Assume that Bradley Lane has a sole income from Fisher Ltd in which he owns 12% of the ordinary share capital. Currently, Bradley has no savings.
In August, 2018, Fisher Ltd reported net profits after tax of $800,000 for the last financial year, 2017-18 (1 July, 2017 to 30 June, 2018), and announced it expects net profits after tax for the current financial year, 2018-19, to be 20% higher than last financial year’s figure. The company has a dividend payout ratio of 70%, which it plans to continue, and will pay the annual dividend for 2017-18 in late-September, 2018, and the dividend for 2018-19 in late-September, 2019.
In late-September, 2019, Bradley wishes to spend $95,000, which will include the cost of a new car. How much can he consume in late-September, 2018 if the capital market offers an interest rate of 10% per year?
Solution
PAT |
Dividend Payout Percentage |
Dividend paid |
Dividend Income of Bradley |
Interest Income |
Closing Income |
|
2017-18 |
800000 |
70% |
560000 |
67200 |
6720 |
73920 |
2018-19 |
960000 |
70% |
672000 |
80640 |
15456 |
96096 |
Amount required at the end of September, 2019 = $95000
Amount that will be available = $ 96096
Amount that can be used = $ 1096
QUESTION 1 continued
Speedy Delivery Ltd, which operates a courier service, requires a new van. It has received two quotes. Van A will cost $70,000 now, has a three year life and will cost $7,000 a year to operate. Van B will cost $90,000 now, has a four year life and will cost $9,000 a year to operate. The relevant discount rate is 6 per cent per annum. Ignoring depreciation and taxes, calculate the AEC for each. Which van do you recommend that Speedy Delivery Ltd buy, and state why?
Solution
or
AEC= NPV/ Project Life
Van A |
|||||
0 |
1 |
2 |
3 |
||
Cost |
-$ 70,000.00 |
||||
Inflows |
$ 7,000.00 |
$ 7,000.00 |
$ 7,000.00 |
||
DCF |
1.000 |
0.943 |
0.890 |
0.840 |
|
PV of Cash Flows |
-$ 70,000.00 |
$ 6,603.77 |
$ 6,229.98 |
$ 5,877.33 |
|
NPV |
-$ 51,288.92 |
||||
EAC |
-$ 17,096.31 |
||||
EAC= |
-$ 51,288.92/3 |
=-$17,096.31 |
|||
Van B |
|||||
0 |
1 |
2 |
3 |
4 |
|
Cost |
-$ 90,000.00 |
||||
Inflows |
$ 9,000.00 |
$ 9,000.00 |
$ 9,000.00 |
$ 9,000.00 |
|
DCF |
1.000 |
0.943 |
0.890 |
0.840 |
0.792 |
PV of Cash Flows |
-$ 90,000.00 |
$ 8,490.57 |
$ 8,009.97 |
$ 7,556.57 |
$ 7,128.84 |
NPV |
-$ 58,814.05 |
||||
EAC |
-$ 14,703.51 |
EAC= |
-$ 58,814.05/4 |
=-$14,703.51 |
Van B will be selected as it has less negative NPV
QUESTION 1 continued
Because of the drought, Farmers Bank Ltd has experienced large losses on its rural loan portfolio and is unable to meet its next two annual interest payments on its recent issue of unsecured notes. The notes are of $1,000 face value each, mature in September, 2023 and bear a yearly interest coupon payment of 13%.
The Bank paid the interest due this month (September, 2018), and following a meeting of creditors, arranged to defer payment of the next two interest coupons due in September, 2019 and September, 2020 respectively. Under the arrangement with creditors, the Bank will pay the remaining interest coupons (due in September, 2021, September, 2022 and September, 2023) on their due dates, and pay the two deferred coupons (without interest) along with the normal final interest payment and face value of the notes on the maturity date. Farmers Bank Ltd’s notes are now seen as risky, and require a 19% per annum return.
REQUIRED: Calculate the current value of each Farmers Bank unsecured note.
