MOV can be described as the limit of the standard that should be fulfilled by the strategies proposed by the manager in manner to be approved by the executives of the project. It is a level of the project delivery that should must be accomplished by the project charter or planning strategies. Following are some of the vital aspects that should be accomplished by the documents and constraints of the project related to the development of the online stud farm management system:
Strategy: proper and effective strategy is necessary for the delivery of the project considering the modifications on the existing system of the Globex and allowing better and efficient delivery and output. The strategy should always consider the delivery of the activities and actions within the milestone.
Customer: the needs and requirements of the customers are increasing with higher rate and it is the desire of the customers to avail better and fast services from the organization side. The standard of the services those are currently being provided to the consumers should be enhanced and fast services should be introduced to the consumers.
Financial: the desired project should be a cost effective solution for the identified problems, as the transformation will be accomplished through the transformation of the existing paper work into an online system that can be helpful in allowing the automation and speeding the existing services.
Operational: the system should be capable of accomplishing the existing activities and more and allowing the employees and staffs for the accomplishment of the activities. The operational activities related to the organization must not be hampered although it should be enhanced through the execution of the project in successful and efficient manner.
Social: the project should be social friendly emphasizing on not affecting the overall functionalities and objectives of the project. The economy must be agreed on the establishment, which can be accomplished through adhering the sustainability management by the organization.
Following are the two vital objectives and aspects that must be fulfilled by the project considering the standard and quality of the project considering overall activities included in the project:
Quality is a crucial factor for the deployment of the successful project as the online management system should not only be capable of delivering the necessary activities or objectives rather it should be capable of delivering the activities in better and enhanced way. The proposed management system brings out the maximum high quality of the output considering the fulfillment of the needs and requirements of the consumers.
The clients of any organization will be happier and much satisfied, if the proposed solution would be capable of enhancing the limitations of the services delivery. The proposed system will not allow the enhancement in the existing system of the organization rather it will be empowering the functioning and operations of the organization. it will also allow the availability of the data and information 24*7 and eliminate the existing problems of redundancy, saving, and many more.
WBS |
Task Name |
Duration |
Start |
Finish |
1 |
Communication with the stakeholders about MOV |
21 days |
Mon 5/14/18 |
Mon 6/11/18 |
1.1 |
Identification of the areas needing modifications |
5 days |
Mon 5/14/18 |
Fri 5/18/18 |
1.2 |
Ranking the impacts |
4 days |
Mon 5/21/18 |
Thu 5/24/18 |
1.3 |
Identification of the values |
3 days |
Fri 5/25/18 |
Tue 5/29/18 |
1.4 |
Development of the metric |
4 days |
Wed 5/30/18 |
Mon 6/4/18 |
1.5 |
Informing the stakeholders |
3 days |
Tue 6/5/18 |
Thu 6/7/18 |
1.6 |
confirmation from the stakeholders |
2 days |
Fri 6/8/18 |
Mon 6/11/18 |
Globex will be offered with a solution for the online management system that can enhance the quality and pace of the operational activities being accomplished within the organization through eliminating the extra efforts and allowing automation. This management system will be able to collect, store and share the data and information related to the operational activities those were previously done by pen and paper work. The proposed system will be free from human errors, cost effective, no maintenance charges, eliminate the existing problems and many more. In addition to this, the proposed system will allow the availability of the backup, and data and information related to the current ongoing activities and previously accomplished operations. Thus, it will also be helpful in considering the growth and development of the project and allowing the managers to think of the strategies those could be implemented for the enhancement in the quality of the project.
