This paper discussed about the show Riverina Agricultural and Lifestyle that mainly arranged to display different types of agricultural events, different lifestyle products. It is mainly identified that different manual techniques are get utilized by organization to manage the large number details that is not in proper manner so the Globex business that mainly aligned with the show which develop the roistering system.
In this paper, information about budget, project schedule, management plan and different resources are discussed. It is also identified that this paper elaborates about different challenges and risks identified in the project to develop the roster system of RALS.
Customer: It mainly identified about a developed system that is helpful to mitigate all related queries that are mainly raised by people.
Strategy: It is found that the system is more beneficial to track various kinds of volunteer’s details to track them.
Social: the developed system is mainly found to more advantageous for doing the communication with different clients
Operational: the proper utilization of roistering system mainly helps to store significant information of volunteers in the system that leads to make the different organizational operations easier.
Financial: the roistering system that mainly developed by Globex become helpful to provide large quantity of return money that is mainly invested by business.
In the context of RALS Roistering system project, the two types of project value are listed below:
Better: this RALS venture checked the advancement of different framework to expand the work proficiency with the help of data administration.
Cheaper: RALS task mainly helps to deal with various data that mainly diminish all types of general costs related to general cost of data framework administration.
Rank |
Impact |
Metrics |
Timeframe |
1 |
Financial |
Revenue and Money Profit era |
6 months |
2 |
Customer |
All clients returning to association based on different administrative work. |
2 months |
3 |
Operational |
Reduction of consumption of time to finish different hierarchical techniques. |
2 months |
4 |
Strategy |
All volunteers need to have the capacity for getting associated with all clients |
1 month |
Define the scope: The RALS ticketing system advancement techniques helps to build up the project team and different materials to develop all types of project operations.
Requirements: All project requirements are shown in the table format:
Resource Name |
Type |
Budgeter |
Work |
Computer Devices |
Material |
Documenter |
Work |
IT Engineer |
Work |
Network Components |
Material |
Planner |
Work |
Project Manager |
Work |
Storage |
Material |
System Analyst |
Work |
Tester |
Work |
Wireless routers |
Material |
The in-scope of project includes:
The out-scope of project includes:
Deliverables: The deliverables of this project are listed below:
The acceptance criteria of this system discuss about the meeting of different requirements along with the demands and needs of clients. Apart from that, it also assists to minimize about response time to have proper solution of different queries.
Material resources: Different types of technical requirements to complete the project according to pre-determined results discuss about secondary storage, operating system, display adapter etc.
Human resource: The people who are needed to complete the project within the time include system developer, project manager, business analyst, system analyst, project sponsor, investment manager etc.
Resource Name |
Type |
Material Label |
Initials |
Group |
Max. Units |
Std. Rate |
Ovt. Rate |
Cost/Use |
Accrue At |
Base Calendar |
Developer |
Work |
D |
100% |
$80.00/hr |
$0.00/hr |
$0.00 |
Prorated |
Standard |
||
System analyst |
Work |
S |
100% |
$90.00/hr |
$0.00/hr |
$0.00 |
Prorated |
Standard |
||
Accountant |
Work |
A |
100% |
$85.00/hr |
$0.00/hr |
$0.00 |
Prorated |
Standard |
||
Project manager |
Work |
P |
100% |
$90.00/hr |
$0.00/hr |
$0.00 |
Prorated |
Standard |
||
Tester |
Work |
T |
100% |
$70.00/hr |
$0.00/hr |
$0.00 |
Prorated |
Standard |
||
Executive sponsor |
Work |
E |
100% |
$75.00/hr |
$0.00/hr |
$0.00 |
Prorated |
Standard |
||
Requirement analyst |
Work |
R |
100% |
$65.00/hr |
$0.00/hr |
$0.00 |
Prorated |
Standard |
||
Risk manager |
Work |
R |
100% |
$70.00/hr |
$0.00/hr |
$0.00 |
Prorated |
Standard |
Task Name |
Duration |
Start |
Finish |
Resource Names |
RAILS Rostering System |
244 days |
Mon 9/25/17 |
Thu 8/30/18 |
|
Specification determination |