Solution:
Face Value |
1000 |
|||
Interest Rate |
13% |
|||
Required Rate |
19% |
|||
Year |
Interest |
PVF @ 19% |
PV |
|
1 |
2019 |
0.840 |
$ – |
|
2 |
2020 |
0.706 |
$ – |
|
3 |
2021 |
$ 130.00 |
0.593 |
$ 77.14 |
4 |
2022 |
$ 130.00 |
0.499 |
$ 64.83 |
5 |
2023 |
$ 390.00 |
0.419 |
$ 163.43 |
5 |
2023 |
$ 1,000.00 |
0.419 |
$ 419.05 |
$ 724.45 |
||||
Current Market Price of Unsecured Note |
$ 724.45 |
QUESTION 2
Ruth Bray is age 42 today and plans to retire on her 63rd birthday. With future inflation, Ruth estimates that she will require around $1,600,000 at age 63 to ensure that she will have a comfortable life in retirement. She is a single professional and believes that she can contribute $3,700 at the end of each month, starting in one month’s time and finishing on her 63rd birthday.
At the age of Bray will have $ 1,604,515.59 (Refer Appendix: Table 1).
There is a surplus of $ 4,515.59 as the required amount of funds at the age of 63 years is for only $ 1600000.
Monthly pension that Bray will receive will be = $ 26.44
Monthly Pension= Surplus/ Cumulative Factor of 288 terms i.e. 0.4%
= $4515.59/170.817
= $26.44
Workings:
Calculation of Number of terms=
No. of years = 87-63
= 24
No. of Months in each year = 24*12 = 288 Month
Calculation of monthly rate= 4.8/12
QUESTION 2 continued.
James and Mary Hall wish to borrow $750,000 to buy a home. The loan from the Federal Bank requires equal monthly repayments over 25 years, and carries an interest rate of 4.5% per annum, compounded monthly. The first repayment is due at the end of one month after the loan proceeds are received.
You are required to calculate:
Loan Amount |
750000 |
|
Loan Terms |
25 |
|
Interest p.a. |
4.50% |
|
Compounding |
Monthly |
|
Effective Annual Rate |
i=(1+(r/m))m−1 |
|
((1+(4.50/12))^12)-1 |
||
EAR= |
4.594% |
Refer Table 3
EMR= EAC/12 |
=4.594/12 |
0.383% |
Amount of Loan |
$ 750,000.00 |
|
Cumulative PVAF @ 0.383% for 300 terms (25 years * 12 Months |
300 Months |
178.196 |
Installment= Loan Amount/ PVAF |
$ 750000/4208.85 |
$ 4,208.85 |
Therefore, the amount of installment is $ 4208.85
QUESTION 2 continued.
Solution:
Refer Table 4
Opening Balance |
$ 750,000.00 |
Installment (1-12th ) |
$ 3,000.00 |
Installment (12-24th ) |
$ 3,500.00 |
25-300th |
$ Y |
Cumulative Factor @ 0383% from 25th to 300 term, taking 25th month is the first term. |
170.223 |
Therefore Y= |
$4,351.01 |
Solution:
Time take to repay the loan in installments of $ 4400 will be 23 years and 1 month (Refer Table 5) |
23.0833 years |
Therefore in terms of months and years, it will take 23 years and around 1 month.The answer is arrived by preparing the table at the discounting rate of 0.383%
At 277th month, the balance became zero.
Therefore, the total number of years= 277/12
= 23 years 1 mon
QUESTION 3
This question relates to alternative investment choice techniques
William Slater is considering the following cash flows for two mutually exclusive projects.
