Introduction
The following assignment is based on the alignment of the operations that would help in execution of the improved project operations. The development of the activities would be helpful for executing the implementation construction activities (Schwalbe 2015). The natural heritage site would be constructed for the alignment of the activities supporting the implementation of the successive construction activities. The allowance would be aligned for the significant development of the functions would be formed for listing the utilization of the effective implication of the successful stakeholder management, risk management, project planning, and lesson learnt from the study. The successful reflection of the project management skills would be aligned for the complete report.
Part 1
Stakeholder Management
The project of construction of world class attraction and national heritage site would require the implication of the effective development and processing (Walker 2015). The project would include a number of stakeholders for executing the project and it would support the implication of the effective roles and responsibilities for supporting the implication of the effective activity development. The stakeholder management involve the identification of the stakeholders, analysis of the stakeholders, and stakeholder communication plan development. The identification of the stakeholders in based on the roles played by them for the project of construction of world class attraction and national heritage site. The stakeholders are the key personal that are directly or indirectly affected by the project activities. The stakeholders have some influence, expectation, and power in the execution of the project activities (Fleming and Koppelman 2016). The analysis is based on these criteria so that the completion of the project can assist the development of the operations. The influence and power of the stakeholders can be divided into categories of high, low, and medium. The analysis can also be helpful for defining the influence of the probable project development. The communication plan is based on the need for transferring the information to the stakeholders. It is important for managing the communication with the stakeholders as it would help in ceasing the influence and power factors for the project (Heagney 2016). The stakeholder management for the project is given below,
Stakeholder |
Roles |
Influence |
Power |
Communication |
Client |
In charge of acceptance or rejection of the final project deliverable |
High |
High |
Progress Update of the project is required by the client |
Investors |
Provide initial investments for the project activities |
High |
High |
Resource Usage documents are submitted to the investors |
Visitors |
End users of the cultural heritage building for the general entertainment purpose |
Low |
High |
Inauguration and publically availability of the heritage building would be conveyed to the visitors |
Government |
Inspection of the site to check whether construction activities have followed all safety measures |
High |
Low |
Completion and safety details of the heritage site developed would be conveyed |
Project Manager |
Ensure that all activities are completed and project meets the SLA with the client |
Low |
High |
Progress, Issues, and change requirements in the project |
Risk Management
According to Bessis (2015), Risk Management is the process of reducing the possible impact of the risk factors in a project operation. The project of construction of world class attraction and national heritage site would be dependent on the various construction activities and it would tend to involve many risk factors like lack of construction materials, interjection by locals, quality issues, unapproved designs, and overshoot of time and budget constraints. These five are the major risks that can impact the completion of the construction activities. The risk management can be divided into risk identification, analysis, and mitigation (Glendon, Clarke and McKenna 2016). The process of risk management comprises of the development of the effective and smart influence of the risk factors on the project of construction of world class attraction and national heritage site. The risk management is initiated by the process of risk identification for the construction project. The various possible risks that can affect the project completion are listed in this process. The risk factors would result in forming the major problems for the smooth operation of the project activities (McNeil, Frey and Embrechts 2015). The analysis is done by analysing the possible impact, probability, and the severity of the individual risk factors. The implication of the risk analysis can be used for the formation of the major risk factors. The following table would show the risk management requirements for the project of construction of world class attraction and national heritage site,
Risk Identification |
Risk Analysis |
Risk Mitigation |
|||
Name |
Description |
Probability |
Severity |
Impact |
Mitigation Strategy |
Lack of Construction Materials |
The construction project would require a number of construction materials and shortage of the materials would lead to this problem of shortage of resources. The lack of materials would result in delaying the completion of the construction activities for project of construction of world class attraction and national heritage site. |
Possible |
Major |
High |
Resource Management Plan should be project |
Interjection by Locals |
The locals can probably interject in the construction process due to the noise and air pollution that might occur during the construction activities. The locals play an external role in influencing the project as most of the activities of the project would be dependent on the execution support by the local community. |
Rare |
Moderate |
Medium |
Social Gatherings for influencing people |
Quality Issues |
Quality issues are another major factor that would result in forming the major problem for the development of the cultural heritage building for the project of construction of world class attraction and national heritage site. |
Likely |
Critical |
Extreme |
Quality Management Plan should be developed for this problem |
Unapproved Designs |
The unapproved and unreviewed designs of the site would also result in forming the major setback for the project operations. The construction activities might not get completed due to this problem. |
Rare |
Major |
Medium |
Design testing and approval process should be used |
Overshoot of Time and Budget Constraints |
The delay of the project activities due to the various possible project problems. The delay in project would result in forming the problems for the client in overcoming the possible issues. |
Almost Certain |
Minor |
Low |
Schedule and Budget Management Plan should be used |
Project Planning
The following is the project plan for the project of construction of world class attraction and national heritage site,
WBS |
Task Name |
Duration |
Start |
