The project is being developed for forming the accurate and systematic development of the project operations. The project would evaluate the use of project management concepts for the project of developing a browser application on iOS platform that would allow direct downloading from the Internet platform. The project would integrate the use of application development and project management concepts for forming the appropriate development of the project operations. The development of the project operations would help in developing plan for implementing the integrated operations of the project for developing the applications on iOS platform.
1. Major Deliverables, End Results, and Stakeholders
1.1 Deliverables table for the project
The major deliverables for the project are given in the table below,
Major Deliverables |
Finish Date |
Gathering Human and non Human Resources |
Tue 6/6/17 |
Making Project Charter Document |
Thu 6/8/17 |
Project Manager’s approval of charter |
Tue 6/13/17 |
Developing plan outline |
Tue 6/20/17 |
Developing architecture plan for designing |
Tue 7/11/17 |
Approval of plan and design |
Wed 7/12/17 |
Making design outline |
Tue 7/25/17 |
Completing the design |
Tue 8/8/17 |
Application Interface development |
Fri 8/25/17 |
Developing program for application |
Tue 9/19/17 |
Integrating the program with application |
Thu 9/28/17 |
URL integration |
Thu 10/5/17 |
CSS development |
Thu 10/12/17 |
HTML integration |
Thu 10/19/17 |
Direct download function implication |
Tue 10/31/17 |
Application Testing |
Wed 11/29/17 |
Getting patents of design, function and browser name |
Mon 12/4/17 |
Released in App store for some users |
Wed 12/6/17 |
Government Approval |
Tue 12/19/17 |
Released to all users |
Mon 12/25/17 |
Making final reports |
Thu 12/28/17 |
Signing off the reports |
Mon 1/1/18 |
1.2 End Result of the Project
The project had been made for developing the application browser for iOS platform that would enable direct downloading from the Internet Platform. The project would form the specific development of project operations for integration of the project management concepts and the application development activities for developing a new application compatible with iOS base that allow direct downloads.
1.3 Stakeholders of the project
The list of stakeholders and their roles in the project had been given below.
Resource Name |
Roles and Responsibilities |
Project Manager |
Approval of charter |
Approval of plan and design |
|
Signing off the reports |
|
Project Closure |
|
Project Planner |
Selecting methodology for plan |
Developing plan outline |
|
Alignment of plan with project objectives |
|
Project Budgeter |
Analyzing the requirements of the project |
Gathering Human and non Human Resources |
|
Developer |
UX styling platform is selected |
UX appearance and theme is developed |
|
Color and Font is developed |
|
Fixing any issues |
|
Designer |
Implementing the architecture plan for designing |
Making design outline |
|
Reviewing the design |
|
Completing the design |
|
Tester |
Design Testing |
Program Testing |
|
Web connectivity testing |
|
Direct download function testing |
|
Security Testing |
|
Programmer |
Selecting programming platform |
Developing program for application |
|
Integrating the program with application |
|
Direct download function implication |
|
System Analyst |
Analyzing the design requirements |
Developing architecture plan for designing |
|
Direct download function implication |
|
Released to all users |
|
URL integration |
|
CSS development |
|
HTML integration |
|
Direct download function implication |
|
Clerk |
Making Project Charter Document |
Submitting the Document |
|
Getting feedbacks from the users |
|
Making final reports |
2. Motivation for the project
The project had been chosen for forming the accurate development of project operations for integrating the activities of the system development. The main reason that would be developed for implementing the project is the need for direct downloading in the system. The browser of iOS would be developed for forming the system integration and formation of the accurate development function.
4.1 In Tabular format
WBS |
Task Name |
Duration |
Start |
Finish |
Resource Names |
Cost |
0 |
Development of Browser Application for direct downloading in IOS platform |
157 days |
Mon 5/29/17 |
Tue 1/2/18 |
$134,380.00 |
|
1 |
Project Initialization |
12 days |
Mon 5/29/17 |
Tue 6/13/17 |
$7,880.00 |
|
1.1 |
Analyzing the requirements of the project |
2 days |
Mon 5/29/17 |
Tue 5/30/17 |
Project Budgeter |
$1,280.00 |
1.2 |
Gathering Human and non Human Resources |
5 days |
Wed 5/31/17 |
Tue 6/6/17 |
Project Budgeter |
$3,200.00 |
1.3 |
Making Project Charter Document |
2 days |
Wed 6/7/17 |
Thu 6/8/17 |
Clerk |
$1,200.00 |
1.4 |
Submitting the Document |
2 days |
Fri 6/9/17 |
Mon 6/12/17 |
Clerk |
$1,200.00 |
1.5 |
Project Manager’s approval of charter |
1 day |
Tue 6/13/17 |