Year Cash Flows, Investment P ($) Cash Flows, Investment Q ($)
0 -60,000 -60,000
1 20,000 30,000
2 30,000 30,000
3 44,000 30,000
You are required to answer the following questions:
Total Cash Flows |
$ 94,000.00 |
Annual Cash Flows (20000+30000+44000)/3 |
$ 31,333.33 |
Project P |
|
Years |
Cash Flows |
0 |
-$ 60,000.00 |
1 |
$ 31,333.33 |
2 |
$ 31,333.33 |
3 |
$ 31,333.33 |
Years |
1.91 years |
Project Q |
|
Years |
Cash Flows |
0 |
-$ 60,000.00 |
1 |
$ 30,000.00 |
2 |
$ 30,000.00 |
3 |
$ 30,000.00 |
Years |
2 Years |
Decision: |
On the basis of payback period Project P will be selected under the assumption that project cash flows will occur evenly from year 1 to year 3. |
Project P |
||
Years |
Cash Flows |
Cumulative CF |
0 |
-$ 60,000.00 |
-$ 60,000.00 |
1 |
$ 20,000.00 |
-$ 40,000.00 |
2 |
$ 30,000.00 |
-$ 10,000.00 |
3 |
$ 44,000.00 |
$ 34,000.00 |
Years |
2.23 |
Project Q |
|
Years |
Cash Flows |
0 |
-$ 60,000.00 |
1 |
$ 30,000.00 |
2 |
$ 30,000.00 |
3 |
$ 30,000.00 |
Years |
2.00 |
Decision: |
On the basis of payback period Project Q will be selected under the assumption that project cash flows will occur at the end of each year from 1 to year 3. |
QUESTION 3 continued.
– The net present values of each project?
Project P |
||||
Years |
Cash Flows |
PVF @ 8% |
NPV |
|
0 |
-$ 60,000.00 |
1.000 |
-$ 60,000.00 |
|
1 |
$ 20,000.00 |
0.926 |
$ 18,518.52 |
|
2 |
$ 30,000.00 |
0.857 |
$ 25,720.16 |
|
3 |
$ 44,000.00 |
0.794 |
$ 34,928.62 |
|
$ 19,167.30 |
||||
Project Q |
||||
Years |
Cash Flows |
PVF @ 8% |
NPV |
|
0 |
-$ 60,000.00 |
1.000 |
-$ 60,000.00 |
|
1 |
$ 30,000.00 |
0.926 |
$ 27,777.78 |
|
2 |
$ 30,000.00 |
0.857 |
$ 25,720.16 |
|
3 |
$ 30,000.00 |
0.794 |
$ 23,814.97 |
|
$ 17,312.91 |
||||
Decision: |
On the basis of Net Present Value, Project P will be selected. |
– The present value (or profitability) indexes of each project?
Profitability Index= |
(NPV + Initial Investment)/ Initial Investment |
Or
Project P |
|||
Years |
Cash Flows |
PVF @ 8% |
NPV |
0 |
-$ 60,000.00 |
1.000 |
-$ 60,000.00 |
1 |
$ 20,000.00 |
0.926 |
$ 18,518.52 |
2 |
$ 30,000.00 |
0.857 |
$ 25,720.16 |
3 |
$ 44,000.00 |
0.794 |
$ 34,928.62 |
NPV |
$ 19,167.30 |
Profitability Index= (19167.3+60000)/60000
= 1.32
Project Q |
|||
Years |
Cash Flows |
PVF @ 8% |
NPV |
0 |
-$ 60,000.00 |
1.000 |
-$ 60,000.00 |
1 |
$ 30,000.00 |
0.926 |
$ 27,777.78 |
2 |
$ 30,000.00 |
0.857 |
$ 25,720.16 |
3 |
$ 30,000.00 |
0.794 |
$ 23,814.97 |
NPV |
$ 17,312.91 |
Profitability Index = (17312.91+60000)/60000
= 1.29
Decision: |
On the basis of Profitability Index, Project P will be selected. |
QUESTION 3 continued.
[NOTE: It is satisfactory if the approximate IRR is calculated for Investment P by trial and error, and stated as a percentage correct to the nearer whole number. The IRR for Investment Y, where the positive cash flows form an ordinary annuity, should be calculated as a percentage exactly, correct to 1 decimal place.]
