The project manager assumed that the budget that is needed for completing the project successfully is around $80,000.00. However it is identified that around $67,960.00 is required for completing all the project activities successfully within the specified time and budget and $17,000.00 has been kept for material resources and for other additional purposes.
The different types of assumptions that are made for budget preparation are as follows:
Requirement cost: The project manager analyzes the Australian market properly for preparing the budget for different types of material resources that are required for repairing the Australian storage facility. It is found that during preparing the budget for material resources they assumes that the cost of the materials will not vary much in the coming future in comparison to the cost that is estimated by them.
Low chances of scope creep: It is assumed by the project manager that scope creep within the project will not occur and for this they analyzes the requirement of the project properly before project planning so that the chances of scope creep will become low.
Budget needed for completing activities: The project manager estimated that the budget, which is needed for repairing Australian storage facility, is around $80,000.
Budget for risk minimization: The project manager estimated that $6,800 is required for minimizing the risks that are mainly associated with the project.
Task Name |
Duration |
Start |
Finish |
Repairing Australian Storage facility |
181 days |
Thu 21-09-17 |
Thu 31-05-18 |
Project initiation phase |
17 days |
Thu 21-09-17 |
Fri 13-10-17 |
Business case development |
2 days |
Thu 21-09-17 |
Fri 22-09-17 |
Analysis of feasibility |
3 days |
Mon 25-09-17 |
Wed 27-09-17 |
Project charter establishment |
4 days |
Thu 28-09-17 |
Tue 03-10-17 |
Team members appointment |
5 days |
Wed 04-10-17 |
Tue 10-10-17 |
Reviewing phase of the project |
3 days |
Wed 11-10-17 |
Fri 13-10-17 |
Milestone: Completion of initiation phase |
0 days |
Fri 13-10-17 |
Fri 13-10-17 |
Planning phase |
37 days |
Mon 16-10-17 |
Tue 05-12-17 |
Project plan creation |
6 days |
Mon 16-10-17 |
Mon 23-10-17 |
Resource plan creation |
7 days |
Tue 24-10-17 |
Wed 01-11-17 |
Financial plan creation |
8 days |
Thu 02-11-17 |
Mon 13-11-17 |
Testing quality |
9 days |
Tue 14-11-17 |
Fri 24-11-17 |
creation of acceptance plan |
7 days |
Mon 27-11-17 |
Tue 05-12-17 |
Milestone: Completion of planning phase |
0 days |
Tue 05-12-17 |
Tue 05-12-17 |
Execution phase |
121 days |
Wed 06-12-17 |
Wed 23-05-18 |
Agreement from participants |
10 days |
Wed 06-12-17 |
Tue 19-12-17 |
External issues settlement |
9 days |
Wed 20-12-17 |
Mon 01-01-18 |
Financing and creating agreement for the project |
8 days |
Tue 02-01-18 |
Thu 11-01-18 |
Preparatory work completion |
11 days |
Fri 12-01-18 |
Fri 26-01-18 |
Completion of strategies that stops leakage |
12 days |
Mon 29-01-18 |
Tue 13-02-18 |
Creating strategies that resolves issues |
14 days |
Wed 14-02-18 |
Mon 05-03-18 |
Activity adjustment |
12 days |
Tue 06-03-18 |
Wed 21-03-18 |
Whole repair completion |
9 days |
Thu 22-03-18 |
Tue 03-04-18 |
Adjustment of activities |
8 days |
Wed 04-04-18 |
Fri 13-04-18 |
Completion of repair risk |
7 days |
Mon 16-04-18 |
Tue 24-04-18 |
Analysis of work completed |
11 days |
Wed 25-04-18 |
Wed 09-05-18 |
Closure of issues |
10 days |
Thu 10-05-18 |
Wed 23-05-18 |
Milestone: Completion of execution phase |
0 days |
Wed 23-05-18 |
Wed 23-05-18 |
Closure phase |
6 days |
Thu 24-05-18 |
Thu 31-05-18 |
Construction of gas storage completion |
2 days |
Thu 24-05-18 |
Fri 25-05-18 |
Financial reporting |
2 days |
Mon 28-05-18 |
Tue 29-05-18 |
Analysis of the work |
1 day |
Wed 30-05-18 |
Wed 30-05-18 |
Milestone: Completion of Closure phase |
1 day |
Thu 31-05-18 |
Thu 31-05-18 |
Table 2: Gantt chart
(Source: Created by Author)
In this project, agile methodology is mainly used as it assists in breaking various project deliverables into number of manageable activities which are not available for re-ordering however they can be properly managed as well as tracked for completing the project (Larsonand Gray2013). It is identified that this methodology mainly focuses on time management and therefore proper as well as frequent reviews for improving the financial condition of the project in terms of profitability as well as productivity is generally done (Teller, Kock and Gemunden 2014). The agile methodology engages in continual improvement procedure by effectively encouraging all the project team members so that they can team up effectively ad assists in providing proper effort for managing different types of construction related task.
The tool and technique that is utilized in this project for organizing as well as designing the project effectively is Gantt chart. The advantages of using Gantt chart in the project are provided below:
Tracking: The project schedule which is generally created assists the project managers to keep proper track on the activities of the project (AhernLeavyand Byrne2014)
Cost: The cost that is required for completing each of the project activities can be reflected with the help of Gantt chart and thus it is found that the Gantt chart assists inn providing an overview about the cost that is needed for completing the activities of the project.
Idea about activities of the project: The Gantt chart provides idea about the initiation as well as execution of each of the activities that are generally completed for repairing the Australian Storage facility (Hornstein 2015).
