The aim of this report is to evaluate the existing system of the TOSIG (Tier One Suppliers Insurance Company) and propose the cloud computing as the appropriate approach for the management of the new customers. The identified problem was that the agents were not able to retrieve data while communicating with new customers outside the office premises and that led to the less influence on the customers to be associate with the organization. Cloud computing will allow the agents to be connected with the data and information 24*7 hours and thus, improve the figures of the new customers associating with the organization.
1.2 Objectives
1.3 Budget Estimate and Assumptions
The feasibility study can be done with a budget of $ 10,000 however; the entire project can be delivered with a budget of $ 50,000 as expressed in this report.
1.3.1 Assumptions
Following are the assumptions:
1.3.2 Project Name
Name of the project will be Transformation in TOSIG
The expected time for the project will be less than seven months
2. Business case
2.1 Roles and Responsibilities
Stakeholder |
Name |
Roles |
Responsibilities |
Organization executives |
Tahlia McWilliams |
Take hard decisions on sensitive transformations |
Take decisions considering every stakeholder |
Project Manager |
Archer Polglaze |
Manage the project activities and stakeholders |
Maintain the project constraints |
Business Analyst |
Gabriella Dunbabin |
Analyze the needs and requirements of the business |
Comply the solution with the business requirements |
Market analyst |
Nathan Liston |
Analyze the competitors status |
Propose a sophisticated data analysis |
Resource Manager |
Leah Nairn |
Manage the resources for the delivery of the project |
Make sure that there is neither lack in resources or excess in resources |
Cloud Vendors |
Microsoft Azure |
Provide cloud services |
Comply the TOSIG’s policy with theirs |
IT technicians |
Liam Learmonth |
Manage the technical jobs |
Make sure that the system does not have any bugs or glitches |
HR |
Jacob Macarthur-Onslow |
Manage the human resources |
To aware the human resources about their rights |
Finance Manager |
Gabriel Hetherington |
Manage the financial status of the project |
Make sure that the financial related requirements are fulfilled |
2.2 Organizational Structure
The agents are facing trouble in presenting the overall information in front of the customers that is not helping in engaging them with the organization and take insurance from the company. The agents are not able to access the data and information on the field and hence, not able to attract customers so, cloud implementation within the existing system will be helpful in eliminating this issue and providing the agents with a facility to access the data and information on the fields. This transformation will not need the data migration over the cloud rather the organization will also need to utilize on-demand software services and providing the agents with the mobile devices those are compatible with the new applications.
3.1 Tools and Techniques
SAP ERP, Microsoft AZURE, IT infrastructure, High bandwidth internet connection, latest mobile devices with better configuration, and wireless connectivity are the tools those are necessary for the successful deployment of this project.
4. Stakeholder Analysis
4.1 Stakeholder Register
SL No |
Stakeholder |
Interest |