Following are the scopes for the project that should be covered by the execution of this proposed project:
Resource Name |
Type |
Max. Units |
Std. Rate |
Ovt. Rate |
Cost/Use |
Accrue At |
Base Calendar |
Project Manager |
People |
100% |
$10.00/hr |
$0.00/hr |
$0.00 |
Prorated |
Standard |
Marketing and Commerce Manager |
People |
100% |
$5.00/hr |
$0.00/hr |
$0.00 |
Prorated |
Standard |
Technical Expert |
Technology |
100% |
$5.00/hr |
$0.00/hr |
$0.00 |
Prorated |
Standard |
System Trainer |
People |
100% |
$5.00/hr |
$0.00/hr |
$0.00 |
Prorated |
Standard |
Technical Integration Specialist |
Technology |
100% |
$10.00/hr |
$0.00/hr |
$0.00 |
Prorated |
Standard |
Developer |
Technology |
100% |
$10.00/hr |
$0.00/hr |
$0.00 |
Prorated |
Standard |
IT Manager |
People |
100% |
$5.00/hr |
$0.00/hr |
$0.00 |
Prorated |
Standard |
People |
100% |
$5.00/hr |
$0.00/hr |
$0.00 |
Prorated |
Standard |
|
Project Supervisor |
Other |
100% |
$10.00/hr |
$0.00/hr |
$0.00 |
Prorated |
Standard |
Hardware |
Technology |
$2,000.00 |
$0.00 |
Prorated |
|||
Development Software |
Facility |
$1,000.00 |
$0.00 |
Prorated |
0 |
Online Stud Farm Management System |
1 |
Phase 1: project Planning |
1.1 |
Arrangement of Meeting between the Virtucon and Globex for the communication purpose |
1.2 |
Preparing the Proposal of the Project |
1.3 |
Identifying the feasibility of the proposed solution |
1.4 |
proposing of the draft of the virtucon |
1.5 |
Forwarding for the Approval |
1.6 |
Paper Sign-off by the involved stakeholders in the virtucon and globex |
1.7 |
Development of the Project Charter |
1.8 |
forwarding for the Approval |
1.9 |
Phase 1 completed |
2 |
Phase 2: Project Initiation |
2.1 |
Procurement plan for the project funds |
2.2 |
identifying the list of requirements necessary for the project |
2.3 |
Proposing the System Design Proposal |
2.4 |
Estimating the roles and responsibilities of the stakeholders in the project |
2.5 |
Phase 2 completed |
3 |
Phase 3: Project Execution |
3.1 |
Developing the Procurement of needed Software |
3.2 |
Developing the Procurement of needed Hardware |
3.3 |
Integrating the Hardware within existing System |
3.4 |
Initiating the Proposed System Development |
3.5 |
Developing the Online Management System for the farm |
3.6 |
implementing the Features |
3.7 |
Integrating the UI |
3.8 |
Evaluating the system functioning |
3.9 |
documenting the completion of this phase |
3.1 |
Phase 3 completed |
4 |
Phase 4: Training |
4.1 |
providing Training of Globex Employees |
4.2 |
Developing the strategies of Marketing Plan |
4.3 |
Providing System Tutorial Brochure |
4.4 |
Phase 4 completed |
5 |
phase 5: Project Closing |
5.1 |
Post Project Review after completion |
5.2 |
preparing Documentation of Entire Project |
5.3 |
Sign Off from the stakeholders |
5.4 |
Project Manager and other executive Sign Off |
5.5 |
Phase 5 completed |
WBS |
Task Name |
Duration |
Start |
Finish |
Predecessors |
0 |
Online Stud Farm Management System |
81 days |
Mon 12/18/17 |
Mon 4/9/18 |
|
1 |
Phase 1: project Planning |
35 days |
Mon 12/18/17 |
Fri 2/2/18 |
|
1.9 |
Phase 1 completed |
0 days |
Fri 2/2/18 |
Fri 2/2/18 |
9 |
2 |
Phase 2: Project Initiation |
10 days |
Mon 2/5/18 |
Fri 2/16/18 |
|
2.5 |
Phase 2 completed |
0 days |
Fri 2/16/18 |
Fri 2/16/18 |
15 |
3 |
