the calendar for the task. The planning stage would include influencing the outline for the working of the assembling to site. The execution stage would contain the usage of the exercises for the undertaking. The testing stage would include the examination of the results of the execution stage and alter the exercises if required. The venture conclusion stage would contain the advancement of the exercises for definite shutting of the undertaking.
The project manager plays a significant role in the development of the project and completion of the project successfully. The complete management and alignment of the project activities fall under the responsibility of the project manager. The skills and competencies required by the project manager for this large project are listed in the table below,
Skills |
Competencies |
Communication Leadership Team Management Negotiation Personal Organization Risk Management |
Execution Decision Making Strategy Development Technical Competence Critical Thinking Business Expert |
The objectives of the project of Construction of Manufacturing Site at JKB Bloggins Ltd are given below,
The project of Construction of Manufacturing Site at JKB Bloggins Ltd consists of both in scope and out of scope items. The project plan, documents, risk management plan, and manufacturing site are the in scope items of the project. These should be included in the project for the development of proper documents and alignment of the operations.
The deliverables for the project of Construction of Manufacturing Site at JKB Bloggins Ltd are given below,
Documents: The Project Initiation and Charter Documents are made for the project in 7 days by Tue 10/4/16. The final documents of the project are made in 5 days by Tue 3/6/18.
Plan and Design: The complete reviewed plan is developed in 23 days by Thu 12/1/16 and the design is developed in 45 days by Thu 3/2/17.
Site and Structure: The site of the new manufacturing unit of JKB Bloggins Ltd is bought for HK$ 6,000,000.00 on Mon 3/20/17. The structure of the building is built in 171 days by Tue 12/19/17
Equipments and Materials: The materials are bought at a price of HK$ 2,789,200.00 on Wed 5/10/17 and the equipments are bought at a price of HK$ 668,800.00 on Tue 11/21/17.
Final Documentation and Manufacturing Site: The final documentation is formed in 5 days by Tue 3/6/18. The manufacturing site will be in work by Thu 3/29/18.
Recruiting and Training of staff: The training and recruiting of staffs is another major factor that would be required in the project. The training session would last of 12 months and it would be helpful for the staff recruited for working at the new manufacturing site of JKB Bloggins Ltd.
The project plan consists of 6 phase namely initial phase, plan phase, design phase, execution phase, documentation and approval phase, and closure phase and they act as milestones of the project (Keatley et al. 2017). The milestone of the project of Construction of Manufacturing Site at JKB Bloggins Ltd along with the time schedule is given in the table below,
WBS |
Task Name |
Duration |
Start |
Finish |
M1 |
Initial Phase |
24 days |
Mon 9/19/16 |
Thu 10/20/16 |
M2 |
Plan Phase |
23 days |
Tue 11/1/16 |
Thu 12/1/16 |
M3 |
Design Phase |
45 days |
Fri 12/30/16 |
Thu 3/2/17 |
M4 |
Execution Phase |
251 days |
Fri 3/3/17 |
Fri 2/16/18 |
M5 |
Documentation and Approval |
22 days |
Wed 2/28/18 |
Thu 3/29/18 |
M6 |
Project is closed |
1 day |
Fri 3/30/18 |
Fri 3/30/18 |
Table 1: Project Milestones with Schedule Duration
(Source: Created by the author)
The technical requirements of the project are Analyst, Documenter, Project Manager, Planner, Designer, Client, Contractor, Workers, Engineer, Government Officer, Site, Equipments, Iron Pillars, Cement, Brick, Sand, Clay, and Transportation Cost.
The transportation of the materials is aligned for the construction of the building site where the manufacturing of the materials would take place. The out of scope of the project are change management, transportation of the materials, and marketing of the event for the project.
The work breakdown structure is developed for forming the specific work packages and aligning the operations of the project for ensuring that the project is completed in specific time. The work breakdown structure for the project of Construction of Manufacturing Site at JKB Bloggins Ltd is in the appendix section of the report below.
