Cost estimation is a science that uses various techniques to project the expense of activities and assets a project. Cost estimation anticipates the resources as well as the related costs required to execute a specific project. Therefore cost estimation aid the project manager by making sure that the project attains its objectives within the agreed budget and timeframe. Similarly, Trendowicz and Jeffery (2014) define cost estimation as a practice of predicting the expenses required to complete a project with a defined scope.
Accordingly, cost estimation is the main component of project cost management which entails the knowledge of controlling, monitoring and planning a project’s financial expenses. Thus, the approximated aggregate project expense referred to as cost estimate is utilised to authorise a project’s budget in addition to managing its expenses. The individual who is responsible for preparing a cost estimate is the project manager.
Project managers use defined techniques to create cost estimates which are utilised in analysing the financial feasibility of a certain project, the budget for the project expenses, and monitoring the project expenditure. As a result, an accurate cost estimate is key for deliberating on whether to take on a project, determining the final scope of the project and for making sure that the project remains financially feasible and does not incur cost overruns.
A cost is a set of all the expenses that are involved to ensure that a project is accomplishing all the way from inauguration up to completion. Therefore, these project costs are classified into various approaches and detailed levels (Boardman et al., 2017). The most common and simplest classification groups cost into two major classes direct costs and indirect costs.
Direct costs: These expenses are broadly categorised as those related with a specific part as a project activity. In the case of project management, direct costs are costs which are billed solely to a particular project activity such as the expense of resources to generate physical products; money spends to address specific project risks, wages for the project team and fuel for machinery.
Indirect costs: These are expenses related to a given cost center which are incurred by several projects concurrently and at times with wavering amounts (Harrison, and Lock, 2017). Under project management, security expenses, quality control, and utilities are often categorised as indirect costs because they are jointly used across various projects and are not directly payable to a particular project.
Certainly, a cost estimate is more than a simple list of costs. Nonetheless, a cost estimate also illustrates the underlying assumptions for every cost. Therefore, these assumptions are grouped into a report referred to as the basis of the estimate which describes in detail the cost inclusions and exclusions. Consequently, the basis of estimate offers a chance to the project stakeholders to interpret the costs associated with the project to have a clear picture regarding how and where the actual costs are likely to vary with the projected costs (Mahamid, 2015, p. 117. Furthermore, past the comprehensive divisions of direct and indirect costs, the expenses of a project come in some more distinct subdivisions. Some of the common types of costs include:
The chief constituents of a cost estimate include the development of standard units of measure, determining the quantity units for every component which means the real-time measurement process and determining the reasonable cost for every unit.
When offered with a cost estimate some of the questions that I will ask include:
How did you establish your standard unit of measure?
Which estimate component did you use in determining the number of units?
What is your cost determinant for each unit reasonable?
The contingency plan can be established by exhaustively analysing the risks facing a specific project. Therefore, when developing a contingency plan the project manager and the team ought to always adhere to the following principles:
Maintaining the project operations by closely focusing on what is to be realised by delivering a minimum level of service and operability.
Defining the project’s timeframe.
Identifying the triggering factors that are likely to cause the project to develop a contingency plan.
The contingency plan should be made simple and clear
Defining success that is what is required to ensure the projected return to usual business operation.
Question 2: Managing and reporting cost & schedule
Provide an outline of the EVM concepts for senior management to review. Include your summary your analysis as to whether this concept would be beneficial for adopting and also what some of the challenges may be (e.g., advantages/disadvantages)
Earned value management (EVM) is a practise used by project managers to quantity the performance of the project as well as its progress in an objective way (Fleming, and Koppelman, 2016). Accordingly, EVM can collectively include the measurements of the three elements of the project management triangle that is costs, scope and time.
Therefore, earned value management can accurately project the performance problems of a project in a single integrated system. Indeed, this is a significant plus to project management (Batselier, and Vanhoucke, 2015). Therefore earned value management is a systematic project management tactic that is utilised to determine changes in projects with regard to the differences of work planned and work performed. Consequently, EVM is vital on the schedule and cost control which is important to predicting the project, hence EVM offers project managers with quantitative data for making project decisions.
Advantages of Earned Value Management
NASA research shows that the initial version of EVM was advanced by the Defence Department (DOD) to monitors its programs in the 1960s (Colin, and Vanhoucke, 2015, p. 3160). In the recent past, EVM has become a compulsory requirement for the administration of the United States whereby the Office of Management and Budget (OMB) is supporting the application of EVM as the most effective performance-oriented management system for controlling software projects (Davies, 2016). Similarly, EVM is gaining strides in different sectors such as education institutions, consulting corporations, and private industries.
Measures of Earned Value Management
The EVM comprises both derived data and primary components having individual data point value being built on the period when the EVM was undertaken on the project (Webb, 2017).
Primary data points
Budget At Completion (BAC): refers to the overall project costs.
Budgeted Cost for Work Scheduled (BCWS)/Planned Value (PV): It refers to the amount of time conveyed in Pounds of the work carried out alongside the schedule plan
PV = BAC* percentage of planned work.
Budgeted Cost for Work Performed (BCWP)/Earned Value (EV): It refers to the time amount expressed in Pounds on the real work undertaken
EV = BAC * percentage of actual work
Actual Cost of Work Performed (ACWP)/ Actual Coat (AC): It refers to the actual cost expressed in Pounds that is spent on a given task up to date.
Derived Datapoints
Derived data points
The expected total costs needed to accomplish the work
EAC = BAC/CPI
= AC + ETC
= AC + ((BAC-EV) / CPI) this is for a typical scenario
= AC + (BAC –EV) for an atypical scenario where atypical assumes that the same variance is not likely to happen in future
Estimated to Complete (ETC): It refers to the projected expense needed to complete all the outstanding work.