Comparison of Agile methodology with Waterfall
Agile methodology |
Waterfall methodology |
It is identified that this methodology mainly focuses on time management and therefore proper as well as frequent reviews for improving the financial condition is necessary (Lock 2014) |
It is identified that the methodology of waterfall do not focus on time management and thus it prevents different types of compatibility issues which are mainly associated with the project. |
The agile methodology engages in continual improvement procedure by effectively encouraging all the project team members |
This methodology mainly helps in allowing the team to focus on other project aspects so that the developers can ensure appropriate quality of development in each of the stage (Hornstein 2015). |
Comparison of Gantt chart with WBS
Gantt chart |
Work breakdown structure |
The project schedule which is generally created assists the project managers to keep proper track on the activities of the project. |
It is identified that the structure of work breakdown structure helps in organizing various types of work that are associated with the team into number of manageable sections (Svejvig and Andersen 2015). |
The cost that is required for completing each of the project activities can be reflected with the help of Gantt hart and thus it is found that the Gantt chart assists in providing an overview about the cost that is needed for completing the activities of the project (Mir and Pinnington 2014). |
It is mainly found as a groundwork that assists developing proper budget plan for the project. |
The estimated resources include:
Financial resources: The estimated financial resources for repairing the Australian storage facility is around $80,000.00
Human resources: The various human resources that are mainly needed for repairing the Australian storage facility are provided below:
Resource Name |
Type |
Material Label |
Initials |
Group |
Max. Units |
Std. Rate |
Ovt. Rate |
Cost/Use |
Accrue At |
Base Calendar |
Project manager |
Work |
100% |
$50.00/hr |
$0.00/hr |
$0.00 |
Prorated |
Standard |
|||
Supervisor |
Work |
S |
100% |
$40.00/hr |
$0.00/hr |
$0.00 |
Prorated |
Standard |
||
Contractor |
Work |
C |
100% |
$40.00/hr |
$0.00/hr |
$0.00 |
Prorated |
Standard |
||
Business analyst |
Work |
B |
100% |
$30.00/hr |
$0.00/hr |
$0.00 |
Prorated |
Standard |
||
Project planner |
Work |
P |
100% |
$35.00/hr |
$0.00/hr |
$0.00 |
Prorated |
Standard |
||
Site planner |
Work |
S |
100% |
$30.00/hr |
$0.00/hr |
$0.00 |
Prorated |
Standard |
Material resources:The material resources which are needed for completing project include steel coatings, components for infrastructure improvement, mobile resources scaffolding, tank cranes as well as paint.
Analogous estimation techniques and tool is mainly used in order to estimate the project resources (Kerzner 2017). It is identified that this project is mainly used for estimating the budget that is needed for repairing the storage facility of Australia. It is found that the technique which is used not only assists in making reliable as well as proper estimation but also helps inreducing costs.
Ahern, T., Leavy, B. and Byrne, P.J., 2014. Complex project management as complex problem solving: A distributed knowledge management perspective. International Journal of Project Management, 32(8), pp.1371-1381.
Fleming, Q.W. and Koppelman, J.M., 2016, December.Earned value project management. Project Management Institute.
Hornstein, H.A., 2015. The integration of project management and organizational change management is now a necessity. International Journal of Project Management, 33(2), pp.291-298.
Hwang, B.G. and Ng, W.J., 2013. Project management knowledge and skills for green construction: Overcoming challenges. International Journal of Project Management, 31(2), pp.272-284.
Kerzner, H., 2013. Project management: a systems approach to planning, scheduling, and controlling. John Wiley & Sons.
Kerzner, H., 2017. Project management metrics, KPIs, and dashboards: a guide to measuring and monitoring project performance. John Wiley & Sons.
Larson, E.W. and Gray, C., 2013. Project Management: The Managerial Process with MS Project. McGraw-Hill.
Leach, L.P., 2014. Critical chain project management.Artech House.
Lock, M.D., 2014. The essentials of project management.Ashgate Publishing, Ltd..
Mir, F.A. and Pinnington, A.H., 2014.Exploring the value of project management: linking project management performance and project success. International journal of project management, 32(2), pp.202-217.
Nicholas, J.M. and Steyn, H., 2017. Project management for engineering, business and technology.Taylor & Francis.
Svejvig, P. and Andersen, P., 2015. Rethinking project management: A structured literature review with a critical look at the brave new world. International Journal of Project Management, 33(2), pp.278-290.
Teller, J., Kock, A. and Gemünden, H.G., 2014. Risk management in project portfolios is more than managing project risks: A contingency perspective on risk management. Project Management Journal, 45(4), pp.67-80.
Essay Writing Service Features
Our Experience
No matter how complex your assignment is, we can find the right professional for your specific task. Contact Essay is an essay writing company that hires only the smartest minds to help you with your projects. Our expertise allows us to provide students with high-quality academic writing, editing & proofreading services.Free Features
Free revision policy
$10Free bibliography & reference
$8Free title page
$8Free formatting
$8How Our Essay Writing Service Works
First, you will need to complete an order form. It's not difficult but, in case there is anything you find not to be clear, you may always call us so that we can guide you through it. On the order form, you will need to include some basic information concerning your order: subject, topic, number of pages, etc. We also encourage our clients to upload any relevant information or sources that will help.
Complete the order formOnce we have all the information and instructions that we need, we select the most suitable writer for your assignment. While everything seems to be clear, the writer, who has complete knowledge of the subject, may need clarification from you. It is at that point that you would receive a call or email from us.
Writer’s assignmentAs soon as the writer has finished, it will be delivered both to the website and to your email address so that you will not miss it. If your deadline is close at hand, we will place a call to you to make sure that you receive the paper on time.
Completing the order and download