Tue 6/13/17 |
Project Manager |
$1,000.00 |
2 |
Architecture and Planning |
21 days |
Wed 6/14/17 |
Wed 7/12/17 |
$14,680.00 |
|
2.1 |
Selecting methodology for plan |
2 days |
Wed 6/14/17 |
Thu 6/15/17 |
Project Planner |
$1,280.00 |
2.2 |
Developing plan outline |
3 days |
Fri 6/16/17 |
Tue 6/20/17 |
Project Planner |
$1,920.00 |
2.3 |
Alignment of plan with project objectives |
4 days |
Wed 6/21/17 |
Mon 6/26/17 |
Project Planner |
$2,560.00 |
2.4 |
Analyzing the design requirements |
3 days |
Tue 6/27/17 |
Thu 6/29/17 |
System Analyst |
$2,160.00 |
2.5 |
Developing architecture plan for designing |
8 days |
Fri 6/30/17 |
Tue 7/11/17 |
System Analyst |
$5,760.00 |
2.6 |
Approval of plan and design |
1 day |
Wed 7/12/17 |
Wed 7/12/17 |
Project Manager |
$1,000.00 |
3 |
Application Design |
19 days |
Thu 7/13/17 |
Tue 8/8/17 |
$15,200.00 |
|
3.1 |
Implementing the architecture plan for designing |
5 days |
Thu 7/13/17 |
Wed 7/19/17 |
Designer |
$4,000.00 |
3.2 |
Making design outline |
4 days |
Thu 7/20/17 |
Tue 7/25/17 |
Designer |
$3,200.00 |
3.3 |
Reviewing the design |
2 days |
Wed 7/26/17 |
Thu 7/27/17 |
Designer |
$1,600.00 |
3.4 |
Completing the design |
8 days |
Fri 7/28/17 |
Tue 8/8/17 |
Designer |
$6,400.00 |
4 |
Application Development |
60 days |
Wed 8/9/17 |
Tue 10/31/17 |
$64,120.00 |
|
4.1 |
Application Interface development |
13 days |
Wed 8/9/17 |
Fri 8/25/17 |
$11,440.00 |
|
4.1.1 |
UX styling platform is selected |
2 days |
Wed 8/9/17 |
Thu 8/10/17 |
Developer |
$1,760.00 |
4.1.2 |
UX appearance and theme is developed |
7 days |
Fri 8/11/17 |
Mon 8/21/17 |
Developer |
$6,160.00 |
4.1.3 |
Color and Font is developed |
4 days |
Tue 8/22/17 |
Fri 8/25/17 |
Developer |
$3,520.00 |
4.2 |
Application Programming |
24 days |
Mon 8/28/17 |
Thu 9/28/17 |
$22,080.00 |
|
4.2.1 |
Selecting programming platform |
2 days |
Mon 8/28/17 |
Tue 8/29/17 |
Programmer |
$1,840.00 |
4.2.2 |
Developing program for application |
15 days |
Wed 8/30/17 |
Tue 9/19/17 |
Programmer |
$13,800.00 |
4.2.3 |
Integrating the program with application |
7 days |
Wed 9/20/17 |
Thu 9/28/17 |
Programmer |
$6,440.00 |
4.3 |
Web function implementation |
23 days |
Fri 9/29/17 |
Tue 10/31/17 |
$30,600.00 |
|
4.3.1 |
URL integration |
5 days |
Fri 9/29/17 |
Thu 10/5/17 |
Web Expert |
$3,800.00 |
4.3.2 |
CSS development |
5 days |
Fri 10/6/17 |
Thu 10/12/17 |
Web Expert |
$3,800.00 |
4.3.3 |
HTML integration |
5 days |
Fri 10/13/17 |
Thu 10/19/17 |
Web Expert |
$3,800.00 |
4.3.4 |
Direct download function implication |
8 days |
Fri 10/20/17 |
Tue 10/31/17 |
Programmer, Web Expert, System Analyst |
$19,200.00 |
5 |
Application Testing |
21 days |
Wed 11/1/17 |
Wed 11/29/17 |
$15,960.00 |
|
5.1 |
Design Testing |
4 days |
Wed 11/1/17 |
Mon 11/6/17 |
Tester |
$3,040.00 |
5.2 |
Program Testing |
4 days |
Tue 11/7/17 |
Fri 11/10/17 |
Tester |
$3,040.00 |
5.3 |
Web connectivity testing |
4 days |
Mon 11/13/17 |
Thu 11/16/17 |
Tester |
$3,040.00 |
5.4 |
Direct download function testing |
4 days |
Fri 11/17/17 |
Wed 11/22/17 |
Tester |
$3,040.00 |
5.5 |
Security Testing |
5 days |
Thu 11/23/17 |
Wed 11/29/17 |
Tester |
$3,800.00 |
6 |
Application Deployment |
18 days |
Thu 11/30/17 |
Mon 12/25/17 |
$11,740.00 |
|
6.1 |
Getting patents of design, function and browser name |
3 days |
Thu 11/30/17 |
Mon 12/4/17 |
Patent Rights[1] |
$1,200.00 |
6.2 |
Released in App store for some users |
2 days |
Tue 12/5/17 |
Wed 12/6/17 |
IOS Authorization[1] |
$2,000.00 |
6.3 |
Getting feedbacks from the users |
4 days |
Thu 12/7/17 |
Tue 12/12/17 |
Clerk |
$2,400.00 |
6.4 |
Fixing any issues |
2 days |
Wed 12/13/17 |
Thu 12/14/17 |
Developer |
$1,760.00 |
6.5 |
Government Approval |
3 days |
Fri 12/15/17 |
Tue 12/19/17 |
Government Permission[1] |
$1,500.00 |
6.6 |
Released to all users |
4 days |
Wed 12/20/17 |
Mon 12/25/17 |
System Analyst |
$2,880.00 |
7 |
Project documentation |
5 days |
Tue 12/26/17 |
Mon 1/1/18 |
$3,800.00 |
|
7.1 |
Making final reports |
3 days |
Tue 12/26/17 |
Thu 12/28/17 |
Clerk |
$1,800.00 |
7.2 |
Signing off the reports |
2 days |
Fri 12/29/17 |
Mon 1/1/18 |
Project Manager |
$2,000.00 |
8 |
Project is closed |
1 day |
Tue 1/2/18 |
Tue 1/2/18 |
Project Manager |
$1,000.00 |
Conclusion
The project network diagram and the critical path had shown that the project activities are in line with the operations of the project. The dependencies of the project activities had shown that the operations of the project have occurred one after another. The constraint of the project is ‘as soon as possible’ and it would develop the practical development of the project. The project had integrated the use of application development and project management concepts for forming the appropriate development of the project operations. The development of the project operations had helped in developing plan for implementing the integrated operations of the project for developing the applications on iOS platform.
