The following assignment had been developed for listing the elements of project in a project charter document for the project of ‘Develop a higher education website for students’. The project charter would serve the option for transferring the initial information to the project team members and the aligning the utilization of the effective management and operations (Ekrot, Kock & Gemünden, 2016). The charter document would help the project team for understanding the basic information and initial requirements for the project. A WBS of project plan is included this report for developing the understanding of the effective completion. The complete charter document would align with the inclusion of the prospects of development and understanding. The alignment would also be helpful for easing the simplification and development.
The objectives of the project of ‘Develop a higher education website for students’ are,
The scope of the project of ‘Develop a higher education website for students’ is given below,
In scope: The documentation of project progress, project plan development, design of website, development of website, testing, and go live are the in scope items of the project.
Out of scope: The training and change management are out of scope items of the project as they are not in need for the completion of the project.
The MOV is the analysis of the project outcomes based on the factors of better, faster, cheaper, and do more. The project deliverable of website for students has been analysed on these factors as given below,
Better |
The development of the website would allow the integration of the information and aligning the single database for the higher education information. |
Faster |
The students would be able to access the information from a single platform and it would align with the increasing the faster access to the information. |
Cheaper |
Since no other resources would be required for accessing information, it would consume less resources for the operations |
Do More |
The students can provide feedback on the information and review it for improving the operations |
The waterfall methodology has been selected for the development of the website as it would allow the utilization of the effective and improved operations. The activities would result in listing the project for developing and designing the website using innovative tools and operations. The following diagram would show the waterfall methodology model,
Reason for selection of Waterfall Methodology: The waterfall methodology would allow the use of sequential process and it would help in getting the following benefits for the project of website development,
Strengths |
Weakness |
Steady process All information is pre-assumed and analysed All process would be completed sequentially |
Tracking is not possible Inclusion of change management would be difficult Time consuming |
Strengths: The use of waterfall methodology would be helpful for defining the completion of the project management operations. The waterfall methodology is helpful as it is a steady process and involves the support and development of the effective operations. The involvement of the processes would be aligned with the formation of the information access and development. The utilization of the successive management process would involve the utilization of the sequence completion of the project. The implication of waterfall methodology is helpful for ensuring the effective completion of the project.
Weaknesses: The lack of possibility of progress tracking would be helpful for making the major drawback for the use of the methodology. The management of the processes would involve the utilization of the proper and effective management processing. The change management would provide the major role for project of website development. However, using waterfall methodology, the project would not get the opportunity of developing change management process.
Stakeholders |
Power |
Influence |
Role |
Client |
High |
High |
Providing initial requirements for the project |
Sponsors |
High |
Low |
Providing the resources required for the project |
End Users |
Low |
Low |
Using the end product of the project |
Project team |
Low |
High |
Executing the project activities |
Contractor |
High |
Low |
Inspection the functionality of the website and making it Go live |
Communication Plan
Sender |
Information |
Method of Communication |
Frequency |
Receiver |
Client |
Project Requirements |
Board Meeting |
Once |
|
Project Manager |
Project Requirements |
Reports |
Once |
Project team |
Project Manager |
Project Progress |
Meetings |
Weekly |
Client |
Project team |
Project Progress |
Emails |
Monthly |
Project Manager |
The leadership qualities of the project manager are,
Excellent Communication: the project manager must be able to communicate with the project team members and the client about the requirements and progress of project.
Positive Attitude: the project manager must bring positivity in the operations for motivating the project team members.
Competence and Integrity: The project manager must possess the qualities of competence and integrity of the operations.
Team Builder: The project manager would have to make sure that project team would be managed and executed by the use of the effective operations.
Cool, Calm, and Problem Solver: The project manager must have cool mind and he/she would be responsible for solving the problems of the project calmly.
