In this project, the front fence will be constructed along the side of the allotment that is bordering the 14 Hemmings Street. The other three sides of the allotment are bordering other allotments or properties and therefore they will require a boundary fence. By definition, a front fence is a fence installed within three meters next to a street boundary and is usually at the front of the plot.
The total length of the front fence is about 18 m.
Reinforcing mesh is only used to reinforce the concrete footing
Size of reinforcing mesh = 18m x 0.3m = 5.4 m2 + 10% wastage
= 5.4m2 + 0.54m2 = 5.94m2 = 6m2
Concrete footing: the dimension of the footing is 18m long, 0.3m wide and 0.6m deep
Volume of concrete footing = 18m x 0.3m x 0.6m = 3.24 m3 + 10% wastage
= 3.24m3 + 0.324m3 = 3.564m3 = 3.6m3
Size of bricks used: 480mm long, 230mm wide and 150mm high
Number of bricks used:
= 150 + 135 = 285 + 10% wastage
= 285 + 28.5 = 313.5 = 314 bricks
Length sandstone capping: 600mm + 2(20mm) = 600mm + 40mm = 640mm
640mm * 9 pieces = 5760mm = 5.76 m + 10% wastage = 5.76m + 0.576m = 6.336m = 6.3 m
Length of metallic panels = 1.7m x 8 pieces = 13.6 m + 10% wastage
= 13.6m + 1.36m = 14.96m = 15m
Item |
Particulars |
Unit |
Quantity |
Rate ($) |
Amount ($) |
1 |
Site clearing and preparation |
Item |
200 |
||
2 |
Excavation |
M3 |
3.6 |
100 |
360 |
3 |
Compaction |
M2 |
6 |
5 |
30 |
4 |
Supply and delivery of reinforcing mesh |
M2 |
6 |
5 |
30 |
5 |
Installation of reinforcing mesh |
Item |
15 |
||
6 |
Supply and placing of footing concrete |
M3 |
3.6 |
200 |
720 |
7 |
Supply and delivery of bricks |
No |
314 |
0.7 |
219.80 |
8 |
Laying of bricks |
Hours |
24 |
40 |
960 |
9 |
Supply and delivery of metallic panels |
M |
15 |
100 |
1500 |
10 |
Installation of metallic panels |
Hours |
8 |
35 |
280 |
11 |
Supply and delivery of sandstone capping |
M |
6.3 |
200 |
1260 |
12 |
Installation of sandstone capping |
Hours |
10 |
35 |
350 |
13 |
Removal of excavated materials |
Item |
500 |
||
14 |
Final cleaning |
Item |
1000 |
||
|
Sub-total 1 |
|
|
|
7,424.8 |
20% Builder’s margin |
1,484.96 |
||||
|
Sub-total 2 |
|
|
|
8,909.76 |
10% GST |
891 |
||||
|
Grand Total |
|
|
|
9,801 |
Part B
Question 1
The labour component of installing the metal panels has been calculated based on the length of panels to be installed. In this case, the total length of the panels to be installed is estimated to be 15 meters. Since the metal panels will be installed after completing the footing, brick fence and sandstone capping, the work can be done in one day. Therefore if all the materials and equipment are available on site, one metal panel installer and one labourer can complete the work in 8 hours. The wage of a metal panel installer and labourer is $23 and $12 per hour respectively. This means that cost of labour per four for metal panel installation is $35. The work will take 8 hours hence total labour cost is $35 x 8 = $280.
Question 2
Since this is a variation, the labour components will not be priced at the same rate as the main project work tendered on. This is because the variation is not part of the original tender and therefore it has to be valued or priced using a different schedule of rates. This variation includes rates of added items of work such as excavating some volumes of soil and constructing a linear distance of fence. It also requires new resources for the added work, such as equipment, materials and labour (Sergeant, 2017). Some of these materials, equipment and labour, such as sandstone capping and metal panel installer, were not needed in the original tender and therefore should be priced separately.
Question 3
Yes, some directly employed labour has been utilized in the costing. The directly employed labour component that has been utilized is the foreman and supervisor. The company will not hire a new foreman or supervisor but will use the ones involved in the main project. The cost of the foreman and supervisor labour has been creatively included in the builder’s margin. The builder’s actual margin for this project is 15% but it has been raised to 20%. By calculation, this gives extra $371.24. Therefore the company will retain a margin of 15% and use the extra $371.24 to pay for the foreman and supervisor’s for the work they will done in relation to the front fence variation.
Question 4
One of the dangers associated with sandstone capping work is defects. Sandstones are porous and therefore susceptible to various environmental conditions such as high humidity, chemical attack and stains. When the material absorbs water, it becomes vulnerable to bacterial growth, mold and stains that reduce its durability (Sandstone Pavers, 2016). These risks can be prevented by ensuring that the sandstone is properly sealed. Another risk is losses when these material is broken. Being a natural stone, sandstone costs higher than other artificial stones and therefore any breakage during installing will be very costly. This risk can be prevented by handling the sandstone carefully during installation.
Part C
Question 1
The main benefit of estimating cost of a task by separately costing the plant, materials and labour required is that each of these components has a different standard rate of cost. For instance, the rate of material is mainly affected by the quantity and quality of materials; the rate of labour is affected by the qualification of the staff, working hours and nature of work to be done (Manfredonia, Majewski, & Perryman, 2016); and the rate of plant is affected by the type of work, working conditions and size of plant. Using these different standard rates helps in lowering the total cost of work. Another benefit is that each of these components are affected by different conditions, such as demand and supply, regional market conditions, political climate, environmental conditions, etc.
