This report is related to the construction of Federation Square which has been facing issues in its completion due to administrative and construction chaos associated and compounded by the project’s inability to develop an adequate brief at the outset of the project. It is a prime mega project whose completion is in dark state and is required an instant suitable strategic construction procurement method to effectively complete it within the budget and stipulated time(Lam & Chan, 2017).
Managing projects effectively is a fundamental good governance issue. The strategic project provides appropriate balances and checks to assure that the contractor is providing the desired services at the desired standards. It ensures the efficient and economical use of public funds. That’s why it is necessary to implement a suitable contract procurement strategy during the construction of the business(Watermeyer, 2012).
The procurement system or delivery system is a managerial system that allocates particular authorities and responsibilities to the people and the organizations. It defines various elements of a construction project(ProcurePoint, 2017). There are various types of procurement methods such as: Early Contractor Involvement (ECI),design & construct, traditional, alliancing, and Public Private Partnerships (PPP), etc.(Richards, 2006).
The decision regarding selection of procurement method to be utilized in the project should be taken as soon as possible and it should also be supported by the user’s business case for the project. The risks related to each procurement approach and how these risks affect the user should also be taken into account. The development of the procurement construction strategy depends on the various factors such as external factors, project characteristics, client resources, cost issues, ability to make changes, timings etc.(Coastal Carolina University, 2012).
Currently, by reviewing the case study of the Federation Square Project, it can be stated that the current procurement approach used by the procurement manager is traditional procurement approach. Under the traditional procurement approach, consultants are employed for designing and cost control, design work is separate from the construction, and contractor is responsible for all types of works(Purchasing-procurement-center, 2017). Basically, there are three types of contracts under the traditional procurement method named Lump sum contracts, cost reimbursement contracts, and measurement contracts.
The current procurement strategy of the Federation Square Project is Lump Sum because in the year 1999 the project entered into a lump sum, fixed fee contract to construct Federation Square by the then Victorian Government Office of Major Projects acting on behalf of the State Government. Fixed amount under this contract is not subject to recalculation and employer does not have any opportunity to make variations(Engel, 2011).
The major drawback of utilizing traditional method is the documentation of the contract which can be a time consuming process. Also, incomplete documentation can lead to less time and cost certainty which can further lead to disagreements. Further, duration of the whole project may be longer as compared to the other procurement methods because this strategy is sequential in nature and without finishing the design phase, the construction cannot be commenced(Davis, et al., 2008). Further, the contractor cannot give any contribution in the designing or planning of the project as they were not present during this phase (Yip & Chin, 2011)
In the current federation square project, the main issues are coming because traditional approach is related to the ongoing or ever-changing designing of the project and subsequent documentation. The ongoing development of the design has made it difficult for the tenderers to define the scope, time, and risk required for the construction of the project. Hence, it is necessary to change the current procurement construction strategy for the project(Kong & Gray, 2017).
The final selection of the procurement construction strategy takes account of the issues like(Crespin-Mazet & Dontenwill, 2012):
As per the review of the previous procurement construction strategy, it can be stated that no form of traditional procurement is suitable for this construction project because this construction project is a large complex construction project which is not possible to handle by applying the traditional approach. The project has already been delayed and it is facing the issue of design completion in the complex construction and working conditions(Victorian Government, 2012).
There are many approaches adopted by project procurement managers as per their suitability but as per the review of the current condition of the project, the best suitable construction procurement strategy is the management procurement strategy. The reason for selecting this strategy is due to its suitability to large, complex, and fast- moving projects and federation square project is a large and complex project where early completion is desirable. The most noticeable difference between the traditional building contracts and the management procurement contracts is the altered contracts between the main contractor and client. Under the traditional method, builder is called to file tender for the building work. Under this, the contractor assesses the building costs as per the requirements of the documents and specifications of the supplied tender and after all this, the builder submit a firm price for the construction costs, overheads costs, and a profit margin while, under the construction management, a choice is provided by the contract manager which consist of a predetermined fee on the basis of either fixed or percentage or combination of both(DVPM, 2017).
The management procurement strategy involves three variants: management contracting, design and manage, and construction management. These three forms have subtle differences. Construction management approach is most suitable to be used or federation square project(University of Illinois, 2017). It is a type of arrangement where the client appoints a construction manager on a fee basis and the construction manager has the sole responsibility for managing and aligning the design and construction phases of the project. This type of approach gives the greater measure of control to the client and the client can accept a significant amount of risk. The appointed management contractor is an agent(Department of Housing and Public Works, 2017).
Here in the development of the federation square project, the project is struggling from the issue of countless design revisions, political intervention, delays, and damages. The projects are facing all these issues due to the lack of the contract manager who can deal with all these issues and enables cooperation to advance the project’s constructability (MyManagementGuide, 2011).