Resource Name |
Roles and Responsibilities |
Analyst |
Analyzing the requirements of the project |
Documenter |
Developing the project documents |
Project Manager |
Management of the project activities |
Planner |
Forming the project plan |
Risk Analyst |
Mitigation the risk factors identified |
HR manager |
Managing the resources of the project and communication process |
Designer |
Developing the design of the website |
Tester |
Testing the functionality of the website developed |
Developer |
Developing the website supporting the inclusion of the information of the higher studies |
Consulting Engineer |
Inspecting the final operations of the website |
The work breakdown structure for the project of Develop a higher education website for students would comprise of developing an understanding of the progress of the project and align it with the formation of the smart and effective management process. The implication of the effective and smart project completion would be aligned for developing the smart identification of the project completions. The work packages of the project include the phases of initial phase, planning phase, execution phase (includes work packages of website designing and website developing), and closure. The initial phase is the first work package required for developing the effective and improved operation development for initialization of the project operations and it includes the activities of requirement analysis, charter documentation, resource accumulation, submission of documents, review and signs off, and kick off. The second work package is the planning phase that would result in identification of the activities required for the completion of the project and forming the schedule for the activities. The activities of this work package are activities are listed, scheduling of the project activities, risk management planning, communication planning, and plan approvals. The execution phase is the work package comprising of sub work packages of website designing and developing. It is the main work package as the website development and designing is the most crucial aspect of modifying the influence of managing the configuration of the operations. The activities of the website designing include interface of website developed, review of functions, design development, simulation of design, and design approval. The activities of website development include functions are programmed, website features are developed, structure of website is developed, all functions are integrated, alpha testing, beta testing, and system developed. The final work package of the project is closure that results in termination of the project. Final documents are made, inspection, submission of documents, review and sign off, and closed are the inclusive work of the work package. The following is the work breakdown structure for the project,
The project of ‘Develop a higher education website for students’ has been developed for designing and developing the website for the students so that they can access information and develop an identification of the aspects of development. The identified activities would be inclusive of documentation and planning process along with the website development and designing. The task list is given below,
WBS |
Task Name |
0 |
Develop a higher education website for students |
1 |
Initial Phase |
1.1 |
Requirement Analysis |
1.2 |
Charter Documentation |
1.3 |
Resource Accumulation |
1.4 |
Submission of documents |
1.5 |
Review and Sign off |
1.6 |
Kick off |
2 |
Planning Phase |
2.1 |
Activities are listed |
2.2 |
Scheduling of the project activities |
2.3 |
Risk management planning |
2.4 |
Communication Planning |
2.5 |
Plan Approvals |
3 |
Execution Phase |
3.1 |
website Designing |
3.1.1 |
Interface of website developed |
3.1.2 |
Review of Functions |
3.1.3 |
Design Development |
3.1.4 |
Simulation of design |
3.1.5 |
Design Approval |
3.2 |
Website Development |
3.2.1 |
Functions are programmed |
3.2.2 |
Website Features are developed |
3.2.3 |
Structure of website is developed |
3.2.4 |
All functions are integrated |
3.2.5 |
Alpha testing |
3.2.6 |
Beta testing |
3.2.7 |
System Developed |
4 |
Closure |
4.1 |
Final Documents are made |
4.2 |
Inspection |
4.3 |
Submission of documents |
4.4 |
Review and Sign off |
4.5 |
Closed |
The project is divided into phases and the completion of the activities would be summed for getting the duration of the phase. The addition of the time taken for the completion of the each of the phases would result in developing the final project deliverable. The following is the time taken for the project activities,
