The project had been made for constructing the footpath for people walking on the road. The project had been deployed for constructing the footpath or sidewalk at Quota Park. The initial requirements of the project include the use of proper project management concept for developing the operations of the project. The project would help in making an appropriate plan for constructing the pathways or footpath in Quota Park. The project would include the construction of the footpath along with development of the infrastructure at the park.
The project would be formed with the development of the sidewalk at the Quota Park. The inclusion of the various documents such as project charter would ensure the development of the most suitable project operations completion. The construction project had been prone for developing the plan for the construction of the project.
The objectives of the project include the operations of the project management tools and methods for the construction process. The objectives of the project are,
The high level requirements of the project include the,
The primary assumption of the project is that the resources of the project is easily available. It is considered that the operations of the project would go on smoothly. The sponsor would ensure the investments required for the construction of the pathways in the project.
The time, budget, and quality are the constraints of the project management operations of the project. The operations of the project are bounded by the deployed and estimated time duration of the project. The budget is also limited by the investors and their investments in the project.
The high level risks in the project are given in the table below,
Sl. No |
Project Risk Type |
Impact |
Probability |
1. |
Delay in completion of the project operations |
Would cause the operations of the project to take more time for completion of the project operations |
Medium |
2. |
Over budget of the project |
The operations of the project would not be completed by the estimated budget and resources allocation done by the project manager and planner. |
Medium |
3 |
Inferior quality of pathway |
The developed pathway would be of inferior quality than the expected quality of the side walk by the sponsors |
High |
Summary Milestone Schedule:
Task Name |
Duration |
Start |
Finish |
Construction of Footpath at Quota Park |
550 days |
Wed 16-08-17 |
Tue 24-09-19 |
Stage I |
300 days |
Wed 16-08-17 |
Tue 09-10-18 |
SITE ESTABLISHMENT |
57 days |
Wed 16-08-17 |
Thu 02-11-17 |
PROVISION FOR TRAFFIC |
20 days |
Fri 03-11-17 |
Thu 30-11-17 |
ENVIRONMENTAL MANAGEMENT |
31 days |
Fri 01-12-17 |
Fri 12-01-18 |
DRAINAGE |
29 days |
Mon 15-01-18 |
Thu 22-02-18 |
PROTECTIVE TREATMENTS |
30 days |
Fri 23-02-18 |
Thu 05-04-18 |
EARTHWORKS |
36 days |
Fri 06-04-18 |
Fri 25-05-18 |
LANDSCAPE AND REVEGETATION WORKS |
34 days |
Mon 28-05-18 |
Thu 12-07-18 |
ROAD FURNITURE |
38 days |
Fri 13-07-18 |
Tue 04-09-18 |
MISCELLANEOUS MRC TASKS |
25 days |
Wed 05-09-18 |
Tue 09-10-18 |
Stage I Completed |
0 days |
Tue 09-10-18 |
Tue 09-10-18 |
Stage II |
250 days |
Wed 10-10-18 |
Tue 24-09-19 |
SITE ESTABLISHMENT |
80 days |
Wed 10-10-18 |
Tue 29-01-19 |
PROVISION FOR TRAFFIC |
20 days |
Wed 30-01-19 |
Tue 26-02-19 |
ENVIRONMENTAL MANAGEMENT |
25 days |
Wed 27-02-19 |
Tue 02-04-19 |
DRAINAGE |
20 days |
Wed 03-04-19 |
Tue 30-04-19 |
PROTECTIVE TREATMENTS |
27 days |
Wed 01-05-19 |
Thu 06-06-19 |
EARTHWORKS |
40 days |
Fri 07-06-19 |
Thu 01-08-19 |
LANDSCAPE AND REVEGETATION WORKS |
38 days |
Fri 02-08-19 |
Tue 24-09-19 |
Stage II Completed |
0 days |
Tue 24-09-19 |
Tue 24-09-19 |
Summary Budget:
For Stage I
SUMMARY OF ESTIMATE |
|
SITE ESTABLISHMENT |
$ 11,000 |
PROVISION FOR TRAFFIC |
$ 520 |
ENVIRONMENTAL MANAGEMENT |
$ 720 |
DRAINAGE |
$ 100,263 |
PROTECTIVE TREATMENTS |
$ 1,188,480 |
EARTHWORKS |
$ 213,000 |
LANDSCAPE AND REVEGETATION WORKS |
$ 580,000 |
ROAD FURNITURE |
$ 16,500 |
MISCELLANEOUS MRC TASKS |
$ 26,310 |
TOTAL |
$ 2,136,793 |
For Stage II
SUMMARY OF ESTIMATE |
|
SITE ESTABLISHMENT |
$ 14,000 |
PROVISION FOR TRAFFIC |
$ 760 |
ENVIRONMENTAL MANAGEMENT |
$ 480 |
DRAINAGE |
$ 20,610 |
PROTECTIVE TREATMENTS |
$ 802,750 |
EARTHWORKS |
$ 321,100 |
LANDSCAPE AND REVEGETATION WORKS |
$ 117,550 |
Total |
$ 1,277,250 |
Stage 1 |
$ 2,136,793.00 |
Stage 2 |
$ 1,277,250.00 |
Total |
$ 34,14,043.20 |
Stakeholder List:
The stakeholders in the project include sponsors or investors, project manager, planner, budgeter, contractor, designer, and engineer.