Resource Name |
|
Analyst |
Analyzing the requirements |
Documenter |
Developing PID document, Charter Documentation, Submission of the documents, and Making final documents |
Project Manager |
Review and Sign off, Plan Approval, Design review and approval, Review and Sign off the final documents, Project is closed, and Final Inspection of the completed building structure |
Planner |
Selecting Plan Strategy, Developing plan outline, Plan review, and Plan Completion |
Designer |
Selecting Building Design Platform, Developing design of the new building, Reviewing the design, and Simulation of the design |
Client |
Site Approval, Work Started at New Manufacturing Site, Selection of the site for the new building, and Final Inspection of the completed building structure |
Contractor |
Site Clearing, Different Sections of Manufacturing unit are built, and Final Inspection of the completed building structure |
Workers |
Floors are built, Emergency Exit is constructed, Laying of Iron Pillars for building, and Building Structure is formed |
Engineer |
Fire Safety is installed, Final Inspection of the completed building structure, Testing the functionality of the equipments installed, Equipments are installed, and Training of the Staffs |
The project schedule for the project of Construction of Manufacturing Site at JKB Bloggins Ltd has been developed by using the Ms-Project software and it has been shown in the table below,
WBS |
Task Name |
Duration |
Start |
Finish |
0 |
Construction of Manufacturing Site at JKB Bloggins |
400 days |
Mon 9/19/16 |
Fri 3/30/18 |
M1 |
Initial Phase |
24 days |
Mon 9/19/16 |
Thu 10/20/16 |
1.1 |
Analyzing the requirements |
5 days |
Mon 9/19/16 |
Fri 9/23/16 |
1.2 |
Developing PID document |
7 days |
Mon 9/26/16 |
Tue 10/4/16 |
1.3 |
Charter Documentation |
7 days |
Wed 10/5/16 |
Thu 10/13/16 |
1.4 |
Submission of the documents |
3 days |
Fri 10/14/16 |
Tue 10/18/16 |
1.5 |
Review and Sign off |
2 days |
Wed 10/19/16 |
Thu 10/20/16 |
M2 |
Plan Phase |
23 days |
Tue 11/1/16 |
Thu 12/1/16 |
2.1 |
Selecting Plan Strategy |
3 days |
Tue 11/1/16 |
Thu 11/3/16 |
2.2 |
Developing plan outline |
5 days |
Fri 11/4/16 |
Thu 11/10/16 |
2.3 |
Plan review |
3 days |
Fri 11/11/16 |
Tue 11/15/16 |
2.4 |
Plan Completion |
10 days |
Wed 11/16/16 |
Tue 11/29/16 |
2.5 |
Plan Approval |
2 days |
Wed 11/30/16 |
Thu 12/1/16 |
M3 |
Design Phase |
45 days |
Fri 12/30/16 |
Thu 3/2/17 |
3.1 |
Selecting Building Design Platform |
3 days |
Fri 12/30/16 |
Tue 1/3/17 |
3.2 |
Developing design of the new building |
15 days |
Wed 1/4/17 |
Tue 1/24/17 |
3.3 |
Reviewing the design |
7 days |
Wed 1/25/17 |
Thu 2/2/17 |
3.4 |
Simulation of the design |
10 days |
Fri 2/3/17 |
Thu 2/16/17 |
3.5 |
Design review and approval |
5 days |
Fri 2/24/17 |
Thu 3/2/17 |
4 |
Training Phase |
253 days |
Fri 3/3/17 |
Tue 2/20/18 |
4.1 |
Development of training manual |
13 days |
Fri 3/3/17 |
Tue 3/21/17 |
4.2 |
Hiring of the trainers |
5 days |
Wed 3/22/17 |
Tue 3/28/17 |
4.3 |
Training Scheduling |
8 days |
Wed 3/29/17 |
Fri 4/7/17 |
4.4 |
Training Session initiated |
3 days |
Mon 4/10/17 |
Wed 4/12/17 |
4.5 |
Training Completed |
2 days |