WBS |
Task Name |
Duration |
Start |
Finish |
0 |
Develop a higher education website for students |
66 days |
Mon 10/1/18 |
Mon 12/31/18 |
1 |
Initial Phase |
10 days |
Mon 10/1/18 |
Fri 10/12/18 |
1.1 |
Requirement Analysis |
2 days |
Mon 10/1/18 |
Tue 10/2/18 |
1.2 |
Charter Documentation |
2 days |
Wed 10/3/18 |
Thu 10/4/18 |
1.3 |
Resource Accumulation |
4 days |
Fri 10/5/18 |
Wed 10/10/18 |
1.4 |
Submission of documents |
1 day |
Thu 10/11/18 |
Thu 10/11/18 |
1.5 |
Review and Sign off |
1 day |
Fri 10/12/18 |
Fri 10/12/18 |
1.6 |
Kick off |
0 days |
Fri 10/12/18 |
Fri 10/12/18 |
2 |
Planning Phase |
12 days |
Mon 10/15/18 |
Tue 10/30/18 |
2.1 |
Activities are listed |
2 days |
Mon 10/15/18 |
Tue 10/16/18 |
2.2 |
Scheduling of the project activities |
3 days |
Wed 10/17/18 |
Fri 10/19/18 |
2.3 |
Risk management planning |
4 days |
Mon 10/22/18 |
Thu 10/25/18 |
2.4 |
Communication Planning |
3 days |
Fri 10/26/18 |
Tue 10/30/18 |
2.5 |
Plan Approvals |
0 days |
Tue 10/30/18 |
Tue 10/30/18 |
3 |
Execution Phase |
58 days |
Mon 10/1/18 |
Wed 12/19/18 |
3.1 |
website Designing |
12 days |
Wed 10/31/18 |
Thu 11/15/18 |
3.1.1 |
Interface of website developed |
3 days |
Wed 10/31/18 |
Fri 11/2/18 |
3.1.2 |
Review of Functions |
2 days |
Mon 11/5/18 |
Tue 11/6/18 |
3.1.3 |
Design Development |
5 days |
Wed 11/7/18 |
Tue 11/13/18 |
3.1.4 |
Simulation of design |
2 days |
Wed 11/14/18 |
Thu 11/15/18 |
3.1.5 |
Design Approval |
0 days |
Thu 11/15/18 |
Thu 11/15/18 |
3.2 |
Website Development |
58 days |
Mon 10/1/18 |
Wed 12/19/18 |
3.2.1 |
Functions are programmed |
4 days |
Fri 11/16/18 |
Wed 11/21/18 |
3.2.2 |
Website Features are developed |
3 days |
Thu 11/22/18 |
Mon 11/26/18 |
3.2.3 |
Structure of website is developed |
5 days |
Tue 11/27/18 |
Mon 12/3/18 |
3.2.4 |
All functions are integrated |
6 days |
Tue 12/4/18 |
Tue 12/11/18 |
3.2.5 |
Alpha testing |
3 days |
Wed 12/12/18 |
Fri 12/14/18 |
3.2.6 |
Beta testing |
3 days |
Mon 12/17/18 |
Wed 12/19/18 |
3.2.7 |
System Developed |
0 days |
Mon 10/1/18 |
Mon 10/1/18 |
4 |
Closure |
8 days |
Thu 12/20/18 |
Mon 12/31/18 |
4.1 |
Final Documents are made |
2 days |
Thu 12/20/18 |
Fri 12/21/18 |
4.2 |
Inspection |
4 days |
Mon 12/24/18 |
Thu 12/27/18 |
4.3 |
Submission of documents |
1 day |
Fri 12/28/18 |
Fri 12/28/18 |
4.4 |
Review and Sign off |
1 day |
Mon 12/31/18 |
Mon 12/31/18 |
4.5 |
Closed |
0 days |
Mon 12/31/18 |
Mon 12/31/18 |
The project comprises of a number of resources for taking care of the activities and aligning with the completion of the effective project completion. The project team would comprise of Analyst, Documenter, Project Manager, Planner, Risk Analyst, HR manager, Designer, Tester, Developer, and Consulting Engineer. The following is the responsible activities of the project human resources for the completion of the activities,
Resource Name |
Responsibilities |
Work |
Analyst |
Requirement Analysis |
16 hrs |
Documenter |
Charter Documentation Submission of documents Final Documents are made Submission of documents |
48 hrs |
Project Manager |
Resource Accumulation Review and Sign off Review and Sign off |
48 hrs |
Planner |
Activities are listed Scheduling of the project activities |
40 hrs |
Risk Analyst |
Risk management planning |
32 hrs |
HR manager |
Communication Planning |
24 hrs |
Designer |
Interface of website developed Review of Functions Design Development Website Features are developed Structure of website is developed All functions are integrated |
192 hrs |
Tester |
Simulation of design Alpha testing Beta testing |
64 hrs |
Developer |
Functions are programmed |
32 hrs |
Consulting Engineer |
Inspection |
32 hrs |
Conclusion
It can be concluded from the assignment that the development had been effectively implied for easing the utilization of the formation development. The alignment had been involved for improving the management of the successive inclusion management. The involvement had been implied for easing the successful development model. The completion of the project of ‘Develop a higher education website for students’ had been done for developing a website for the students for accessing information of higher studies. A WBS of project plan was included this report for developing the understanding of the effective completion. The complete charter document had aligned with the inclusion of the prospects of development and understanding. The alignment had also helped for easing the simplification and development.
