Discuss About The Financial Intelligence For HR Professionals?
All the cost that is involved in the production process is known as manufacturing overhead. The manufacturing overhead is a wide term which comprises of various other factory cost also. However, the cost incurred with respect to direct material and direct labour is excluded from the manufacturing overhead. As there is no direct cost and it is a kind of overhead it is also known as indirect cost. Apart from the manufacturing cost there are also certain cost in relation to selling and distribution and various other general and administrative expenses that are not added to the product cost. These cost are shown in the income statement of the company as and when they are incurred. Such cost may include inspection cost, maintenance and repair of any asset, depreciation of an equipment, etc. Based on the general accounting principle, it is necessary to value the inventories and the cost of goods sold on the basis of direct cost and manufacturing overheads(Berman, Knight and Case, n.d.).
It is a common practise that the overhead has to be allocated and assigned to all the particular units if the company produces more than a single product. Manufacturing overhead is also distributed in this manner. For example, depreciation of the machine is calculated taking into consideration the value of the machinery, electricity is based on the units consumed and so on (Shim and Siegel, 2008).
There are a large number of ways by which the company can assign and allocate overhead. These methods are chosen by the companies depending on the market forces and the nature of operations the company carries out. These can be divided into two broad groups- conventional approach and activity based method (modern).
Let us now understand the concept of conventional approach first, in this method the manufacturing overhead was simply allocated on the basis of machine hours or the labour hours or any changes in the degree of the prime cost (Bruner, Eades and Schill, 2017). It is observed that the manufacturing overhead is increased with the decrease in the labour hours or machine hours. When the accountant of the company does not use different cost drivers but uses a single cost driver for all the overheads, then the rate calculated is said it be single blanket rate (Saltelli, Chan and Scott, 2008).
In the question, we are asked to calculate the cost per unit using the single blanket rate. The formula for calculating the single overhead rate is budgeted cost divided by the number of hours required for production. On calculating on the basis of labour hours we have found out that the manufacturing rate is 48/product unit. This means that for Fred it costs $96 (48*2) as he took two hours to complete one unit whereas for Martha it costs $144 (48*3) as it took three hours for him to complete one unit.
PARTICULARS |
FRED |
MARTHA |
Production units |
1000 |
5000 |
Direct materials |
40 |
60 |
Direct labours |
30 |
45 |
Manufacturing overheads |
96 |
144 |
Total Cost Per Unit |
166 |
249 |
Total Manufacturing Costs |
$8,16,000 |
|
Total Hours Required |
17000 hours |
|
(1000 units of Fred *2 + 5000 units of Martha*3 hours) |
||
Manufacturing Overhead Per Hour = |
Total Manufacturing Costs |
|
Total Hours |
||
Manufacturing Overhead Per Hour = |
816000 |
|
17000 |
In this question, we have been asked to calculate the cost involved in the cost activity based on different cost drivers. The word “cost activity” is a technical term used in cost accounting which can be explained as different types of activities that are involved in the manufacturing process. The cost activities together form a cost pool. Although these cost are not directly attributable to the product still they form a part of the cost. The other word used “cost driver” is a factor on which the cost of a activity is dependent (Taylor, 2008).
Following is the table that shows the rate of each activity as per the cost driver. For example, the expenses related to machine are $450000 which is divided by the budgeted cost driver of 9000 hours resulting in the rate of absorption $50/ machine hour. In the given table the rate of absorption has been calculated based on their respective cost drivers.
ACTIVITY |
COST($) |
COST DRIVER |
Budgeted Level |
RATE ($) |
Machine Related Costs |
450000 |
Machine hours |
9000 hours |
50/hour |
Setup & Inspection |
180000 |
Number of production runs |
40 runs |
4500/run |
Engineering |
90000 |
Engineering change orders |
100 change orders |
900/order |
Plant Related Costs |
96000 |
Square footage of space |
1920 sq. ft. |
50/sq.ft |
TOTAL |
816000 |
There is basically two approaches- conventional approach and activity based costing. The activity based costing is a practical as well as a logical approach in which the overhead is allocated in a more logical manner i.e. on the basis of the actual usage (Clarke and Clarke, 1990). This approach is adopted by the business having large scale of operations in which the there are a huge number of machineries and equipments used. Using a single blanket rate, is however very illogical as it does no determine the true overhead that should be allocated rather overhead is allocated on the basis of a one particular overhead rate. Therefore, the overhead allocated according to the single blanket rate is usually wrong. There is a direct relationship between the products and the activities undertaken and so the overhead calculated based on this approach is said to be appropriate. Hence, we can conclude that activity based costing is less arbitrary when compared to the conventional approach. As explained above, the activity based costing is used in the large businesses because there is a requirement of calculating true cost and also the proper classification of the cost has to be known (Fairhurst, 2015).
The price per unit of Fred was $199.20 whereas the price per unit of Martha was $298.8 when the firm was pricing its product @ 120% of the total manufacturing cost i.e. when it was selling its products at a margin of 20%. Earlier, the cost was calculated based on the conventional approach but after calculating the cost as per activity based costing, the product cost will be as follows (it will still price it product @120% of the manufacturing cost) (Galbraith, Downey and Kates, 2002)-
Price per unit of Fred = 120%*504.30= $605.16 per unit.