Mon 2/19/18 |
Tue 2/20/18 |
M4 |
Execution Phase |
251 days |
Fri 3/3/17 |
Fri 2/16/18 |
5.1 |
Site Development |
37 days |
Fri 3/3/17 |
Mon 4/24/17 |
5.1.1 |
Selection of the site for the new building |
5 days |
Fri 3/3/17 |
Thu 3/9/17 |
5.1.2 |
Land is Bought |
7 days |
Fri 3/10/17 |
Mon 3/20/17 |
5.1.3 |
Site Approval |
10 days |
Tue 3/21/17 |
Mon 4/3/17 |
5.1.4 |
Site Clearing |
15 days |
Tue 4/4/17 |
Mon 4/24/17 |
5.2 |
Infrastructure Development |
214 days |
Tue 4/25/17 |
Fri 2/16/18 |
5.2.1 |
Requirement Materials are bought |
12 days |
Tue 4/25/17 |
Wed 5/10/17 |
5.2.2 |
Laying of Iron Pillars for building |
15 days |
Thu 6/1/17 |
Wed 6/21/17 |
5.2.3 |
Building Structure is formed |
40 days |
Thu 6/22/17 |
Wed 8/16/17 |
5.2.4 |
Floors are built |
25 days |
Thu 8/17/17 |
Wed 9/20/17 |
5.2.5 |
Different Sections of Manufacturing unit are built |
20 days |
Thu 9/21/17 |
Wed 10/18/17 |
5.2.6 |
Equipments are installed |
24 days |
Thu 10/19/17 |
Tue 11/21/17 |
5.2.7 |
Equipments are transported |
15 days |
Wed 11/22/17 |
Tue 12/12/17 |
5.2.8 |
Fire Safety is installed |
5 days |
Wed 12/13/17 |
Tue 12/19/17 |
5.2.9 |
Emergency Exit is constructed |
8 days |
Wed 12/20/17 |
Fri 12/29/17 |
5.2.10 |
Final Inspection of the completed building structure |
5 days |
Mon 1/1/18 |
Fri 1/5/18 |
5.2.11 |
Testing the functionality of the equipments installed |
10 days |
Mon 1/8/18 |
Fri 1/19/18 |
5.2.12 |
Training of the Staffs |
20 days |
Mon 1/22/18 |
Fri 2/16/18 |
M5 |
Documentation and Approval |
22 days |
Wed 2/28/18 |
Thu 3/29/18 |
6.1 |
Making final documents |
5 days |
Wed 2/28/18 |
Tue 3/6/18 |
6.2 |
Review and Sign off the final documents |
4 days |
Wed 3/7/18 |
Mon 3/12/18 |
6.3 |
Government Inspection |
3 days |
Tue 3/13/18 |
Thu 3/15/18 |
6.4 |
Approval of the government |
7 days |
Fri 3/16/18 |
Mon 3/26/18 |
6.5 |
Work Started at New Manufacturing Site |
3 days |
Tue 3/27/18 |
Thu 3/29/18 |
M6 |
Project is closed |
1 day |
Fri 3/30/18 |
Fri 3/30/18 |
Table 2: Project Schedule in a table format
(Source: Created by the author)
The Gantt chart of the project is formed by using Ms-Project Software and it is consists of a table of project schedule and a time frame showing the extent of the project operations (Siami-Irdemoosa, Dindarloo and Sharifzadeh 2015). The Gantt chart of the project of Construction of Manufacturing Site at JKB Bloggins Ltd is shown below,
Critical Path Analysis: The critical path of the project of Construction of Manufacturing Site at JKB Bloggins Ltd is shown by highlighting in the appendix section of the report below. The critical path node structure for the project of Construction of Manufacturing Site at JKB Bloggins Ltd is given below,
0àM1à1.1à1.2à1.3à1.4à1.5àM2à2.1à2.2à2.3à2.4à2.5àM4à4.1à4.1.1à4.1.2à4.1.3à4.1.4à4.2à4.2.3à4.2.4à4.2.5à4.2.6à4.2.7à4.3à4.4à4.5àM5à5.1à5.2à5.3à5.4à5.5à5.6àM6
It is for ensuring that the project is represented in a stratified diagram that shows the activities of the project in a cohesive manner (Keatley et al. 2017). The network diagram for the project of Construction of Manufacturing Site at JKB Bloggins Ltd is in the appendix section of the report below.