Impact |
1 |
Organization executives |
Very high |
Very High |
2 |
Project Manager |
High |
Very High |
3 |
Business Analyst |
Medium |
High |
4 |
Market analyst |
Medium |
Medium |
5 |
Resource Manager |
Low |
High |
6 |
Cloud Vendors |
Very High |
Very Low |
7 |
IT technicians |
Low |
Low |
8 |
HR |
Medium |
Low |
9 |
Finance Manager |
Very Low |
Low |
10 |
Customers |
Very Low |
Very Low |
11 |
Agents |
Very High |
High |
4.2 Stakeholder Prioritization Matrix
Interest |
|||||
Very High |
6 |
11 |
1 |
||
High |
2 |
||||
Medium |
8 |
4 |
3 |
||
Low |
7 |
5 |
|||
Very low |
10 |
9 |
|||
Impact |
Very Low |
Low |
Medium |
High |
Very High |
5. Milestone Schedule
Milestones:
Task Name |
Duration |
Start |
Finish |
TOSIG migration to cloud |
192 days |
Mon 5/28/18 |
Tue 2/19/19 |
Project Planning |
42 days |
Mon 5/28/18 |
Tue 7/24/18 |
Milestone 1: Planning completed |
0 days |
Tue 7/24/18 |
Tue 7/24/18 |
New platform preparation |
38 days |
Wed 7/25/18 |
Fri 9/14/18 |
Milestone 2: New platform preparation completed |
0 days |
Fri 9/14/18 |
Fri 9/14/18 |
Import services routine |
52 days |
Fri 11/2/18 |
Mon 1/14/19 |
Evaluation of new clients |
3 days |
Thu 1/10/19 |
Mon 1/14/19 |
Milestone 4: Importing Data completed |
0 days |
Mon 1/14/19 |
Mon 1/14/19 |
Project closure |
26 days |
Tue 1/15/19 |
Tue 2/19/19 |
Milestone 5: project Hand over completed |
0 days |
Tue 2/19/19 |
Tue 2/19/19 |
Schedule and Budget
WBS |
Task Name |
Duration |
Start |
Finish |
Resource Names |
Cost |
1 |
TOSIG migration to cloud |
192 days |
Mon 5/28/18 |
Tue 2/19/19 |
$47,224.00 |
|
1.1 |
Project Planning |
42 days |
Mon 5/28/18 |
Tue 7/24/18 |
$12,880.00 |
|
1.1.1 |
Defining project objectives |
2 days |
Mon 5/28/18 |
Tue 5/29/18 |
Business analyst, Market analyst, Project Manager, System Analyst |
$800.00 |
1.1.2 |
Estimating Milestones |
3 days |
Wed 5/30/18 |
Fri 6/1/18 |
Business analyst, Market analyst, Project Manager, System Analyst |
$1,200.00 |
1.1.3 |
Developing migration plan |
2 days |
Mon 6/4/18 |
Tue 6/5/18 |
$480.00 |
|
1.1.3.1 |
Defining Methods |
2 days |
Mon 6/4/18 |
Tue 6/5/18 |
Business analyst, Market analyst, System Analyst |
$480.00 |
1.1.4 |
Defining Audit control requirements |
2 days |
Wed 6/6/18 |
Thu 6/7/18 |
Business analyst, Market analyst, System Analyst, Finance Manager, Project Manager |
$880.00 |
1.1.5 |
Quality Management plan definition |
9 days |
Fri 6/8/18 |
Wed 6/20/18 |
$2,160.00 |
|
1.1.5.1 |
Defining the risks |
3 days |
Fri 6/8/18 |
Tue 6/12/18 |
Finance Manager, Market analyst, Resource Manager, TOSIG Executive |
$600.00 |
1.1.5.2 |
Defying the plans for testing |
3 days |
Wed 6/13/18 |
Fri 6/15/18 |
Business analyst, Market analyst, System Analyst |
$720.00 |
1.1.5.3 |
Defining rollback plan |
3 days |
Mon 6/18/18 |
Wed 6/20/18 |
Business analyst, Cloud Service Provider, Resource Manager, System Analyst |
$840.00 |
1.1.6 |
Defining system run |
4 days |
Thu 6/21/18 |
Tue 6/26/18 |
Business analyst, Finance Manager, Project Manager, Resource Manager, System Analyst |
$1,760.00 |
1.1.7 |
Estimating budget of the project |
4 days |
Wed 6/27/18 |
Mon 7/2/18 |
Finance Manager, Project Manager, Resource Manager |
$1,120.00 |
1.1.8 |
HR planning |
6 days |
Tue 7/3/18 |
Tue 7/10/18 |
Finance Manager, Project Manager, Resource Manager |
$1,680.00 |
1.1.9 |
Executing Kick-off meeting |
10 days |
Wed 7/11/18 |