Amrollahi, A., Ghapanchi, A. H., & Talaei-Khoei, A. (2014). Three decades of research on strategic information system plan development.Communications of the Association for Information Systems, 34(1), 84.
Bentahar, O., & Cameron, R. (2015). Design and Implementation of a Mixed Method Research Study in Project Management. Electronic Journal of Business Research Methods, 13(1).
Braglia, M., & Frosolini, M. (2014). An integrated approach to implement project management information systems within the extended enterprise.International Journal of Project Management, 32(1), 18-29.
Cagliano, A. C., Grimaldi, S., & Rafele, C. (2015). Choosing project risk management techniques. A theoretical framework. Journal of Risk Research, 18(2), 232-248.
Cs.bilkent.edu.tr. (2018). A Guide To Project Management Body Of Knowledge. Retrieved 28 August 2018, from https://www.cs.bilkent.edu.tr/~cagatay/cs413/PMBOK.pdf
Drury-Grogan, M.L., 2014. Performance on agile teams: Relating iteration objectives and critical decisions to project management success factors. Information and Software Technology, 56(5), pp.506-515.
Ekrot, B., Kock, A. & Gemünden, H.G., (2016). Retaining project management competence—Antecedents and consequences. International Journal of Project Management, 34(2), pp.145-157.
Fleming, Q. W., & Koppelman, J. M. (2016, December). Earned value project management. Project Management Institute.
Ghosal, S., Chaturvedi, S., Taywade, A., & Jaisankar, N. (2015). Android application for ticket booking and ticket checking in suburban railways. Indian Journal of Science and Technology, 8(S2), 171-178.
Giorgadze, L., Alibiev, D., Chirico, G. D., & Kazhikenova, A. S. (2017). Minimization of product defects by the means of implementing correct test pyramid in the software development process.
Goetsch, D. L., & Davis, S. B. (2014). Quality management for organizational excellence. pearson.
Mahadevan, L., Kettinger, W. J., & Meservy, T. O. (2015). Running on Hybrid: Control Changes when Introducing an Agile Methodology in a Traditional” Waterfall” System Development Environment. CAIS, 36, 5.
Pmi.org. (2013). A Guide To Project Management Body Of Knowledge. Retrieved 28 August 2018, from https://www.pmi.org/-/media/pmi/documents/public/pdf/pmbok-standards/pmbok-guide-5th-errata.pdf
Špundak, M. (2014). Mixed agile/traditional project management methodology–reality or illusion?. Procedia-Social and Behavioral Sciences, 119, 939-948.
Works.gov.bh. (2018). A Guide To Project Management Body Of Knowledge. Retrieved 28 August 2018, from https://www.works.gov.bh/English/ourstrategy/Project%20Management/Documents/Other%20PM%20Resources/PMBOKGuideFourthEdition_protected.pdf
Www2.fiit.stuba.sk. (2018). A GUIDE TO PROJECT MANAGEMENT BODY OF KNOWLEDGE. Retrieved 28 August 2018, from https://www2.fiit.stuba.sk/~bielik/courses/msi-slov/reporty/pmbok.pdf
Essay Writing Service Features
Our Experience
No matter how complex your assignment is, we can find the right professional for your specific task. Contact Essay is an essay writing company that hires only the smartest minds to help you with your projects. Our expertise allows us to provide students with high-quality academic writing, editing & proofreading services.Free Features
Free revision policy
$10Free bibliography & reference
$8Free title page
$8Free formatting
$8How Our Essay Writing Service Works
First, you will need to complete an order form. It's not difficult but, in case there is anything you find not to be clear, you may always call us so that we can guide you through it. On the order form, you will need to include some basic information concerning your order: subject, topic, number of pages, etc. We also encourage our clients to upload any relevant information or sources that will help.
Complete the order formOnce we have all the information and instructions that we need, we select the most suitable writer for your assignment. While everything seems to be clear, the writer, who has complete knowledge of the subject, may need clarification from you. It is at that point that you would receive a call or email from us.
Writer’s assignmentAs soon as the writer has finished, it will be delivered both to the website and to your email address so that you will not miss it. If your deadline is close at hand, we will place a call to you to make sure that you receive the paper on time.
Completing the order and download