The cost budget for the project is developed in Ms-Excel with the help of formulas and tables (Yildiz et al. 2014). The budget of the project of Construction of Manufacturing Site at JKB Bloggins Ltd is shown below,
Project Budget for the Project of Construction of Manufacturing Site at JKB Bloggins |
||||
Resource Name |
Resource Type |
Rate |
Usage |
Cost |
Analyst |
Human |
£ 700.00 |
40 |
£ 28,000.00 |
Documenter |
Human |
£ 800.00 |
176 |
£ 140,800.00 |
Project Manager |
Human |
£ 1,500.00 |
152 |
£ 228,000.00 |
Planner |
Human |
£ 900.00 |
168 |
£ 151,200.00 |
Designer |
Human |
£ 1,150.00 |
280 |
£ 322,000.00 |
Client |
Human |
£ – |
184 |
£ – |
Contractor |
Human |
£ 1,250.00 |
320 |
£ 400,000.00 |
Workers |
Human |
£ 1,000.00 |
704 |
£ 704,000.00 |
Engineer |
Human |
£ 1,400.00 |
512 |
£ 716,800.00 |
Government Officer |
Human |
£ – |
80 |
£ – |
Site |
Cost |
£ 6,000,000.00 |
1 |
£ 6,000,000.00 |
Equipments |
Material |
£ 400,000.00 |
1 |
£ 400,000.00 |
Iron Pillars |
Material |
£ 650,000.00 |
1 |
£ 650,000.00 |
Cement |
Material |
£ 600,000.00 |
1 |
£ 600,000.00 |
Brick |
Material |
£ 618,000.00 |
1 |
£ 618,000.00 |
Sand |
Material |
£ 500,000.00 |
1 |
£ 500,000.00 |
Clay |
Material |
£ 421,200.00 |
1 |
£ 421,200.00 |
Transportation Cost |
Material |
£ 120,000.00 |
1 |
£ 120,000.00 |
Total Budget |
£ 12,000,000.00 |
Table 3: Cost Budget for the project
(Source: Created by the author)
Time Phase Budget: The time phased budget is developed with the help of the Cash Flow tab of the Ms-Project software. The diagram has money values in pounds in the Y axis and the time period in quarters of years in the X axis. The quarter 3, 2016 exhausts a budget of £ 60,000.00. The quarter 4, 2016 exhausts a budget of £ 285,200.00. The quarter 1, 2017 exhausts a budget of £ 6,372,800.00. The quarter 2, 2017 exhausts a budget of £ 3,115,200.00. The quarter 3, 2017 exhausts a budget of £ 534,000.00. The quarter 4, 2017 exhausts a budget of £ 1,038,800.00. The quarter 1, 2018 exhausts a budget of £ 94,000.00. The time phased budget for the project of Construction of Manufacturing Site at JKB Bloggins Ltd is in the appendix section of the report below.
The project risk matrix for the project of Construction of Manufacturing Site at JKB Bloggins Ltd are given below,
Risk Name and Description |
Risk Type |
Probability |
Severity |
Impact |
Mitigation |
Delay in project activities: The time plays a significant factor for the project and due to any issues the project activities might get delayed. |
Operational |
Almost Certain |
Medium |
High |
Development of a proper project schedule |
Cost Overrun: The cost overrun is the issue when the project cannot be completed with the amount of resources gathered within the period. |
Financial |
Likely |
Very High |
Extreme |
Making provisional budgeting |
Quality Issues: The construction activities of the project would involve the use of the raw materials and the degraded quality of the materials would cause the issues in project. |
Procurement |
Possible |
High |
Very High |
Ensuring the quality of the project raw materials |
Table 4: Project Risk Matrix
(Source: Created by the author)
The project communication plan for the project of Construction of Manufacturing Site at JKB Bloggins Ltd are given below,
Information to be Send |
Receiver |
Communication Timing |
Communication Method |
Sender |
Project Status Report |
Project Client |
Quarterly |
Documents |
Project Manager |
Project and Change Requirements |
Project Team |
Weekly |
|
Project Manager |
Work Requests |
Project Manager |
Monthly |
Messages |
Project Client |
Progress Documents |
Documenter |
Daily |
Documents |
|
Team Responsibility |
Project Team |
Daily |
Reports |
Planner |
Table 5: Project Communication Matrix
(Source: Created by the author)
The undertaking control procedure can be shaped by following the means said underneath,
The Transactional Leadership authority is exceptionally useful for the advancement of the enhanced exercises of the undertaking combination and administration (Cable and Cheung 2017). The arrangement of the venture operations would be useful for shaping the arrangement of the operations. The arrangement of the exercises would help in shaping the improvement of the operations.