Tue 7/24/18 |
Finance Manager, Project Manager, Resource Manager |
$2,800.00 |
1.1.10 |
Milestone 1: Planning completed |
0 days |
Tue 7/24/18 |
Tue 7/24/18 |
$0.00 |
|
1.2 |
New platform preparation |
38 days |
Wed 7/25/18 |
Fri 9/14/18 |
$7,828.00 |
|
1.2.1 |
Acquiring API |
5 days |
Wed 7/25/18 |
Tue 7/31/18 |
IT technician, Programmer, Software[1], System Analyst |
$780.00 |
1.2.2 |
Reviewing API |
4 days |
Wed 8/1/18 |
Mon 8/6/18 |
IT technician, Programmer, Software[1], System Analyst, Cloud Service Provider |
$804.00 |
1.2.3 |
reviewing the existing system |
6 days |
Tue 8/7/18 |
Tue 8/14/18 |
IT technician, Programmer, Software[1], System Analyst |
$916.00 |
1.2.4 |
New customer relationship system |
2 days |
Wed 8/15/18 |
Thu 8/16/18 |
IT technician, Programmer, Software[1], System Analyst, Business analyst, Market analyst |
$692.00 |
1.2.5 |
Customer preferences identification |
5 days |
Fri 8/17/18 |
Thu 8/23/18 |
IT technician, Programmer, Software[1], System Analyst, Business analyst, Market analyst |
$1,580.00 |
1.2.6 |
Data migration |
3 days |
Fri 8/24/18 |
Tue 8/28/18 |
IT technician, Programmer, Software[1], System Analyst, Business analyst, Market analyst |
$988.00 |
1.2.7 |
Documenting detailed requirements |
7 days |
Wed 8/29/18 |
Thu 9/6/18 |
IT technician, Programmer, Software[1], System Analyst |
$1,052.00 |
1.2.8 |
Defining the business rules |
2 days |
Fri 9/7/18 |
Mon 9/10/18 |
IT technician, Programmer, Software[1], System Analyst |
$372.00 |
1.2.9 |
System Configuration |
4 days |
Tue 9/11/18 |
Fri 9/14/18 |
IT technician, Programmer, Software[1], System Analyst |
$644.00 |
1.2.10 |
Milestone 2: New platform preparation completed |
0 days |
Fri 9/14/18 |
Fri 9/14/18 |
$0.00 |
|
1.3 |
Existing platform and devices identification |
34 days |
Mon 9/17/18 |
Thu 11/1/18 |
$10,088.00 |
|
1.3.1 |
Analysing the specification of the devices |
6 days |
Mon 9/17/18 |
Mon 9/24/18 |
Business analyst, Cloud Service Provider, Finance Manager, Hardware[1], IT technician, Project Manager, Resource Manager, Software[1], System Analyst, TOSIG Executive |
$3,272.00 |
1.3.2 |
distributing new mobile devices |
8 days |
Tue 9/25/18 |
Thu 10/4/18 |
Business analyst, Cloud Service Provider, Finance Manager, Hardware[1], IT technician, Project Manager, Resource Manager, Software[1], System Analyst, TOSIG Executive |
$4,296.00 |
1.3.3 |
task review and quality assurance |
20 days |
Fri 10/5/18 |
Thu 11/1/18 |
$2,520.00 |
|
1.3.3.1 |
evaluating the data exports |
6 days |
Fri 10/5/18 |
Fri 10/12/18 |
Cloud Service Provider, Hardware[1], IT technician, Programmer, Software[1] |
$776.00 |
1.3.3.2 |
Analysing growth in the new customers’ list |
5 days |
Mon 10/15/18 |
Fri 10/19/18 |
Cloud Service Provider, Hardware[1], IT technician, Programmer, Software[1] |
$680.00 |
1.3.3.3 |
Milestone 3: Analysis of existing platform completed |
9 days |
Mon 10/22/18 |
Thu 11/1/18 |
Cloud Service Provider, Hardware[1], IT technician, Programmer, Software[1] |
$1,064.00 |
1.4 |
Import services routine |
52 days |
Fri 11/2/18 |
Mon 1/14/19 |
$10,852.00 |
|
1.4.1 |
Mapping trial data to API |
7 days |
Fri 11/2/18 |
Mon 11/12/18 |
IT technician, Programmer, System Analyst |
$952.00 |
1.4.2 |
Building routines |
4 days |
Tue 11/13/18 |
Fri 11/16/18 |
IT technician, Programmer, System Analyst, Hardware[1], Software[1] |
$744.00 |
1.4.3 |