Phase 3: Project Execution |
19 days |
Mon 2/19/18 |
Thu 3/15/18 |
|
3.10 |
Phase 3 completed |
0 days |
Thu 3/15/18 |
Thu 3/15/18 |
26 |
4 |
Phase 4: Training |
6 days |
Fri 3/16/18 |
Fri 3/23/18 |
|
4.4 |
Phase 4 completed |
0 days |
Fri 3/23/18 |
Fri 3/23/18 |
31 |
5 |
phase 5: Project Closing |
11 days |
Mon 3/26/18 |
Mon 4/9/18 |
|
5.5 |
Phase 5 completed |
0 days |
Mon 4/9/18 |
Mon 4/9/18 |
37 |
WBS |
Task Name |
Duration |
Start |
Finish |
Predecessors |
0 |
Online Stud Farm Management System |
81 days |
Mon 12/18/17 |
Mon 4/9/18 |
|
1 |
Phase 1: project Planning |
35 days |
Mon 12/18/17 |
Fri 2/2/18 |
|
1.1 |
Arrangement of Meeting between the Virtucon and Globex for the communication purpose |
15 days |
Mon 12/18/17 |
Fri 1/5/18 |
|
1.2 |
Preparing the Proposal of the Project |
5 days |
Mon 1/8/18 |
Fri 1/12/18 |
2 |
1.3 |
Identifying the feasibility of the proposed solution |
3 days |
Mon 1/15/18 |
Wed 1/17/18 |
3 |
1.4 |
proposing of the draft of the Virtucon |
3 days |
Thu 1/18/18 |
Mon 1/22/18 |
4 |
1.5 |
Forwarding for the Approval |
2 days |
Tue 1/23/18 |
Wed 1/24/18 |
5 |
1.6 |
Paper Sign-off by the involved stakeholders in the Virtucon and Globex |
3 days |
Thu 1/25/18 |
Mon 1/29/18 |
6 |
1.7 |
Development of the Project Charter |
2 days |
Tue 1/30/18 |
Wed 1/31/18 |
7 |
1.8 |
forwarding for the Approval |
2 days |
Thu 2/1/18 |
Fri 2/2/18 |
8 |
1.9 |
Phase 1 completed |
0 days |
Fri 2/2/18 |
Fri 2/2/18 |
9 |
2 |
Phase 2: Project Initiation |
10 days |
Mon 2/5/18 |
Fri 2/16/18 |
|
2.1 |
Procurement plan for the project funds |
4 days |
Mon 2/5/18 |
Thu 2/8/18 |
10 |
2.2 |
identifying the list of requirements necessary for the project |
3 days |
Fri 2/9/18 |
Tue 2/13/18 |
12 |
2.3 |
Proposing the System Design Proposal |
2 days |
Wed 2/14/18 |
Thu 2/15/18 |
13 |
2.4 |
Estimating the roles and responsibilities of the stakeholders in the project |
1 day |
Fri 2/16/18 |
Fri 2/16/18 |
14 |
2.5 |
Phase 2 completed |
0 days |
Fri 2/16/18 |
Fri 2/16/18 |
15 |
3 |
Phase 3: Project Execution |
19 days |
Mon 2/19/18 |
Thu 3/15/18 |
|
3.1 |
Developing the Procurement of needed Software |
1 day |
Wed 2/21/18 |
Wed 2/21/18 |
16 |
3.2 |
Developing the Procurement of needed Hardware |
2 days |
Mon 2/19/18 |
Tue 2/20/18 |
15 |
3.3 |
Integrating the Hardware within existing System |
2 days |
Thu 3/8/18 |
Fri 3/9/18 |
18 |
3.4 |
Initiating the Proposed System Development |
1 day |
Wed 2/21/18 |
Wed 2/21/18 |
19 |
3.5 |
Developing the Online Management System for the farm |
5 days |
Thu 2/22/18 |
Wed 2/28/18 |
19,21 |
3.6 |
implementing the Features |
5 days |
Thu 3/1/18 |
Wed 3/7/18 |
22 |
3.7 |
Integrating the UI |
2 days |
Thu 3/8/18 |
Fri 3/9/18 |
23 |
3.8 |
Evaluating the system functioning |
3 days |
Mon 3/12/18 |
Wed 3/14/18 |
24 |
3.9 |
documentation of the completion of this phase |
1 day |
Thu 3/15/18 |
Thu 3/15/18 |
25 |
3.10 |
Phase 3 completed |
0 days |
Thu 3/15/18 |
Thu 3/15/18 |
26 |
4 |
Phase 4: Training |
6 days |
Fri 3/16/18 |
Fri 3/23/18 |
|
4.1 |
providing Training of Globex Employees |
2 days |
Fri 3/16/18 |
Mon 3/19/18 |
27 |
4.2 |
Developing the strategies of Marketing Plan |
2 days |
Tue 3/20/18 |
Wed 3/21/18 |
29 |
4.3 |
Providing System Tutorial Brochure |
2 days |
Thu 3/22/18 |
Fri 3/23/18 |
30 |
4.4 |
Phase 4 completed |
0 days |
Fri 3/23/18 |