ETC = EAC – AC
= (BAC / CPI) – (EV/CPI)
= (BAC – EV) / CPI
Cost Variance (CV) illustrates the level of under or over budget
CV = EV – AC a negative sign means over budget while positive is under budget
Schedule Variances (SV) it shows the extent to which the project is lagging or is ahead of timeframe.
SV = EV – PV negative sign imply behind schedule and positive ahead of schedule
Variance At Completion (VAC): refers to the variance of the entire cost of the work and projected cost
VAC = BAC – EAC
Cost performance index
CPI = EV /AC where < 1 means over and > 1 under budget
Schedule performance index
SPI = EV / PV where > 1 means ahead and < 1 means behind the schedule
For each scenario list your assessment of
Scenario 1: CPI = EV/AC
= 80/50 and 3700/3100
= 1.6 and 1.193 respectively which means that the scenario is under budget.
Scenario 2: CPI = EV/AC
= 50/80 and 3100/3700
0.625 and 0.838 meaning the scenario under budget
Scenario 3: CPI = EV/AC
= 15/10
= 1.5 meaning it is under budget
Scenario 4: CPI = EV/AC
1900/1350
= 1.407 meaning it is under budget
All the four scenarios have a positive cost variance (CV) thus, they are all under budget.
Scenario 1
SV = EV – PV
= 80-50 = 30-scenario 1 is ahead of schedule
SPI = EV/PV
= 80/30 = 2.67-which means it is ahead of schedule
Scenario 2
SV = EV – PV
50-80 = -30-sceraio 2 is behind the schedule
SPI = EV/PV
50/30 = 1.67- which means it is ahead of schedule
Scenario 3
SV = EV – PV
15-10 = 5-scenario 3 is ahead of schedule
SPI = EV/PV
15/30 = 0.5- which means it is ahead of schedule
Scenario 4
SV = EV – PV
15 -10 = 5- scenario 4 is ahead of schedule
SPI = EV/PV
15/30 = 0.5 – which means it is ahead of schedule
Critical ratio is determined as a measure of the achieved progress against the planned progress of a project. Therefore, the critical ratio comprises a schedule performance index and cost performance index. Therefore, for SPI scenario 1 and 2 their tasks are ahead of schedule which 3 and 4 their task and behind schedule. In the case of CPI tasks for scenario 2 are behind schedule while tasks for scenario 1, 3 and 4 are ahead of the task.
What the data may indicate re: project performance
What are some possible factors/causes?
Any recommendations that you would make as the PM?
Based on the data for scenario 1, 3 and 4 it indicates data the project performance for these is effective because both the cost performance index and cost variance, schedule variance and schedule performance index are all under budget and ahead of schedule respectively. However, the performance of the scenario seems to have incurred problems since its schedule performance index is behind schedule.
Some of the possible factors that could be doing the project to lag could be introducing changes in the course of the project. As a project manager, I would recommend that the project should involve stakeholders in all project stages to help in identifying all the possible needs to be accomplished by the project. Involvement of stakeholders helps to reduce the probability of introducing change along the project course. Consequently, as such help to guarantee that the project is delivered in time, under approved budget and effectively meet customer requirements.
Batselier, J. and Vanhoucke, M., 2015. Empirical evaluation of earned value management forecasting accuracy for time and cost. Journal of Construction Engineering and Management, 141(11), p.05015010.
Boardman, A.E., Greenberg, D.H., Vining, A.R. and Weimer, D.L., 2017. Cost-benefit analysis: concepts and practice. Cambridge University Press.
Colin, J. and Vanhoucke, M., 2015. A comparison of the performance of various project control methods using earned value management systems. Expert Systems with Applications, 42(6), pp.3159-3175.
Davies, R.H., 2016. Value management: Translating aspirations into performance. Routledge.
Fleming, Q.W. and Koppelman, J.M., 2016, December. Earned value project management. Project Management Institute.
Harrison, F. and Lock, D., 2017. Advanced project management: a structured approach. Routledge.
Hatamleh, M.T., Hiyassat, M., Sweis, G.J. and Sweis, R.J., 2018. Factors affecting the accuracy of cost estimate: case of Jordan. Engineering, Construction and Architectural Management, 25(1), pp.113-131.
Mahamid, I., 2015. Factors affecting cost estimate accuracy: Evidence from Palestinian construction projects. International Journal of Management Science and Engineering Management, 10(2), pp.117-125.
Trendowicz, A. and Jeffery, R., 2014. Software project effort estimation. Foundations and Best Practice Guidelines for Success, Constructive Cost Model–COCOMO pags, pp.277-293.
Webb, A., 2017. Using earned value: a project manager’s guide. Routledge.
Essay Writing Service Features
Our Experience
No matter how complex your assignment is, we can find the right professional for your specific task. Contact Essay is an essay writing company that hires only the smartest minds to help you with your projects. Our expertise allows us to provide students with high-quality academic writing, editing & proofreading services.Free Features
Free revision policy
$10Free bibliography & reference
$8Free title page
$8Free formatting
$8How Our Essay Writing Service Works
First, you will need to complete an order form. It's not difficult but, in case there is anything you find not to be clear, you may always call us so that we can guide you through it. On the order form, you will need to include some basic information concerning your order: subject, topic, number of pages, etc. We also encourage our clients to upload any relevant information or sources that will help.
Complete the order formOnce we have all the information and instructions that we need, we select the most suitable writer for your assignment. While everything seems to be clear, the writer, who has complete knowledge of the subject, may need clarification from you. It is at that point that you would receive a call or email from us.
Writer’s assignmentAs soon as the writer has finished, it will be delivered both to the website and to your email address so that you will not miss it. If your deadline is close at hand, we will place a call to you to make sure that you receive the paper on time.
Completing the order and download