23 days |
Mon 9/25/17 |
Wed 10/25/17 |
|
Undertaking feasibility study for the different manual system |
6 days |
Mon 9/25/17 |
Mon 10/2/17 |
Project manager, Requirement analyst |
Business needs identification |
6 days |
Tue 10/3/17 |
Tue 10/10/17 |
Requirement analyst |
Creation of SRS document |
7 days |
Wed 10/11/17 |
Thu 10/19/17 |
Project manager, Requirement analyst |
Meeting arrangement |
4 days |
Fri 10/20/17 |
Wed 10/25/17 |
Project manager |
Milestone: completion of specification determination |
0 days |
Wed 10/25/17 |
Wed 10/25/17 |
|
Development team selection |
38 days |
Thu 10/26/17 |
Mon 12/18/17 |
|
Development of vendor selection |
11 days |
Thu 10/26/17 |
Thu 11/9/17 |
Accountant, Project manager |
Checking development history of the vendors |
12 days |
Fri 11/10/17 |
Mon 11/27/17 |
Executive sponsor, Project manager |
Development task scheduling |
7 days |
Tue 11/28/17 |
Wed 12/6/17 |
Developer, Project manager |
Budget planning for development |
8 days |
Thu 12/7/17 |
Mon 12/18/17 |
Accountant, Executive sponsor, Project manager |
Milestone: completion of team selection |
0 days |
Mon 12/18/17 |
Mon 12/18/17 |
|
Designing phase |
69 days |
Tue 12/19/17 |
Fri 3/23/18 |
|
Module improvement for volunteer management |
21 days |
Tue 12/19/17 |
Tue 1/16/18 |
Developer, Project manager |
First prototype development |
17 days |
Wed 1/17/18 |
Thu 2/8/18 |
Developer |
Improvement within new system installation |
15 days |
Fri 2/9/18 |
Thu 3/1/18 |
Developer, Project manager |
Determining the needs of the system |
16 days |
Fri 3/2/18 |
Fri 3/23/18 |
Project manager, System analyst |
Milestone: Completion of design phase |
0 days |
Fri 3/23/18 |
Fri 3/23/18 |
|
System implementation system |
33 days |
Mon 3/26/18 |
Wed 5/9/18 |
|
Different business objectives development |
13 days |
Mon 3/26/18 |
Wed 4/11/18 |
Developer, Requirement analyst |
Amendments within the part of the system that is implemented |
12 days |
Thu 4/12/18 |
Fri 4/27/18 |
Developer, Project manager |
Using compatible software and hardware |
8 days |
Mon 4/30/18 |
Wed 5/9/18 |
Accountant, Project manager, System analyst |
Milestone: Completion of system implementation system |
0 days |
Wed 5/9/18 |
Wed 5/9/18 |
|
Testing phase |
26 days |
Thu 5/10/18 |
Thu 6/14/18 |
|
Identifying test cases as well as test plan |
7 days |
Thu 5/10/18 |
Fri 5/18/18 |
Tester |
Testing the developed system |
8 days |
Mon 5/21/18 |
Wed 5/30/18 |
Project manager, Tester |
Information system analysis from the data |
9 days |
Thu 5/31/18 |
Tue 6/12/18 |
Executive sponsor, Project manager |
Results documentation |
2 days |
Wed 6/13/18 |
Thu 6/14/18 |
Project manager |
Milestone: acceptance of the test results by client |
0 days |
Thu 6/14/18 |
Thu 6/14/18 |
|
Risk management phase |
30 days |
Fri 6/15/18 |
Thu 7/26/18 |
|
Assessment as well as risk identification |
11 days |
Fri 6/15/18 |
Fri 6/29/18 |
Project manager, Risk manager |
Presenting risks impact |
7 days |
Mon 7/2/18 |
Tue 7/10/18 |
Risk manager |
Risks mitigation |
8 days |
Wed 7/11/18 |
Fri 7/20/18 |
Project manager, System analyst |
Impact of the risk registering |
4 days |
Mon 7/23/18 |
Thu 7/26/18 |
Project manager, Risk manager |
Milestone: Acceptance of the risk document by the client |
0 days |
Thu 7/26/18 |
Thu 7/26/18 |
|
Closure of the project |
25 days |
Fri 7/27/18 |
Thu 8/30/18 |
|
Evaluating roistering system functions |
13 days |
Fri 7/27/18 |
Tue 8/14/18 |
Executive sponsor, Project manager |
Final developed product roll out |
12 days |
Wed 8/15/18 |
Thu 8/30/18 |
Project manager |
Milestone: Completion of closure phase of the project |
0 days |
Thu 8/30/18 |
Thu 8/30/18 |
WBS |
Task Name |
Expected Date |
0 |
RALS Roistering System |
Fri 9/23/16 |
1 |
Achievement of specific determination |
Wed 10/25/17 |
2 |
Proper selection of team based on project requirements |
Mon 12/18/17 |
3 |
Completion of design phase |
Fri 3/23/18 |
4 |
Closure of system implementation system |
Wed 5/9/18 |
5 |
Acceptance of t risk document |
Thu 7/26/18 |
6 |
Completion of closure phase of the project |
Thu 8/30/18 |
Some of project assumptions that are made in this project are mainly listed below:
Budget: the project manager mainly estimates the exact budget that required executing different project activities. Initially, it is set that the estimated budget is $400,000, where as $298.040 will be required to complete all activities and $200, 00 will be required for all other materials including different additional resources.