Fri 3/23/18 |
31 |
5 |
phase 5: Project Closing |
11 days |
Mon 3/26/18 |
Mon 4/9/18 |
|
5.1 |
Post Project Review after completion |
4 days |
Mon 3/26/18 |
Thu 3/29/18 |
32 |
5.2 |
preparing Documentation of Entire Project |
3 days |
Fri 3/30/18 |
Tue 4/3/18 |
34 |
5.3 |
Sign Off from the stakeholders |
2 days |
Wed 4/4/18 |
Thu 4/5/18 |
35 |
5.4 |
Project Manager and other executive Sign Off |
2 days |
Fri 4/6/18 |
Mon 4/9/18 |
36 |
5.5 |
Phase 5 completed |
0 days |
Mon 4/9/18 |
Mon 4/9/18 |
37 |
SL. No. |
Task Name |
Duration |
Resource Names |
0 |
Online Stud Farm Management System |
81 days |
|
1 |
Phase 1: project Planning |
35 days |
|
1.1 |
Arrangement of Meeting between the Virtucon and Globex for the communication purpose |
15 days |
Project Manager |
1.2 |
Preparing the Proposal of the Project |
5 days |
Project Manager, Technical Expert |
1.3 |
Identifying the feasibility of the proposed solution |
3 days |
IT Manager, Technical Expert |
1.4 |
proposing of the draft of the Virtucon |
3 days |
IT Manager |
1.5 |
Forwarding for the Approval |
2 days |
Project Manager, IT Manager |
1.6 |
Paper Sign-off by the involved stakeholders in the Virtucon and Globex |
3 days |
Project Supervisor, Project Manager |
1.7 |
Development of the Project Charter |
2 days |
Technical Expert |
1.8 |
forwarding for the Approval |
2 days |
Project Manager |
1.9 |
Phase 1 completed |
0 days |
|
2 |
Phase 2: Project Initiation |
10 days |
|
2.1 |
Procurement plan for the project funds |
4 days |
Project Supervisor |
2.2 |
identifying the list of requirements necessary for the project |
3 days |
Marketing and Commerce Manager |
2.3 |
Proposing the System Design Proposal |
2 days |
Marketing and Commerce Manager |
2.4 |
Estimating the roles and responsibilities of the stakeholders in the project |
1 day |
Technical Expert |
2.5 |
Phase 2 completed |
0 days |
|
3 |
Phase 3: Project Execution |
19 days |
|
3.1 |
Developing the Procurement of needed Software |
1 day |
IT Manager |
3.2 |
Developing the Procurement of needed Hardware |
2 days |
IT Manager |
3.3 |
Integrating the Hardware within existing System |
2 days |
Technical Integration Specialist |
3.4 |
Initiating the Proposed System Development |
1 day |
Technical Integration Specialist |
3.5 |
Developing the Online Management System for the farm |
5 days |
Technical Integration Specialist |
3.6 |
implementing the Features |
5 days |
Data Management Officer |
3.7 |
Integrating the UI |
2 days |
Developer |
3.8 |
Evaluating the system functioning |
3 days |
Developer |
3.9 |
Documenting the completion of this phase |
1 day |
Developer, Technical Integration Specialist, IT Manager |
3.10 |
Phase 3 completed |
0 days |
|
4 |
Phase 4: Training |
6 days |
|
4.1 |
providing Training of Globex Employees |
2 days |
System Trainer |
4.2 |
Developing the strategies of Marketing Plan |
2 days |
System Trainer |
4.3 |
Providing System Tutorial Brochure |
2 days |
System Trainer |
4.4 |
Phase 4 completed |
0 days |
|
5 |
phase 5: Project Closing |
11 days |
|
5.1 |
Post Project Review after completion |
4 days |
IT Manager |
5.2 |
preparing Documentation of Entire Project |
3 days |
Project Manager |
5.3 |
Sign Off from the stakeholders |
2 days |
Project Supervisor, Marketing and Commerce Manager, Data Management Officer, Developer, Technical Integration Specialist, IT Manager, Technical Expert, System Trainer |