For instance, when needed materials are available abundantly, it means their rate will be lower hence this estimation method will significantly reduce the materials cost. Last but not least, this estimation method helps the contractor to get separate discount for each component. For example, if the contractor is ordering large quantities of materials than equipment then he will get more discount on material costs than on equipment costs.
Question 2
The considerations that would affect the decision on whether to tender on a project or not include:
Question 3
Factors that determine suitable size of plant for excavation work include:
Question 4
The builder’s margin include the following:
Question 5
Engineering drawings take precedence over architectural drawings when estimating and constructing a project because the former are easy to read, understand and interpret than the later. Engineering drawings provide more technical details of the project thus making it easier to extract information such as dimensions and other specifications of the system components. These details are very useful when estimating a project and also when constructing the project on site as workers can easily interpret the drawings and construct them.
On the other hand, architectural drawings usually show how the structure should look like by providing details of its plans, sections and elevations (Shah, (n.d.)). These details alone are not enough to help estimate and construct a project. Additionally, engineering drawings go a step further and show the surroundings of the project, such as site conditions, which have significant impact on the cost and constructability of the project. For these reasons, engineering drawings take more precedence than architectural drawings.
Question 6
Many components of the construction process are being sub-contracted to other parties for the following reasons:
Question 7
Some of the issues with obtaining quotations from strange specialist trade or companies include the following:
Communication difficulties: it is rather obvious that communication is always a problem between two new partners. Since the partners still do not understand each other well, they may not disclose all the necessary information on time thus affecting accuracy of cost estimation.
Uncertain integrity and honesty: one of the issues is that their truthfulness and trustworthiness are not guaranteed and therefore their estimates cannot be trusted or relied upon with 100% confidence. This is because the new specialists may have some hidden agenda and therefore provide inaccurate estimates.
The actual accuracy level of the estimates provided may not be known or trusted because the specialists may be used new or unfamiliar methods. Since they are new, it may also be difficult to find out the accuracy of their past estimates.
The knowledge level and experience of the new specialists may not be known thus making it difficult to know whether to completely trust the estimates and rely on them or not.
The methods used and factors considered when estimating the cost may not be fully disclosed thus making it difficult to conclude whether all relevant variables have been accounted for in the cost estimates. It is important to note that these are new people and therefore information disclosure is still limited.
Ethical conduct is another very important issue when obtaining cost estimates from new specialist trades or companies. Some of these specialist trades or companies may be after fulfilling their personal interests and in the process can fail to provide accurate estimates.
Question 8
The on-costs associated with directly employed labour are:
Question 9
Five conditions of a contract that may produce a cost on the project are:
Question 10
There are several ways in which labour cost of a task can be calculated without knowing the time required to complete the work. One of the ways is using the labour rates of similar projects in the past. If the jobs are similar in terms of size, complexity and challenges, the same labour rates from the previous work can be to calculate labour cost of the present work. Another approach is consulting an experienced engineer or quantity surveyor for assistance.
These professionals have the expertise to help estimate labour cost for different construction projects. Other ways include considering the following factors: type and number of personnel needed for the job, the construction process to be followed, the size of the job, the complexity of the job (specifications and plans), the type of equipment to be used in the job, the type and quantity of materials to be used in doing the job, site conditions and potential risks of the project, among others.
References
Mahindra Construction Equipment. (2017, March 3). Factors Affecting Selection of Construction Equipment. Retrieved from MahindraConstruction Equipment:
Manfredonia, W., Majewski, J., & Perryman, J. (2016, November 2). Cost Estimating. Retrieved from Whole Building Design Guide:
Sandstone Pavers. (2016, June 27). All your sandstone questions answered: Price, Types, Installation, Durability. Retrieved from Sandstone avers:
Sergeant, M. (2017, February 13). Valuing variations under a construction contract. Retrieved from Construction
Shah, Y. ((n.d.)). How Are Drawings Used in a Construction Project?
Standards Australia. (2005). AS 4000-1997 General Conditions of Contract. Sydney: Standards Australia.
Essay Writing Service Features
Our Experience
No matter how complex your assignment is, we can find the right professional for your specific task. Contact Essay is an essay writing company that hires only the smartest minds to help you with your projects. Our expertise allows us to provide students with high-quality academic writing, editing & proofreading services.Free Features
Free revision policy
$10Free bibliography & reference
$8Free title page
$8Free formatting
$8How Our Essay Writing Service Works
First, you will need to complete an order form. It's not difficult but, in case there is anything you find not to be clear, you may always call us so that we can guide you through it. On the order form, you will need to include some basic information concerning your order: subject, topic, number of pages, etc. We also encourage our clients to upload any relevant information or sources that will help.
Complete the order formOnce we have all the information and instructions that we need, we select the most suitable writer for your assignment. While everything seems to be clear, the writer, who has complete knowledge of the subject, may need clarification from you. It is at that point that you would receive a call or email from us.
Writer’s assignmentAs soon as the writer has finished, it will be delivered both to the website and to your email address so that you will not miss it. If your deadline is close at hand, we will place a call to you to make sure that you receive the paper on time.
Completing the order and download