The project presented in this assignment relates to the Workhouse Australia. The company – “WorkHouse Australia” – intends to open three high profile High street Workshop’s for sharing skills, repairing, up-cycling and re-productising consumer goods and technologies. The three site, all across the eastern sea board, are; Toowong Qld, Hawthorn Vic and Leichardt NSW. The base of the project will be at the Yard space in Leichardt.
Part A: Developing the Schedule
In developing the schedule, the following assumptions were taken into consideration;
Part A; Question 2
PartAQ1.mpp |
PartAQ2.mpp |
||
Total Duration |
Total Cost |
Total Duration |
Total Cost |
83 days |
$772,620 |
267 Days |
$772,620 |
The difference in the totals between PartAQ1.mpp and PartAQ2.mpparises from the resource levelling; the total cost does not change since levelling introduces slakes, and no new resources are added. The slake time for personnel are not billed and thus the cost of the project remains the same.
Part A Question 3 : Memo to Harold Steptoe
To: Harold Steptoe
From: The Project Manager,
Subject: Completion of the Planning Phase and Project Updates
The planning state of the WorkHouse Australia Project has been completed successfully. From the schedule developed, the expected completion date of the project is November 5th 2019. Thus, the total duration of the project will be 267 days. The project will take longer than earlier projections, owing to a number of factors. Like any other project the main trade-offs are time and resources. The extended project period was as a result of levelling out the available resources, since some tasks have to be carried out by the same people; requiring the tasks to be spread out.
The project phased two critical choices to make in deciding the levelling approach to use; Increase the budget or Spend more time on the project. Since the current priority was on working within the given budget, the levelling was done by spreading out the tasks. To shorten the duration of time for the project, I would recommend the addition of more resources to the project, especially the Craft Artisans. This will translate to an increase in the project budget. Currently, the estimated direct cost for each project resource is a follows;
Resource Name |
Cost |
Craft Artisan |
$165,680.00 |
Business Analysts |
$162,240.00 |
Knowledge Analysis |
$66,000.00 |
Software Engineers |
$220,880.00 |
Network Engineer |
$21,120.00 |
Mechanical Engineer |
$36,000.00 |
Workshop Assistant |
$88,800.00 |
Accommodation |
$7,500.00 |
Flight |
$4,400.00 |
Total Costs |
$772,620 |
The resources that need to be increased include;
PartAQ3.mpp |
PartAQ4.mpp |
||
Total Duration |
Total Cost |
Total Duration |
Total Cost |
267 Days |
$772,620 |
195 Days |
$772,620 |
The main tasks that were shorted, by allocating more Craft Artisans are ; painting, workbench assembly, power tool assembly, 3d printer setup and test, packing containers, workstation installation, system training, taxonomies development and KMS population. All these tasks involves the use of the craft artisans. From the testing done with “what if” analysis, no further changes can enhance the schedule.
The current project plan does not have any quality control tasks. The WBS only contain tasks that are critical to the completion of the project, but no activity was included to check on quality. Two quality issues can occur on this project;
Software quality: the software to be developed need to be tested for quality issues; particularly, bugs and usability issues. A quality control task would be critical for ensuring that the developed software is of high quality in terms of performance, usability and maintainability (Burke, 2013).
Workshop refurbishment quality: the refurbishment of the workshops requires to be evaluated, to ensure that they meet high quality and are usable.
To ensure such quality issues are taken into consideration, the following activities can be added to the project to enhance quality checks.
WBS |
Task Name |
Predecessor’s |
Duration |
Resource |
5.10 |
Software Quality Check |
5.9 |
1wk |
SE, BA |
2.4 |
Workshop Quality evaluation |
2.3 |
3days |
WA, Quality Control Officer |
Part A Question 6
Two more activities can be included in the project to ensure it is successful. The activities include;
Part B: Revising the Plan
Part B Question 2
Change |
Impact on project duration (longer, shorter or no impact) |
Explanation ( which resources and task clashes were the cause) |
Removal of KMS Module |
Shorter |
Knowledge Analyst was over allocated |
Addition 5.2.1 Sprint 1 |
Shorter |
Knowledge Analyst was over allocated |
Addition 5.2.2 Sprint 2 |
Longer |
Knowledge Analyst |
Addition 5.2.3 Sprint 3 |
Longer |
Knowledge Analyst |
Addition 5.2.4 Sprint 4 |
Longer |
Knowledge Analyst |
Part B Question 3 : Impact of each of these changes on the project cost
Change |
Impact on project Cost (greater ) |
Explanation ( which additional resources were the cause) |
Removal of KMS Module |
Lower |
Workshop Assistant, Craft Artisan |
Addition 5.2.1 Sprint 1 |
Greater |
Workshop Assistant, Craft Artisan |
Addition 5.2.2 Sprint 2 |
Greater |
Workshop Assistant, Craft Artisan |
Addition 5.2.3 Sprint 3 |
Greater |
Workshop Assistant, Craft Artisan |
Addition 5.2.4 Sprint 4 |
Greater |
Workshop Assistant, Craft Artisan |
Part B Question 4: How to manage and monitor progress of the 4 sprints.
To ensure successful completion of the project, a number of monitoring and management approaches will be used. This being an agile methodology, the monitoring of the sprints will be carried out through;
Conclusion
This assignment involved the scheduling of WorkHouse Australia project under different constraints. The main task of the project was to create a schedule using MS Project, level out resources and analyze the effect of various forms of levelling and resource adjustments. From the analysis, it is clear that a given project has to consider the two main trade-offs; time and resources. Increasing resources to a project translates to shortening of the project’s duration. On the other hand, having more time for the project means that the project can – in most case – be down with fewer resources, which may translate to cost savings.
Finally, the project has analyzed the effect of using an agile methodology in the implementation of the project. In this case, the introduction of sprints required addition of more resources, although it did not translate to shortening of the project duration. To monitor progress of an agile project, 3 methods were proposed, namely; sprint burndown, Release burndown and velocity.
References
Burke, R., 2013. Project management: planning and control techniques. New Jersey, USA.
Cervone, H.F., 2011. Understanding agile project management methods using Scrum. OCLC Systems & Services: International digital library perspectives, 27(1), pp.18-22.
James, M., 2009. Scrum methodology. Accessed: Apr, 8, p.2015.
Schwaber, K., 2004. Agile project management with Scrum. Microsoft press.
Turner, J.R., 2014. Handbook of project-based management(Vol. 92). New York, NY: McGraw-hill.
Essay Writing Service Features
Our Experience
No matter how complex your assignment is, we can find the right professional for your specific task. Contact Essay is an essay writing company that hires only the smartest minds to help you with your projects. Our expertise allows us to provide students with high-quality academic writing, editing & proofreading services.Free Features
Free revision policy
$10Free bibliography & reference
$8Free title page
$8Free formatting
$8How Our Essay Writing Service Works
First, you will need to complete an order form. It's not difficult but, in case there is anything you find not to be clear, you may always call us so that we can guide you through it. On the order form, you will need to include some basic information concerning your order: subject, topic, number of pages, etc. We also encourage our clients to upload any relevant information or sources that will help.
Complete the order formOnce we have all the information and instructions that we need, we select the most suitable writer for your assignment. While everything seems to be clear, the writer, who has complete knowledge of the subject, may need clarification from you. It is at that point that you would receive a call or email from us.
Writer’s assignmentAs soon as the writer has finished, it will be delivered both to the website and to your email address so that you will not miss it. If your deadline is close at hand, we will place a call to you to make sure that you receive the paper on time.
Completing the order and download