5.4 |
Project Manager and other executive Sign Off |
2 days |
Project Manager |
5.5 |
Phase 5 completed |
0 days |
Sl. No. |
Task Name |
Duration |
Resource Names |
Cost |
0 |
Online Stud Farm Management System |
81 days |
$6,920.00 |
|
1 |
Phase 1: project Planning |
35 days |
$3,120.00 |
|
1.1 |
Arrangement of Meeting between the Virtucon and Globex for the communication purpose |
15 days |
Project Manager |
$1,200.00 |
1.2 |
Preparing the Proposal of the Project |
5 days |
Project Manager, Technical Expert |
$600.00 |
1.3 |
Identifying the feasibility of the proposed solution |
3 days |
IT Manager, Technical Expert |
$240.00 |
1.4 |
proposing of the draft of the Virtucon |
3 days |
IT Manager |
$120.00 |
1.5 |
Forwarding for the Approval |
2 days |
Project Manager, IT Manager |
$240.00 |
1.6 |
Paper Sign-off by the involved stakeholders in the Virtucon and Globex |
3 days |
Project Supervisor, Project Manager |
$480.00 |
1.7 |
Development of the Project Charter |
2 days |
Technical Expert |
$80.00 |
1.8 |
forwarding for the Approval |
2 days |
Project Manager |
$160.00 |
1.9 |
Phase 1 completed |
0 days |
$0.00 |
|
2 |
Phase 2: Project Initiation |
10 days |
$560.00 |
|
2.1 |
Procurement plan for the project funds |
4 days |
Project Supervisor |
$320.00 |
2.2 |
identifying the list of requirements necessary for the project |
3 days |
Marketing and Commerce Manager |
$120.00 |
2.3 |
Proposing the System Design Proposal |
2 days |
Marketing and Commerce Manager |
$80.00 |
2.4 |
Estimating the roles and responsibilities of the stakeholders in the project |
1 day |
Technical Expert |
$40.00 |
2.5 |
Phase 2 completed |
0 days |
$0.00 |
|
3 |
Phase 3: Project Execution |
19 days |
$1,560.00 |
|
3.1 |
Developing the Procurement of needed Software |
1 day |
IT Manager |
$40.00 |
3.2 |
Developing the Procurement of needed Hardware |
2 days |
IT Manager |
$80.00 |
3.3 |
Integrating the Hardware within existing System |
2 days |
Technical Integration Specialist |
$160.00 |
3.4 |
Initiating the Proposed System Development |
1 day |
Technical Integration Specialist |
$80.00 |
3.5 |
Developing the Online Management System for the farm |
5 days |
Technical Integration Specialist |
$400.00 |
3.6 |
implementing the Features |
5 days |
Data Management Officer |
$200.00 |
3.7 |
Integrating the UI |
2 days |
Developer |
$160.00 |
3.8 |
Evaluating the system functioning |
3 days |
Developer |
$240.00 |
3.9 |
Documenting the completion of this phase |
1 day |
Developer, Technical Integration Specialist, IT Manager |
$200.00 |
3.10 |
Phase 3 completed |
0 days |
$0.00 |
|
4 |
Phase 4: Training |
6 days |
$240.00 |
|
4.1 |
providing Training of Globex Employees |
2 days |
System Trainer |
$80.00 |
4.2 |
Developing the strategies of Marketing Plan |
2 days |
System Trainer |
$80.00 |
4.3 |
Providing System Tutorial Brochure |
2 days |
System Trainer |
$80.00 |
4.4 |
Phase 4 completed |
0 days |
$0.00 |
|
5 |
phase 5: Project Closing |
11 days |
$1,440.00 |
|
5.1 |
Post Project Review after completion |
4 days |
IT Manager |
$160.00 |
5.2 |
preparing Documentation of Entire Project |
3 days |
Project Manager |
$240.00 |
5.3 |
Sign Off from the stakeholders |
2 days |