Project P |
|||
Years |
Cash Flows |
||
0 |
-$ 60,000.00 |
||
1 |
$ 20,000.00 |
||
2 |
$ 30,000.00 |
||
3 |
$ 44,000.00 |
||
IRR |
22.74% |
||
Project Q |
|||
Years |
Cash Flows |
||
0 |
-$ 60,000.00 |
||
1 |
$ 30,000.00 |
||
2 |
$ 30,000.00 |
||
3 |
$ 30,000.00 |
||
IRR |
23.4% |
||
Decision: |
On the basis of IRR, Project Q will be selected. |
Project P |
|||||||
Year |
Cash Flows |
PVF @ 22% |
PV |
PVF @ 23% |
PV |
PVF @ 22.74% |
PV |
0 |
-60000 |
1.000 |
-60000.00 |
1.000 |
-60000.000 |
1.000 |
-60000.00 |
1 |
20000 |
0.820 |
16393.44 |
0.813 |
16260.163 |
0.815 |
16294.61 |
2 |
30000 |
0.672 |
20155.87 |
0.661 |
19829.467 |
0.664 |
19913.57 |
3 |
44000 |
0.551 |
24231.10 |
0.537 |
23644.892 |
0.541 |
23795.47 |
NPV |
600.962 |
-265.478 |
0.00 |
IRR= |
LDR+ |
NPV at LDR |
x (UDR-LDR) |
|
NPV at LDR- NPV at UDR |
||||
0.22 + |
600.962 |
*(.23-.22) |
||
335.484 |
||||
0.22 + |
1.79132906 |
* 0.01 |
||
IRR = 23.79%
Project Q |
|||||||
Year |
Cash Flows |
PVF @ 24% |
PV |
PVF @ 23% |
PV |
PVF @ 23.375% |
PV |
0 |
-60000 |
1.000 |
-60000.00 |
1.000 |
-60000.000 |
1.000 |
-60000.00 |
1 |
30000 |
0.806 |
24193.55 |
0.813 |
24390.244 |
0.811 |
24316.11 |
2 |
30000 |
0.650 |
19510.93 |
0.661 |
19829.467 |
0.657 |
19709.11 |
3 |
30000 |
0.524 |
15734.62 |
0.537 |
16121.518 |
0.532 |
15974.96 |
NPV |
-560.908 |
341.228 |
0.175 |
LDR+ |
NPV at LDR |
x (UDR-LDR) |
||
NPV at LDR- NPV at UDR |
||||
0.23 + |
560.908 |
*(.24-.23) |
||
902.136 |
||||
0.23 + |
0.6217551 |
* 0.01 |
IRR = 23.62%
CROSSOVER POINT |
|||
Project P |
|||
IRR |
23% |
0% |
18.32% |
NPV |
0.00 |
34000 |
4893.17 |
Project Q |
|||
IRR |
23% |
0% |
18.32% |
NPV |
0.00 |
30000 |
4893.23 |
Cross over point = 18.32%
Graphical presentation of cross over point
Solution:
The evaluation of two mutually exclusive projects i.e. Project P and Project Q, which are proposed to be undertaken by William Slater is done using various techniques of capital budgeting. Capital budgeting decisions require significant evaluation as they involve investment of large sums of funds and also they take some period of time to generate returns (Bennouna, Meredith & Marchant, 2010). The basic feature of projects that are mutually exclusive in nature is that only one of such projects can only be undertaken and not all the projects at a time due to limited availability of funds (Finance Management, 2018). In order to select the best suitable project, application of following capital budgeting techniques has been made:
Payback period: It is the length of time that will be taken by a project to recover its cost of initial outlay. When it is assumed that the cash flows in respect of all the projects will occur evenly, it is observed that project P is better than Q because P has a shorter payback period than Q. However, with the change in assumption that cash flows will occur only at the end of each year, the decision on the payback period basis changed. Now, project Q is found to be better than P due to Q’s shorter length of payback term.
Net Present Value: On the basis of NPV, Project P must be selected as it has higher NPV than that of Project Q as higher NPV shows higher profitability of the project (Management Study Guide, 2018).
Profitability Index: On the basis of Profitability Index, Project P will be selected because it has higher PI.
Internal Rate of Return: On the basis of IRR, Project Q will be selected as it has higher IRR and therefore it has the capacity to offer higher returns to the project owner (Management Study Guide, 2018).
QUESTION 4
This question relates to capital budgeting.
Bayside Ferries Ltd is considering the purchase in September, 2018 of two new small hydrofoils costing $480,000 each, which it will fully finance with a fixed interest loan of 9% per annum, with interest paid monthly and the principal repaid at the end of 4 years. The hydrofoils will be used in the company’s passenger transport business.