Finish |
0 |
Construction of world class attraction and national heritage site |
86 days |
Mon 6/25/18 |
Mon 10/22/18 |
1 |
Initialization |
10 days |
Mon 6/25/18 |
Fri 7/6/18 |
1.1 |
Analysis of requirements |
3 days |
Mon 6/25/18 |
Wed 6/27/18 |
1.2 |
Documentation |
2 days |
Thu 6/28/18 |
Fri 6/29/18 |
1.3 |
Tender Development |
4 days |
Mon 7/2/18 |
Thu 7/5/18 |
1.4 |
Tender Submission |
1 day |
Fri 7/6/18 |
Fri 7/6/18 |
1.5 |
Project Approval |
0 days |
Fri 7/6/18 |
Fri 7/6/18 |
2 |
Planning |
14 days |
Mon 7/9/18 |
Thu 7/26/18 |
2.1 |
Sorting out construction activities |
5 days |
Mon 7/9/18 |
Fri 7/13/18 |
2.2 |
Listing them in sequential method |
3 days |
Mon 7/16/18 |
Wed 7/18/18 |
2.3 |
Scheduling them in timeline |
4 days |
Thu 7/19/18 |
Tue 7/24/18 |
2.4 |
Reviewing Project Plan |
2 days |
Wed 7/25/18 |
Thu 7/26/18 |
2.5 |
Plan Approval |
0 days |
Thu 7/26/18 |
Thu 7/26/18 |
3 |
Construction |
55 days |
Fri 7/27/18 |
Thu 10/11/18 |
3.1 |
Site Clearing |
6 days |
Fri 7/27/18 |
Fri 8/3/18 |
3.2 |
Office Site Set up |
4 days |
Mon 8/6/18 |
Thu 8/9/18 |
3.3 |
Safety Equipments are installed |
3 days |
Fri 8/10/18 |
Tue 8/14/18 |
3.4 |
Transportation Set up |
2 days |
Wed 8/15/18 |
Thu 8/16/18 |
3.5 |
External Structure is developed |
15 days |
Fri 8/17/18 |
Thu 9/6/18 |
3.6 |
Internal Structure is developed |
12 days |
Fri 9/7/18 |
Mon 9/24/18 |
3.7 |
Final Furnishing |
10 days |
Tue 9/25/18 |
Mon 10/8/18 |
3.8 |
Emergency exits and safe environment is developed |
3 days |
Tue 10/9/18 |
Thu 10/11/18 |
4 |
Inspection and Closure |
7 days |
Fri 10/12/18 |
Mon 10/22/18 |
4.1 |
Government Inspection and Approval |
2 days |
Fri 10/12/18 |
Mon 10/15/18 |
4.2 |
Client Sign off |
1 day |
Tue 10/16/18 |
Tue 10/16/18 |
4.3 |
Proper final report |
3 days |
Wed 10/17/18 |
Fri 10/19/18 |
4.4 |
Submission of documents |
1 day |
Mon 10/22/18 |
Mon 10/22/18 |
4.5 |
Project Closed |
0 days |
Mon 10/22/18 |
Mon 10/22/18 |
Process for recording the lesson learnt
The lesson learnt can be recorded by the use of the journal and e-portfolio made for storing the day to day activities and the related information processing. The journals are the records that would involve the activities of the project along with the small notes for self improvement. The records are kept for ensuring that the effective documentation would be kept for the alignment of the future prospects. The steps required for recording the lesson learnt are,
Step 1- Collecting information of the activities executed in the project
Step 2- Sorting the new processes or techniques used in the project
Step 3- Analysis of the lesson learnt from the new processes or techniques
Step 4- Documenting the lessons learnt in a proper document
Step 5- Saving the file for future use
Part 2
Reflection of Project Management Skills
In this project of construction of world class attraction and national heritage site, I acted as a project manager and it allowed the implication of the operations for developing the effective alignment of the improved functional development. The project management concepts of planning, scheduling, and developing the effective project plan would be developed. I had been able to understand the project management concepts for stakeholder and risk management processes. The process of risk management comprises of the development of the effective and smart influence of the risk factors on the project of construction of world class attraction and national heritage site. I initiated the risk management by the process of risk identification for the construction project. The various possible risks that can affect the project completion are listed in this process. The risk factors would result in forming the major problems for the smooth operation of the project activities. My analysis was done by analysing the possible impact, probability, and the severity of the individual risk factors. The implication of the risk analysis can be used for the formation of the major risk factors. The stakeholder management involve the identification of the stakeholders, analysis of the stakeholders, and stakeholder communication plan development. The identification of the stakeholders in based on the roles played by them for the project of construction of world class attraction and national heritage site. I realized that the stakeholders are the key personal that are directly or indirectly affected by the project activities. The stakeholders have some influence, expectation, and power in the execution of the project activities. The analysis is based on these criteria so that the completion of the project can assist the development of the operations. The influence and power of the stakeholders can be divided into categories of high, low, and medium.
Conclusion
The above assignment was based on the alignment of the operations that had help in execution of the improved project operations. The development of the activities had been helpful for executing the implementation construction activities. The natural heritage site had been constructed for the alignment of the activities supporting the implementation of the successive construction activities. The allowance had been aligned for the significant development of the functions had been formed for listing the utilization of the effective implication of the successful stakeholder management, risk management, project planning, and lesson learnt from the study. The successful reflection of the project management skills had been aligned for the complete report.
Essay Writing Service Features
Our Experience
No matter how complex your assignment is, we can find the right professional for your specific task. Contact Essay is an essay writing company that hires only the smartest minds to help you with your projects. Our expertise allows us to provide students with high-quality academic writing, editing & proofreading services.Free Features
Free revision policy
$10Free bibliography & reference
$8Free title page
$8Free formatting
$8How Our Essay Writing Service Works
First, you will need to complete an order form. It's not difficult but, in case there is anything you find not to be clear, you may always call us so that we can guide you through it. On the order form, you will need to include some basic information concerning your order: subject, topic, number of pages, etc. We also encourage our clients to upload any relevant information or sources that will help.
Complete the order formOnce we have all the information and instructions that we need, we select the most suitable writer for your assignment. While everything seems to be clear, the writer, who has complete knowledge of the subject, may need clarification from you. It is at that point that you would receive a call or email from us.
Writer’s assignmentAs soon as the writer has finished, it will be delivered both to the website and to your email address so that you will not miss it. If your deadline is close at hand, we will place a call to you to make sure that you receive the paper on time.
Completing the order and download