Project Supervisor, Marketing and Commerce Manager, Data Management Officer, Developer, Technical Integration Specialist, IT Manager, Technical Expert, System Trainer |
$880.00 |
5.4 |
Project Manager and other executive Sign Off |
2 days |
Project Manager |
$160.00 |
5.5 |
Phase 5 completed |
0 days |
$0.00 |
The risk analysis plan is a set of practices that allows the managers to identify, analyze, and propose the strategies those could be implemented for the elimination of the risks and issues in the successful deployment of the online stud farm management system. The first phase of this analysis will be to identify the risks associated with the project and identifying the possible solutions, those could be implemented for the elimination of these risks. There after the risk prioritization and levelling of the risk is another factor that will be helpful in ranking the strategies as per their impact on the project and eliminating the most influencing risk prior to the delivery of the risk management plan for the project. Thereafter the strategies and activities will be considered those could be applied for mitigating the identified risks.
Following are the assumptions those could be considered while delivering the risk management for the online stud farm management system:
Phase |
Risk |
Chance of Occurrence |
Effect on Project |
Management Strategy |
Project closure |
The proposed solution is not capable of providing the effective outcome of the project |
Medium |
High |
The planning strategy is the crucial part for the consideration of the delivery and output of the project. stakeholder communication should be given priority in manner to assure that all the areas being covered and customers will be satisfied of the services being delivered to them |
Project monitoring and controlling |
Many bugs and glitches identified in the proposed system and it is capable of affecting the overall execution of the project |
High |
Very High |
The IT team developing the management system should evaluate the system previously before incorporating within the existing system of the organization. |
Project Execution |
Lack in resources and non-technical works could possibly affect the overall growth and development of the project |
High |
High |
The hardware and software being implemented within the existing system, should be updated and of latest versions in manner to assure that the system will be efficiently delivering the necessary output. |
Project Planning |
Scope creep is always a considerable aspect and emphasizing risk in this phase of the project as it might lack despite of effective and efficient delivery of the above phases |
High |
Very High |
The milestones should be executed and completed within the expected time will be helpful in driving the project concentric to the expected scope of the project. |
Project initiation |
Lacking in financial aspects for the delivery of the phase is another considerable objective of the project |
Very High |
High |
The budget and resource planning should be delivered in an efficient and effective manner assuring the delivery of the project. |
The project team follows one philosophy: team work. The entire team believes if the team members coordinate with each other emphasizing on the fact that they will be able to overcome any challenges and complete all their project duties successfully.