Time: the project manager also predicted the entire required time to complete all project activities to develop the roster system. The time estimated by the project manager is near about 244 days.
Resources: the project team also assumes about different project resources that is mainly needed to develop the RALS system. Hence, it is also deduced that proper assumptions of project resources mainly helps to have proper summary that mainly needed to calculate the budget.
No. |
Rank |
Risk |
Description |
Category |
Root Cause |
Triggers |
Potential Responses |
Risk Owner |
Probability |
Impact |
Status |
R44 |
1 |
System failure |
If system is not get installed in proper manner inside the business that will increase the risks number along with challenges |
Technical risk |
The lack-age of proper knowledge of system developer, the installation techniques are not maintained properly. |
The particular system is not installed properly by taking require time. |
This particular system is require to be installed in proper manner. |
Project manager |
Medium |
High |
Set up in 1 week |
R19 |
2 |
inappropriate budget estimation |
The estimation of budget by project manager is not occurring in accurate manner. |
Financial risk |
They also assume the create budget will not be accurate due to in experienced project manager to do analysis of market share. |
Different budgetary issues that mainly occurs because of in appropriate market analysis. |
Suitable budget estimation are require to be done after the market analysis in effective manner. |
Financial manager |
Medium |
High |
Set up in 3 weeks |
R8 |
3 |
Inappropriate scheduling |
The project manger does not gather better understanding about the project goals and objectives due to which the created schedules will not be exact. |
Project risk |
All types of scheduling related risks occur because of unacceptable amount of information of client’s requirement. |
In appropriate understanding about project created differed types of scheduling risks. |
The project manager also needed to analyse and also determine all project requirements having the proper understanding. |
Project manager |
Medium |
High |
Set up in 2 week |
R32 |
4 |
Improper management |
Inaccurate management of differed project activities created various challenges. |
Project risk |
It occurs because of lack age of proper experience of related manager. |
Improper knowledge of project manager created weak project management. |
The project manager also manages the project by maintaining exact strategies including exact methodologies. |
Project managers |
Medium |
High |
Set up in 1 week |
R28 |
5 |
Resources |
Unacceptable use of project resources |
Resource risk |
Improper uses of differed resources because of proper experience. |
Correct techniques used for resources management are not mainly used. |
The organization must not gathers experience of project managers |
Project manager |
Medium |
Medium |
Set up in 1 week |
Probability of occurrence |
Impact of occurrence |
||||
Very low |
Low |
Medium |
High |
Very high |
|
Very low |
|||||
Low |
|||||
Medium |
Resource risk |
Technical risk |
|||
High |
Schedule risk |
Technical risk |
|||
Very high |
It is mainly recognized that numbers of key elements that are considered become more helpful; to deliver various types of quality based services to all customers including service culture, employee engagement, customer experience etc. Moreover, it is also identified that different types of elements are used to form service culture and different elements are vision, mission, leadership and also various types of organizational norms.
The projected system is identified to be an effective engaging more people with the organization. It is identified that service quality is mainly depends of strategic plan that mainly get utilized by the organization for the proper system installation and maintaining various objectives and goals of the organization.
Project Name:RALS Rostering System |
Project manager Name: (<<Name of the Student>>) |
||||
Sl.No |
Quality related issues that are possible |
Mitigation time |
Method for mitigation |
Owner |
Status |
1 |
Various documents are reports are mainly prepared by completing all phases is not having appropriate quality and adequate information. |
2 moths |
Inspection |
Project manager |
Open |
2 |
Both the software and hardware materials are mainly get utilized to develop the project that is found to be of low quality. |
3 months |
Inspection |
Project manager |
Open |
3 |
The organizational staffs are not very much skilled that results the works done by them have various quality related issues. |
2 months |
Inspection |
project manger |
Open |
The verification activities that help to elaborate all the proposed system meet different conditions and regulation of system and organization. It is mainly identified that all criteria are needed to get fulfilled by the system installed by Globex
The validation testing is needed to be done to elaborate the proposed system quality in this project development phase. The implemented testing method is utilized to meet different needs to businesses as well as clients.