Price per unit of Martha= 120%*181.34= $217.60 per unit.
After this calculation is made , it has been observed that the profit of Fred has increased from $33.20 per unit to $100.86 per unit whereas the profit of Martha has fallen from $49.80 per unit to $36.28 per unit on adopting the ABC approach.
According to the conventional approach of costing, the overhead is allocated on the basis of the volume of production. These may be dependent on the volume of the production hours or even the machine hours consumed. Let us consider an example to understand this better, suppose there is a small manufacture whose volume of production is a little low but there is a huge expenditure of engineering cost, inspection cost, setup cost etc. If the manufacturer directly allocates the overhead on the basis of production hours then the result derived from it may be not reliable and may mislead them (Galbraith, Downey and Kates, 2002). This approach is usually adopted by the manufacturers whose scale of operations is simple and there are very less number of activities in which it is engaged. In such a situation where there is no complexity, a manufacturer may use the single blanket overhead rate for valuation. In case the manufacture is engaged in a number of complex activities, then it should not go for conventional approach rather separate cost drivers is developed in order to carry out proper valuation. If the overhead rate is wrongly charged from the customer then there may be arise in price which could harm the business, therefore the decision of the management in regards to selection of the method should be taken very carefully (TULSIAN, 2016). The conventional approach prevents the true and fair presentation of cost of resource consumed by the final product.
Conventional approach splits the total cost in two categories i.e. fixed cost as well as variable cost which is not considered realistic in the case when the business grows. This approach is not favourable for the manufacturing sectors as the valuation done by them is based on the degree of completion (Holland and Torregrosa, 2008).
The above advantages provide enough proof to say that the activity based costing is more logical and reliable than the conventional approach. There are also certain limitations of the activity based costing. They are-
Therefore, we can draw a conclusion that even though ABC system has many advantage it also has certain disadvantages. Now, it totally depends on the scale of operations as well as the nature of business to decide the compliance of various standards and principles. It is however important for every company whether small or large to give a clear picture of the costs and to charge a correct price from the customers as they are considered as the king of the business and no business can survive in the long run without their support.
References
Berman, K., Knight, J. and Case, J. (n.d.). Financial intelligence for HR professionals.
Bruner, R., Eades, K. and Schill, M. (2017). Case studies in finance. Dubuque, IA: McGraw-Hill Education.
Clarke, R. and Clarke, R. (1990). Strategic financial management. Homewood, Ill.: R.D. Irwin.
Fairhurst, D. (2015). Using Excel for Business Analysis A Guide to Financial Modelling Fundamenta. John Wiley & Sons.
Galbraith, J., Downey, D. and Kates, A. (2002). Designing dynamic organizations. New York: AMACOM.
Hassani, B. (2016). Scenario analysis in risk management. Cham: Springer International Publishing.
Holland, J. and Torregrosa, D. (2008). Capital budgeting. [Washington, D.C.]: Congress of the U.S., Congressional Budget Office.
Khan, M. and Jain, P. (2014). Financial management. New Delhi: McGraw Hill Education.
Palepu, K., Healy, P. and Peek, E. (2016). Business analysis and valuation. Andover, Hampshire, United Kingdom: Cengage Learning EMEA.
Phillips, J. (2014). Capm / pmp. New York: McGraw Hill.
Reilly, F. and Brown, K. (2012). Investment analysis & portfolio management. Mason, OH: South-Western Cengage Learning.
Saltelli, A., Chan, K. and Scott, E. (2008). Sensitivity analysis. Chichester: John Wiley & Sons, Ltd.
Saunders, A. and Cornett, M. (2017). Financial institutions management. New York: McGraw-Hill Education.
Shim, J. and Siegel, J. (2008). Financial management. Hauppauge, N.Y.: Barron’s Educational Series.
Taylor, S. (2008). Modelling financial time series. New Jersey: World Scientific.
TULSIAN, B. (2016). TULSIAN’S FINANCIAL MANAGEMENT FOR CA-IPC (GROUP-I). [S.l.]: S CHAND &
Essay Writing Service Features
Our Experience
No matter how complex your assignment is, we can find the right professional for your specific task. Contact Essay is an essay writing company that hires only the smartest minds to help you with your projects. Our expertise allows us to provide students with high-quality academic writing, editing & proofreading services.Free Features
Free revision policy
$10Free bibliography & reference
$8Free title page
$8Free formatting
$8How Our Essay Writing Service Works
First, you will need to complete an order form. It's not difficult but, in case there is anything you find not to be clear, you may always call us so that we can guide you through it. On the order form, you will need to include some basic information concerning your order: subject, topic, number of pages, etc. We also encourage our clients to upload any relevant information or sources that will help.
Complete the order formOnce we have all the information and instructions that we need, we select the most suitable writer for your assignment. While everything seems to be clear, the writer, who has complete knowledge of the subject, may need clarification from you. It is at that point that you would receive a call or email from us.
Writer’s assignmentAs soon as the writer has finished, it will be delivered both to the website and to your email address so that you will not miss it. If your deadline is close at hand, we will place a call to you to make sure that you receive the paper on time.
Completing the order and download