Testing Routines |
5 days |
Mon 11/19/18 |
Fri 11/23/18 |
IT technician, Programmer, System Analyst, Hardware[1], Software[1] |
$880.00 |
1.4.4 |
Confirming Data Compliance |
8 days |
Mon 11/26/18 |
Wed 12/5/18 |
IT technician, Programmer, System Analyst |
$1,088.00 |
1.4.5 |
Data import |
5 days |
Thu 12/6/18 |
Wed 12/12/18 |
Cloud Service Provider, Hardware[1], Software[1] |
$400.00 |
1.4.6 |
Quality Assurance |
20 days |
Thu 12/13/18 |
Wed 1/9/19 |
$5,948.00 |
|
1.4.6.1 |
Staff Scheduling |
6 days |
Thu 12/13/18 |
Thu 12/20/18 |
Project Manager, Resource Manager, TOSIG Executive |
$1,440.00 |
1.4.6.2 |
Testing schedules |
7 days |
Fri 12/21/18 |
Mon 12/31/18 |
Project Manager, Resource Manager, TOSIG Executive, IT technician, Programmer, Software[1] |
$2,172.00 |
1.4.6.3 |
Test results review |
4 days |
Tue 1/1/19 |
Fri 1/4/19 |
Project Manager, Resource Manager, TOSIG Executive, System Analyst |
$1,280.00 |
1.4.6.4 |
Testing documentation |
3 days |
Mon 1/7/19 |
Wed 1/9/19 |
Project Manager, Resource Manager, TOSIG Executive, Business analyst, IT technician |
$1,056.00 |
1.4.7 |
Evaluation of new clients |
3 days |
Thu 1/10/19 |
Mon 1/14/19 |
$840.00 |
|
1.4.7.1 |
Reviewing QA |
3 days |
Thu 1/10/19 |
Mon 1/14/19 |
Finance Manager, Project Manager, System Analyst |
$840.00 |
1.4.7.2 |
Milestone 4: Importing Data completed |
0 days |
Mon 1/14/19 |
Mon 1/14/19 |
Finance Manager, Project Manager, System Analyst |
$0.00 |
1.5 |
Project closure |
26 days |
Tue 1/15/19 |
Tue 2/19/19 |
$5,576.00 |
|
1.5.1 |
Bugs and glitches fixing process definition |
5 days |
Tue 1/15/19 |
Mon 1/21/19 |
Cloud Service Provider, Hardware[1], IT technician, Programmer, Software[1], System Analyst |
$1,080.00 |
1.5.2 |
patching and maintaining schedule |
5 days |
Tue 1/22/19 |
Mon 1/28/19 |
Cloud Service Provider, Hardware[1], IT technician, Programmer, Software[1], System Analyst |
$1,080.00 |
1.5.3 |
Documentation |
6 days |
Tue 1/29/19 |
Tue 2/5/19 |
Cloud Service Provider, Hardware[1], IT technician, Programmer, Software[1], System Analyst |
$1,256.00 |
1.5.4 |
Manual Data Fixing |
4 days |
Wed 2/6/19 |
Mon 2/11/19 |
Cloud Service Provider, Hardware[1], IT technician, Programmer, Software[1], System Analyst |
$904.00 |
1.5.5 |
Project Hand Over |
6 days |
Tue 2/12/19 |
Tue 2/19/19 |
Cloud Service Provider, Hardware[1], IT technician, Programmer, Software[1], System Analyst |
$1,256.00 |
1.5.6 |
Milestone 5: project Hand over completed |
0 days |
Tue 2/19/19 |
Tue 2/19/19 |
$0.00 |
5.2 Risk Cause and its Effect
Category |
Risk |
Potential Cause(s) |
Potential Response(s) |
Response Strategy |
Design |
Infeasible design |
Waste of time and money |
Considering the needs and requirements while designing |
Exploit |
Resources and team |
Ineffective training |
Difficult quality trainings |
Better trainer and staffs |
Accept |
Change management |
Conflict among stakeholders |
Change request might came into light |
Proper and effective communication |
Reduce |
Cost management |
Project delivery can be costly |
Schedule escalation and improper estimation |
Effective cost management |
Avoid |
Scope |
Improper estimation |
Improper planning |
Proper business case |
Reduce |
5.2.1 Problem
5.2.2 Constraints
Conclusion