Conclusion
It can be concluded that the project of the Construction of Manufacturing Site at JKB Bloggins Ltd had been formed with the help of the project management operations. The principles and functions of the project management had been helpful for overcoming the management of the site. The construction of the manufacturing site for JKB Bloggins Ltd had been formed and this report had formed the use of the project development model for the project documentation. The project plan, documents, risk management plan, and manufacturing site were the in scope items of the project while the change management, transportation of the materials, and marketing of the event were the out of scope items for the project. The deliverables for the project of Construction of Manufacturing Site at JKB Bloggins Ltd were Project Initiation and Charter Documents, complete reviewed plan, site of the new manufacturing unit of JKB Bloggins Ltd, Equipments and Materials, and Final Documentation and Manufacturing Site. The project plan consisted of 6 phase namely initial phase, plan phase, design phase, execution phase, documentation and approval phase, and closure phase and they acted as milestones of the project. The Total Budget of the project of Construction of Manufacturing Site at JKB Bloggins Ltd was £12,000,000.00. However some risk factors like Delay in project activities, Cost Overrun, and Quality Issues were responsible for the generation of the issues for the project.
Bury, R. (2017). Carillion under pressure to inject funds amid growing pension concerns. [online] The Telegraph. Available at: https://www.telegraph.co.uk/business/2017/07/15/carillion-pressure-inject-funds-amid-growing-pension-concerns/ [Accessed 20 Nov. 2017].
Cable, J. and Cheung, C., 2017. Eight Principles of Effective Online Teaching: A Decade-Long Lessons Learned in Project Management Education.
Cicmil, S., Cooke-Davies, T., Crawford, L. and Richardson, K., 2017, April. Exploring the complexity of projects: Implications of complexity theory for project management practice. Project Management Institute.
Coombs, W.T., 2014. Ongoing crisis communication: Planning, managing, and responding. Sage Publications.
Devaux, S.A., 2014. Managing Projects as Investments: Earned Value to Business Value. CRC press.
Fleming, Q.W. and Koppelman, J.M., 2016, December. Earned value project management. Project Management Institute.
Fleming, Q.W. and Koppelman, J.M., 2016, December. Earned value project management. Project Management Institute.
Flyvbjerg, B., 2013. From Nobel prize to project management: getting risks right. arXiv preprint arXiv:1302.3642.
Ganesh, M.K.S. and Thanushkodi, K., 2015. An efficient software cost estimation technique using fuzzy logic with the aid of optimization algorithm. International Journal of Innovative Computing, Vol11 (2) Pp-587-597.
Hegazy, T., 2013. Computer-Based Construction Project Management: Pearson New International Edition. Pearson Higher Ed.
Heldman, K., 2015. PMP project management professional exam deluxe study guide: updated for the 2015 Exam. John Wiley & Sons.
Keatley, D.A., Ferguson, E., Lonsdale, A. and Hagger, M.S., 2017. Lay understanding of the causes of binge drinking in the United Kingdom and Australia: a network diagram approach. Health education research, 32(1), pp.33-47.
Kerzner, H., 2013. Project management: a systems approach to planning, scheduling, and controlling. John Wiley & Sons.
Kerzner, H., 2013. Project management: a systems approach to planning, scheduling, and controlling. John Wiley & Sons.
Larson, E.W. and Gray, C., 2013. Project Management: The Managerial Process with MS Project. McGraw-Hill.
Li, T., Qiu, W.G., Wang, L.C. and Man, S., 2013. study of project duration risk in the network diagram based on matrix algorithm. In Applied Mechanics and Materials (Vol. 405, pp. 3401-3405). Trans Tech Publications.
Martin, B., 2017. The politics of electricity planning in South Africa: A review of dominant advocacy coalitions seeking to influence the Integrated Resource Plan of 2010 (IRP2010), and its update in 2013 (Doctoral dissertation, University of Cape Town).