The project life cycle is waterfall in nature as it deploys the formation of the effective and smart methods of construction. Waterfall deploys the benefit of step by step implementation of the operations. The waterfall model consists of Requirement Analysis, designing of the project operations, implementation of the plan, verification of the plan, and maintenance are the elements of the Waterfall model.
The project approval requirement include covering the quota park with a pathway for the visitors in the park. The requirement criteria include the completion of the operations of the project as per mentioned in the project tender within the allocated time and budget for completion.
Bentley, C., 2015. PRINCE2 For Beginners: From Introduction to Passing Your Foundation Exam. Routledge.
Burke, R., 2013. Project management: planning and control techniques. New Jersey, USA.
Iamandi, O., Popescu, S., Dragomir, M. and Morariu, C., 2015. A Critical Analysis of Project Management Models and its Potential Risks in Software Development. Calitatea, 16(149), p.55.
Kerzner, H., 2013. Project management: a systems approach to planning, scheduling, and controlling. John Wiley & Sons.
Krysi?ski, M. and Miller, P., 2016. The Role of Conflict in Project Management in the PRINCE2 Methodology. EkonomikaiOrganizacjaPrzedsi?biorstwa, (6), pp.3-12.
Mir, F.A. and Pinnington, A.H., 2014. Exploring the value of project management: linking project management performance and project success. International Journal of Project Management, 32(2), pp.202-217.
Morris, P.W., 2013. Reconstructing project management. John Wiley & Sons.
Schwalbe, K., 2015. Information technology project management. Cengage Learning.
Too, E.G. and Weaver, P., 2014. The management of project management: A conceptual framework for project governance. International Journal of Project Management, 32(8), pp.1382-1394.
Vardy, A., 2015. Prince2 Project Management For Beginners: The Ultimate Beginners Crash Course To Learn Prince2 Project Management Quickly And Easily.
Verzuh, E., 2015. The fast forward MBA in project management. John Wiley & Sons.
Essay Writing Service Features
Our Experience
No matter how complex your assignment is, we can find the right professional for your specific task. Contact Essay is an essay writing company that hires only the smartest minds to help you with your projects. Our expertise allows us to provide students with high-quality academic writing, editing & proofreading services.Free Features
Free revision policy
$10Free bibliography & reference
$8Free title page
$8Free formatting
$8How Our Essay Writing Service Works
First, you will need to complete an order form. It's not difficult but, in case there is anything you find not to be clear, you may always call us so that we can guide you through it. On the order form, you will need to include some basic information concerning your order: subject, topic, number of pages, etc. We also encourage our clients to upload any relevant information or sources that will help.
Complete the order formOnce we have all the information and instructions that we need, we select the most suitable writer for your assignment. While everything seems to be clear, the writer, who has complete knowledge of the subject, may need clarification from you. It is at that point that you would receive a call or email from us.
Writer’s assignmentAs soon as the writer has finished, it will be delivered both to the website and to your email address so that you will not miss it. If your deadline is close at hand, we will place a call to you to make sure that you receive the paper on time.
Completing the order and download