The proposed solution will allow TOSIG to effectively manage the new customers and following the project plan proposed in this report will be helpful in developing the project within the expected schedule and time. The proposed solution will be helpful in managing the project constraints and delivering the necessary outcomes and enhancing the performance of the organization.
Binder, J., 2016. Global project management: communication, collaboration and management across borders. Routledge.
Boud, D., Cohen, R. and Sampson, J. eds., 2014. Peer learning in higher education: Learning from and with each other. Routledge.
Fleming, Q.W. and Koppelman, J.M., 2016, December. Earned value project management. Project Management Institute.
Harrison, F. and Lock, D., 2017. Advanced project management: a structured approach. Routledge.
Heagney, J., 2016. Fundamentals of project management. AMACOM Div American Mgmt Assn.
Joseph. Phillips, P.M.P., Cbap, I. And Pmp, C., 2018. Pmp Project Management Professional Study Guide. Mcgraw-Hill Education.
Kerzner, H. and Kerzner, H.R., 2017. Project management: a systems approach to planning, scheduling, and controlling. John Wiley & Sons.
Kerzner, H., 2018. Project management best practices: Achieving global excellence. John Wiley & Sons.
Leach, L.P., 2014. Critical chain project management. Artech House.
Meredith, J.R., Shafer, S.M., Mantel Jr, S.J. and Sutton, M.M., 2016. Project management in practice. Wiley Global Education.
Mir, F.A. and Pinnington, A.H., 2014. Exploring the value of project management: linking project management performance and project success. International journal of project management, 32(2), pp.202-217.
Schwalbe, K., 2015. Information technology project management. Cengage Learning.
Turner, R., 2016. Gower handbook of project management. Routledge.
Verzuh, E., 2015. The fast forward MBA in project management. John Wiley & Sons.
Walker, A., 2015. Project management in construction. John Wiley & Sons.
Essay Writing Service Features
Our Experience
No matter how complex your assignment is, we can find the right professional for your specific task. Contact Essay is an essay writing company that hires only the smartest minds to help you with your projects. Our expertise allows us to provide students with high-quality academic writing, editing & proofreading services.Free Features
Free revision policy
$10Free bibliography & reference
$8Free title page
$8Free formatting
$8How Our Essay Writing Service Works
First, you will need to complete an order form. It's not difficult but, in case there is anything you find not to be clear, you may always call us so that we can guide you through it. On the order form, you will need to include some basic information concerning your order: subject, topic, number of pages, etc. We also encourage our clients to upload any relevant information or sources that will help.
Complete the order formOnce we have all the information and instructions that we need, we select the most suitable writer for your assignment. While everything seems to be clear, the writer, who has complete knowledge of the subject, may need clarification from you. It is at that point that you would receive a call or email from us.
Writer’s assignmentAs soon as the writer has finished, it will be delivered both to the website and to your email address so that you will not miss it. If your deadline is close at hand, we will place a call to you to make sure that you receive the paper on time.
Completing the order and download