Figure 1: Construction Management Procurement
Under this construction management procurement method there are three trade contractors: consultant, architect and construction manager. Under the traditional approach, the construction manager is appointed after the completion of the design and specification phase while in construction management approach, the construction manager can be appointed during the design stage. The construction manager plays an important role in sharing information with the design team (Sokanu, 2017). The great knowledge of the construction manager regarding the build ability results in a more cost efficient design for the federation square project. Currently, the project is going through the critical stage due to its design issue and this is the reason behind the delaying of the overall project so the appointment of the construction manager will help to complete the design of the project as soon as possible and facilitates the construction of the building(Gransberg & Shane, 2010).
The role of the construction managers is diverse and can be executed under an assortment of contractual terms. The most customary form of the construction manager is that when he/she works as an agent of the client. Under this role, he professionally provides a total estimate of the project, undertakes administrative responsibilities during the construction, control cost and schedule services. All the contracts are executed between the contractor and the owner. This approach allows the manager to break down the construction work in a number of contracts. This strategy eliminates the need for the general contractors and the elimination of the general contractors reduces the overall overhead cost of the project(Charpentier, 2017).
There are some key points that need to be considered with management procurement(Whiting, 2017). These points are as follows:
There are some features of construction management method that should be included at the time of adopting this strategy for the completion of the Federation Square Project such as project team relationship, fast track construction, an early appointment of the construction manager etc.(Harris & McCaffer, 2013).
Under the traditional procurement construction methods the construction manager is appointed after the completion of the design and specification phase but in case of construction management, the construction manager is appointed at the early stage of the project (Designing Buildings, 2017). In the case of construction of the Federation Square Project as the project has already been delayed due to the incomplete design phase that’s why it is necessary to involve the construction manager in the design phase so that he/she can participate in the design phase and share their experience regarding the construction. Appointment of the construction manager at the early stage will facilitate to identify the items with long lead times so that they can be started early to complete them by the final completion stage of the project. The careful pre-construction planning to build the methodology resulted in a quicker site start-up period(Designing Buildings, 2017).
Construction management method allows the concept of fast-tracking in a construction project. The fast tracking can be performed by overlapping the planning, design, tender, award, and construction (Gatto, 2015). While comparing to the traditional procurement construction project, the construction management method is just opposite to it because under the traditional approach each activity is dependent on the previous activity and only after the completion of the previous activity a new activity can be started that’s why the federation square project was not completed yet as without the completion of the design the construction phase was not started and the overall project delayed. The ongoing development of the design makes it difficult to define the scope, risks, and time required for completing the constructability of the project. That’s why it is necessary to add the fast-tracking feature of the construction management where specialist contractors in their field are asked to file the tenders for the particular section of the work. This makes the construction commences at the earliest possible time(Gatto, 2015).
Figure 2: Construction Management Method
The construction management method of procurement construction management is characterized by the relationship between the construction manager and the project design team members and the user/ client of the building. Unlike traditional method, in construction management, the builder is appointed on the same rank just like design team members. The alterations by the builder in the design and the construction phase have caused construction management to meet with the complexity of the project(Young, 2009).
Conclusion
Overall, to complete the Federation Square project it is recommended to change the procurement construction strategy from traditional to construction management. This strategy is best suitable to deliver the project as fast as possible without incurring extra charges, time, and risk. Construction management procurement strategy is best suitable to address the issues of the federation square project. The issues of design completion can be solved by the appointment of the construction manager. The issue of delay of the project can be solved by running the design and construction phases simultaneously and by issuing tenders for small tasks of the project.
References
Achilles , 2014. How external factors can affect procurement. [Online] Available at: https://www.achilles.com/en/about-achilles/industry-insights/1308-how-external-factors-can-affect-procurement [Accessed 22 May 2017].
Charpentier, W., 2017. Duties & Responsibilities for a Construction Project Manager. [Online] Available at: https://work.chron.com/duties-responsibilities-construction-project-manager-12731.html [Accessed 22 May 2017].
Coastal Carolina University, 2012. Procurement Decision-Making Process. [Online] Available at: https://www.coastal.edu/procurement/docs/flowchart_jan2012.pdf [Accessed 22 May 2017].
Constructing Excellence, 2015. Procurement (Client). [Online] Available at: https://constructingexcellence.org.uk/resources/procurement-client/ [Accessed 22 May 2017].
Crespin-Mazet, F. & Dontenwill, E., 2012. Sustainable procurement: Building legitimacy in the supply network. journal of Purchasing and Supply Management, 18(4), pp. 207-217.
Davis, P., Love, P. & Baccarini, D., 2008. Building Procurement Methods, s.l.: s.n.
Department of Housing and Public Works, 2017. Procurement Strategy and Contract Selection, s.l.: Department of Housing and Public Works.