Article 1: In this paper of roles of monitoring and evaluation in projects”, Boulmetis and Dutwin (2014) discussed that various project numbers that are associated with third work countries fails because of lack understanding of needs evaluation and proper monitoring. The researchers also highlighted the implication of different project monitoring techniques and proper evaluation of successful completion of project. Moreover, in this paper it also discussed about various common constraints that helps to overcome all related problems. Apart from that, evaluation is a technique that mainly helps to determine the sustainability, relevancy and the impacts of activities based on project performance.
Article 2: This paper mainly discussed about the project management roles to achieve success. Heagney (2016) discussed that roles of different types of project management activities to implement the project is mainly established in different areas that also includes cost controlling, planning, quality, time etc. The researchers mainly identified to determine the overlapping that exists between the project management techniques and the project definition. The researchers also identified that people that involves within the project and different project management techniques based on the objectives, expectations as well as their influences. On the other hand, it also helps to demonstrate the appreciation of the distinction between project management and project to bring the advanced possibilities of project success.
Article 3: In this paper, it mainly reflects about the risk identification techniques by project manager (Anca, Cezar & Adrian, 2015). However, it is mainly identified that project risks is mainly defined as an uncertain events that causes either negative or positive impact based on project objectives. Different risks conditions mainly include various characteristics of project that mainly helps to contribute in the project, lack age of integrated systems and dependencies of different external participants. Apart from that, it is also identified that the risk identification is a basic step to manage different project risks.
Task Name |
Stakeholder |
Signature |
Doing the feasibility study for different manual system |
Project manager, Requirement analyst |
|
Identification of Business Needs |
Requirement analyst |
|
Advancement of vendor selection |
Accountant, Project manager |
|
Checking development history of the vendors |
Executive sponsor, Project manager |
|
Improvement of the new system installation |
Developer, Project manager |
|
Determining the needs of the system |
Project manager, System analyst |
|
Using compatible software and hardware |
Accountant, Project manager, System analyst |
|
Identifying test cases as well as test plan |
Tester |
|
Testing the developed system |
Project manager, Tester |
|
Assessment as well as risk identification |
Project manager, Risk manager |
|
Risks mitigation |
Project manager, System analyst |
|
Evaluating roistering system functions |
Executive sponsor, Project manager |
Anca, U., Cezar, B., & Adrian, U. (2015, November). Risk Identification in Project Management. In International Conference on Economic Sciences and Business Administration (Vol. 2, No. 1, pp. 259-266). Spiru Haret University.
Boulmetis, J., & Dutwin, P. (2014). The ABCs of evaluation: Timeless techniques for program and project managers (Vol. 56). John Wiley & Sons.
Coronel, C., & Morris, S. (2016). Database systems: design, implementation, & management. Cengage Learning.
Heagney, J. (2016). Fundamentals of Project Managementw. AMACOM Div American Mgmt Assn.
Kami, N. (2015). U.S. Patent No. 9,116,916. Washington, DC: U.S. Patent and Trademark Office.
Kendrick, T. (2015). Identifying and managing project risk: essential tools for failure-proofing your project. AMACOM Div American Mgmt Assn.
Pritchard, C. L., & PMP, P. R. (2014). Risk management: concepts and guidance. CRC Press.
Schwalbe, K. (2015). Information technology project management.Cengage Learning.
Tornabene, C., Hussain, M. M., Crowe, T., Cohen, N., & Panzer, J. (2012).U.S. Patent No. 8,103,729. Washington, DC: U.S. Patent and Trademark Office.
Tornabene, C., Hussain, M. M., Crowe, T., Cohen, N., & Panzer, J. (2012).U.S. Patent No. 8,103,729. Washington, DC: U.S. Patent and Trademark Office.
Essay Writing Service Features
Our Experience
No matter how complex your assignment is, we can find the right professional for your specific task. Contact Essay is an essay writing company that hires only the smartest minds to help you with your projects. Our expertise allows us to provide students with high-quality academic writing, editing & proofreading services.Free Features
Free revision policy
$10Free bibliography & reference
$8Free title page
$8Free formatting
$8How Our Essay Writing Service Works
First, you will need to complete an order form. It's not difficult but, in case there is anything you find not to be clear, you may always call us so that we can guide you through it. On the order form, you will need to include some basic information concerning your order: subject, topic, number of pages, etc. We also encourage our clients to upload any relevant information or sources that will help.
Complete the order formOnce we have all the information and instructions that we need, we select the most suitable writer for your assignment. While everything seems to be clear, the writer, who has complete knowledge of the subject, may need clarification from you. It is at that point that you would receive a call or email from us.
Writer’s assignmentAs soon as the writer has finished, it will be delivered both to the website and to your email address so that you will not miss it. If your deadline is close at hand, we will place a call to you to make sure that you receive the paper on time.
Completing the order and download