“The project quality will be determined based on the pre set measurable organization value (MOV) and the project metrics that have also been defined earlier. To analyse the quality of the project, the project supervisor must ensure all the requirements and standards for the project have been made.”
Project Name: Online Stud Farm Management System |
Prepared by: [Please fill] |
Date: 15th May 15, 2018 |
Project Scope Management: The proposed report will be helpful in assuring that the scope of the project is being accomplished and managed in an efficient and effective manner. The proposed report states that the project will be delivered within 108 days and the budget of $ 167,640 |
Scope Change: The project might need change for a single time during the phase of the monitoring and controlling for the identification of the bugs and glitches and thus, changes will be deployed accordingly. |
Changes implementation in scope of the project: The changes will be applied considering the phases from where the project needed to change from where the change will be affecting the project |
The project closure checklist is as follows.
Item |
Check |
No Overspending Done during Project |
|
Deadline for Project is Met |
|
All system errors and bugs have been addressed |
|
System Requirements have been met |
|
‘Signature |
The project evaluation will be done by the project manager. He will first study the documentation of the project and then review the developed system by himself. Furthermore, he will review the item checklist and mark them as completed before signing off from the project.”
Binder, J. (2016). Global project management: communication, collaboration and management across borders. Routledge.
Boud, D., Cohen, R., & Sampson, J. (Eds.). (2014). Peer learning in higher education: Learning from and with each other. Routledge.
Brooks, R., 2015. Financial management: core concepts. Pearson.
Crawford, J.K., 2014. Project management maturity model. CRC Press.
Fleming, Q. W., & Koppelman, J. M. (2016, December). Earned value project management. Project Management Institute.
Gido, J., Clements, J. and Clements, J., 2014. Successful project management. Nelson Education.
Harrison, F. and Lock, D., 2017. Advanced project management: a structured approach. Routledge.
Heagney, J. (2016). Fundamentals of project management. AMACOM Div American Mgmt Assn.
Heldman, K., 2018. PMP: project management professional exam study guide. John Wiley & Sons.
Kerzner, H. and Kerzner, H.R., 2017. Project management: a systems approach to planning, scheduling, and controlling. John Wiley & Sons.
Kerzner, H., 2017. Project management metrics, KPIs, and dashboards: a guide to measuring and monitoring project performance. John Wiley & Sons.
Martinelli, R.J. and Milosevic, D.Z., 2016. Project management toolbox: tools and techniques for the practicing project manager. John Wiley & Sons.
Olson, D., 2014. Information systems project management. Business Expert Press.
Schwalbe, K. (2015). Information technology project management. Cengage Learning.
Turner, R. (2016). Gower handbook of project management. Routledge.
Verzuh, E. (2015). The fast forward MBA in project management. John Wiley & Sons.
Walker, A. (2015). Project management in construction. John Wiley & Sons.
Essay Writing Service Features
Our Experience
No matter how complex your assignment is, we can find the right professional for your specific task. Contact Essay is an essay writing company that hires only the smartest minds to help you with your projects. Our expertise allows us to provide students with high-quality academic writing, editing & proofreading services.Free Features
Free revision policy
$10Free bibliography & reference
$8Free title page
$8Free formatting
$8How Our Essay Writing Service Works
First, you will need to complete an order form. It's not difficult but, in case there is anything you find not to be clear, you may always call us so that we can guide you through it. On the order form, you will need to include some basic information concerning your order: subject, topic, number of pages, etc. We also encourage our clients to upload any relevant information or sources that will help.
Complete the order formOnce we have all the information and instructions that we need, we select the most suitable writer for your assignment. While everything seems to be clear, the writer, who has complete knowledge of the subject, may need clarification from you. It is at that point that you would receive a call or email from us.
Writer’s assignmentAs soon as the writer has finished, it will be delivered both to the website and to your email address so that you will not miss it. If your deadline is close at hand, we will place a call to you to make sure that you receive the paper on time.
Completing the order and download