Martinelli, R.J. and Milosevic, D.Z., 2016. Project management toolbox: tools and techniques for the practicing project manager. John Wiley & Sons.
Martone, R.G., Erickson, A., Mach, M., Hale, T., McGregor, A., Prahler, E.E., Foley, M., Caldwell, M. and Hartge, E.H., 2016, February. EcoPrinciples Connect: A Pilot Project Matching Ecological Principles with Available Data to Promote Ecosystem-Based Management. In AGU Fall Meeting Abstracts.
Mir, F.A. and Pinnington, A.H., 2014. Exploring the value of project management: linking project management performance and project success. International journal of project management, 32(2), pp.202-217.
Mohammad, I., van den Broek, H., Boots, M.L. and Wong, R., Oracle International Corporation, 2016. Showing relationships between tasks in a Gantt chart. U.S. Patent 9,336,502.
Nakamura, S., Kaneko, K., Okada, Y., Yin, C. and Ogata, H., 2015. Cubic gantt chart as visualization tool for learning activity data. In 23rd International Conference on Computers in Education, ICCE 2015. Asia-Pacific Society for Computers in Education.
Nam, S., Lee, D.K., Jeong, Y.K., Lee, P. and Shin, J.G., 2016. Environmental impact assessment of composite small craft manufacturing using the generic work breakdown structure. International Journal of Precision Engineering and Manufacturing-Green Technology, 3(3), pp.261-272.
Nicholas, J.M. and Steyn, H., 2017. Project management for engineering, business and technology. Taylor & Francis.
Nicholas, J.M. and Steyn, H., 2017. Project management for engineering, business and technology. Taylor & Francis.
Pritchard, C.L. and PMP, P.R., 2014. Risk management: concepts and guidance. CRC Press.
Sallis, E., 2014. Total quality management in education. Routledge.
Schwalbe, K., 2015. Information technology project management. Cengage Learning.
Sears, S.K., Sears, G.A., Clough, R.H., Rounds, J.L. and Segner, R.O., 2015. Construction project management. John Wiley & Sons.
Sears, S.K., Sears, G.A., Clough, R.H., Rounds, J.L. and Segner, R.O., 2015. Construction project management. John Wiley & Sons.
Siami-Irdemoosa, E., Dindarloo, S.R. and Sharifzadeh, M., 2015. Work breakdown structure (WBS) development for underground construction. Automation in Construction, 58, pp.85-94.
Svejvig, P. and Andersen, P., 2015. Rethinking project management: A structured literature review with a critical look at the brave new world. International Journal of Project Management, 33(2), pp.278-290.
Turner, R., 2016. Gower handbook of project management. Routledge.
Walker, A., 2015. Project management in construction. John Wiley & Sons.
Yildiz, A.E., Dikmen, I., Birgonul, M.T., Ercoskun, K. and Alten, S., 2014. A knowledge-based risk mapping tool for cost estimation of international construction projects. Automation in Construction, 43, pp.144-155.
Essay Writing Service Features
Our Experience
No matter how complex your assignment is, we can find the right professional for your specific task. Contact Essay is an essay writing company that hires only the smartest minds to help you with your projects. Our expertise allows us to provide students with high-quality academic writing, editing & proofreading services.Free Features
Free revision policy
$10Free bibliography & reference
$8Free title page
$8Free formatting
$8How Our Essay Writing Service Works
First, you will need to complete an order form. It's not difficult but, in case there is anything you find not to be clear, you may always call us so that we can guide you through it. On the order form, you will need to include some basic information concerning your order: subject, topic, number of pages, etc. We also encourage our clients to upload any relevant information or sources that will help.
Complete the order formOnce we have all the information and instructions that we need, we select the most suitable writer for your assignment. While everything seems to be clear, the writer, who has complete knowledge of the subject, may need clarification from you. It is at that point that you would receive a call or email from us.
Writer’s assignmentAs soon as the writer has finished, it will be delivered both to the website and to your email address so that you will not miss it. If your deadline is close at hand, we will place a call to you to make sure that you receive the paper on time.
Completing the order and download