Designing Buildings, 2017. Construction management: appointing the construction manager. [Online]
Available at: https://www.designingbuildings.co.uk/wiki/Construction_management:_appointing_the_construction_manager
[Accessed 22 May 2017].
DVPM, 2017. Construction Management as a Procurement Option , s.l.: DVPM.
Engel, B., 2011. 10 best practices you should be doing now. [Online]
Available at: https://www.supplychainquarterly.com/topics/Procurement/scq201101bestpractices/
Gatto, J., 2015. Electricians, Plumbers: 6 Solutions to Fast-Track Construction Projects. [Online]
Available at: https://www.gocanvas.com/content/blog/post/electricians-plumbers-6-solutions-to-fast-track-construction-projects
[Accessed 22 May 2017].
Gransberg, D. D. & Shane, J. S., 2010. Construction Manager-at-risk Project Delivery for Highway Programs. s.l.:Transportation Research Board.
Gush, R., 2013. Construction Cost Estimation: Challenges and Issues. [Online]
Available at: https://methvin.org/civil-engineering/estimating/388-construction-cost-estimation-challenges-and-issues
Harris, F. & McCaffer, R., 2013. Modern Construction Management. seventh edition ed. s.l.:s.n.
Kong, A. T. & Gray, J., 2017. Traditional Procurement is too slow, s.l.: s.n.
Lam, P. T. & Chan, A. P., 2017. Construction Management As A Procurement Method A New Direction For Asian Constractors , s.l.: s.n.
Mendel, B., 2012. Top 10 Benefits of Construction Management Services. [Online] Available at: https://www.stonemarkcm.com/design-construction-management-blog/2012/01/03/top-10-benefits-of-professional-construction-management/ [Accessed 22 May 2017].
MyManagementGuide, 2011. Project Procurement Management: 5 Steps Of The Process. [Online] Available at: https://www.mymanagementguide.com/project-procurement-management/ [Accessed 21 May 2017].
ProcurePoint, 2017. Procurement System for Construction. [Online] Available at: https://www.procurepoint.nsw.gov.au/before-you-buy/construction/procurement-system-construction [Accessed 22 May 2017].
Purchasing-procurement-center, 2017. The 6 Core Purchasing Strategies. [Online] Available at: https://www.purchasing-procurement-center.com/purchasing-strategies.html [Accessed 22 May 2017].
Richards, G., 2006. Procurement Methods in the Construction Industry. [Online] Available at: https://www.mondaq.com/x/38356/real+estate/Procurement+Methods+in+the+Construction+Industry [Accessed 22 May 2017].
Sokanu, 2017. What is a Construction Manager?. [Online] Available at: https://www.sokanu.com/careers/construction-manager/aka/construction-project-manager/ [Accessed 22 May 2017].
University of Illinois, 2017. Construction Engineering and Management. [Online] Available at: https://cee.illinois.edu/areas/construction-engineering-and-management [Accessed 22 May 2017].
Victorian Government, 2012. Managing Major Projects, s.l.: Victorian Government Printer.
Watermeyer, R. B., 2012. A framework for developing construction procurement strategy. Proceedings of the Institution of Civil Engineers – Management, Procurement and Law,, 165(4), pp. 223-237 .
Whiting, B., 2017. What is Project Procurement Management? – Definition & Process. [Online] Available at: https://study.com/academy/lesson/what-is-project-procurement-management-definition-process.html [Accessed 22 May 2017].
Yip, S. & Chin, M., 2011. Procurement models: improving on the traditional method. [Online] Available at: https://www.minterellison.com/Pub/NL/201112_CLAa/ [Accessed 22 May 2017].
Young, M. L., 2009. Building Relationships In Project Management.[Online] Available at: https://www.projectsmart.co.uk/building-relationships-in-project-management.php [Accessed 22 May 2017].
Essay Writing Service Features
Our Experience
No matter how complex your assignment is, we can find the right professional for your specific task. Contact Essay is an essay writing company that hires only the smartest minds to help you with your projects. Our expertise allows us to provide students with high-quality academic writing, editing & proofreading services.Free Features
Free revision policy
$10Free bibliography & reference
$8Free title page
$8Free formatting
$8How Our Essay Writing Service Works
First, you will need to complete an order form. It's not difficult but, in case there is anything you find not to be clear, you may always call us so that we can guide you through it. On the order form, you will need to include some basic information concerning your order: subject, topic, number of pages, etc. We also encourage our clients to upload any relevant information or sources that will help.
Complete the order formOnce we have all the information and instructions that we need, we select the most suitable writer for your assignment. While everything seems to be clear, the writer, who has complete knowledge of the subject, may need clarification from you. It is at that point that you would receive a call or email from us.
Writer’s assignmentAs soon as the writer has finished, it will be delivered both to the website and to your email address so that you will not miss it. If your deadline is close at hand, we will place a call to you to make sure that you receive the paper on time.
Completing the order and download