Burke, R. (2013). Project management: planning and control techniques. New Jersey, USA.
Heagney, J. (2016). Fundamentals of project management. AMACOM Div American Mgmt Assn.
Kerzner, H. (2013). Project management: a systems approach to planning, scheduling, and controlling. John Wiley & Sons.
Leach, L. P. (2014). Critical chain project management. Artech House.
Mir, F. A., & Pinnington, A. H. (2014). Exploring the value of project management: linking project management performance and project success. International Journal of Project Management, 32(2), 202-217.
Schwalbe, K. (2015). Information technology project management. Cengage Learning.
Turner, J. R. (2014). The handbook of project-based management (Vol. 92). New York, NY: McGraw-hill.
Walker, A. (2015). Project management in construction. John Wiley & Sons.
Lawn, S., Delany, T., Sweet, L., Battersby, M., & Skinner, T. (2015). Barriers and enablers to good communication and information-sharing practices in care planning for chronic condition management. Australian journal of primary health, 21(1), 84-89.
Majchrzak, A., Beath, C. M., Lim, R., & Chin, W. (2014). Managing client dialogues during information systems design to facilitate client learning.
Olson, D. (2014). Information systems project management. Business Expert Press.
Osseiran, A., Boccardi, F., Braun, V., Kusume, K., Marsch, P., Maternia, M., … & Tullberg, H. (2014). Scenarios for 5G mobile and wireless communications: the vision of the METIS project. IEEE Communications Magazine, 52(5), 26-35.
Park, J. G., & Lee, J. (2014). Knowledge sharing in information systems development projects: Explicating the role of dependence and trust. International Journal of Project Management, 32(1), 153-165.
Rose, K. H. (2013). A Guide to the Project Management Body of Knowledge (PMBOK® Guide)—Fifth Edition. Project management journal, 44(3), e1-e1.
Schwalbe, K. (2015). Information technology project management. Cengage Learning.
Silverstone, R. (Ed.). (2017). Media, technology and everyday life in Europe: From information to communication. Routledge.
Snyder, C. S. (2014). A Guide to the Project Management Body of Knowledge: PMBOK (®) Guide. Project Management Institute.
Snyder, C. S., & Stackpole, C. S. (2013). A User’s Manual to the PMBOK Guide. John Wiley & Sons.
Stapel, K., & Schneider, K. (2014). Managing knowledge on communication and information flow in global software projects. Expert Systems, 31(3), 234-252.
Whittemore, S. (2015). Rhetorical memory: A study of technical communication and information management. University of Chicago Press.
Essay Writing Service Features
Our Experience
No matter how complex your assignment is, we can find the right professional for your specific task. Contact Essay is an essay writing company that hires only the smartest minds to help you with your projects. Our expertise allows us to provide students with high-quality academic writing, editing & proofreading services.Free Features
Free revision policy
$10Free bibliography & reference
$8Free title page
$8Free formatting
$8How Our Essay Writing Service Works
First, you will need to complete an order form. It's not difficult but, in case there is anything you find not to be clear, you may always call us so that we can guide you through it. On the order form, you will need to include some basic information concerning your order: subject, topic, number of pages, etc. We also encourage our clients to upload any relevant information or sources that will help.
Complete the order formOnce we have all the information and instructions that we need, we select the most suitable writer for your assignment. While everything seems to be clear, the writer, who has complete knowledge of the subject, may need clarification from you. It is at that point that you would receive a call or email from us.
Writer’s assignmentAs soon as the writer has finished, it will be delivered both to the website and to your email address so that you will not miss it. If your deadline is close at hand, we will place a call to you to make sure that you receive the paper on time.
Completing the order and download