The two new hydrofoils will replace three existing steam ferries and will permit the company to reduce its energy and labour costs by a total of $160,000 a year, over the next 4 years. [Assume these savings are realized at the end of each year.]
The new hydrofoils may be depreciated for tax purposes by the straight-line method to zero over the next 4 years. The company thinks that it can sell the hydrofoils at the end of 4 years for $75,000 each.
The three old ferries being replaced were bought two years ago for $300,000 each, with a then life expectancy of 6 years, and are being depreciated by the straight-line method to zero over 6 years. If the company proceeds with the above purchase, the old ferries will be sold in September, 2018 for $170,000 each.
This is not the first time that the company has considered this purchase and replacement. Twelve months ago, the company engaged Sea Travel Consultants, at a fee of $25,000 paid in advance, to conduct a feasibility study on savings strategies and Sea Travel made the above recommendations. At the time, Bayside Ferries Ltd did not proceed with the recommended strategy, but is now reconsidering the proposal.
Bayside Ferries Ltd further estimates that it will have to spend tax-deductible amounts of $30,000 in 2 years’ time and $40,000 in 3 years’ time overhauling the hydrofoils.
It will also require additions to current assets of $30,000 at the start of the hydrofoils project, which will be fully recoverable at the end of the fourth year after purchase.
Bayside Ferries Ltd’s cost of capital is 11%. The tax rate is 30%. Tax is paid in the year in which earnings are received.
[HINT: As shown in the text-book, it is recommended that for each year you calculate the tax effect first, then identify the cash flows, then calculate the overall net present value. Finally, make your recommendation.]
Opening Balance |
Interest @ 9% p.a. |
Total Interest |
Interest Per year |
480000 |
3600 |
172800 |
43200 |
480000 |
3600 |
172800 |
43200 |
345600 |
86400 |
Reduction in labor cost |
Per Year |
160000 |
||
Total |
||||
Depreciation on New Machine |
Cost |
480000 |
480000 |
|
Less Residual Value |
75000 |
75000 |
||
405000 |
405000 |
|||
Useful life |
4 |
4 |
||
Depreciation per annum |
101250 |
101250 |
202500 |
Old Berries Cost |
300000 |
300000 |
300000 |
900000 |
Useful life |
6 |
6 |
6 |
|
Depreciation per year |
50000 |
50000 |
50000 |
150000 |
Depreciation for 2 years |
100000 |
100000 |
100000 |
300000 |
WDV at the end of 2nd year |
200000 |
200000 |
200000 |
600000 |
Initial Investment |
$ 960,000.00 |
Working Capital |
$ 30,000.00 |
Total Initial Outlay |
$ 990,000.00 |
Years |
0 |
1 |
2 |
3 |
4 |
Total Initial Outlay |
-$ 990,000.00 |
||||
Sale of Old Berries |
$ 483,000.00 |
||||
Decrease In Labor Cost |
$ 160,000.00 |
$ 160,000.00 |
$ 160,000.00 |
$ 160,000.00 |
|
Incremental Depreciation |
-$ 52,500.00 |
-$ 52,500.00 |
-$ 52,500.00 |
-$ 52,500.00 |
|
Interest on loan |
-$ 86,400.00 |
-$ 86,400.00 |
-$ 86,400.00 |
-$ 86,400.00 |
|
Overhauling Expenditure |
$ – |
-$ 30,000.00 |
-$ 40,000.00 |
$ – |
|
Net Cash Flows |
$ 21,100.00 |
-$ 8,900.00 |
-$ 18,900.00 |
$ 21,100.00 |
|
Add Salvage Value |
$ 150,000.00 |
||||
Less Tax |
-$ 6,330.00 |
$ 2,670.00 |
$ 5,670.00 |
-$ 51,330.00 |
|
Cash Flows After Tax |
$ 14,770.00 |
-$ 6,230.00 |
-$ 13,230.00 |
$ 119,770.00 |
|
Add Incremental Depreciation |
$ 52,500.00 |
$ 52,500.00 |
$ 52,500.00 |
$ 52,500.00 |
|
CFAT |
$ 67,270.00 |
$ 46,270.00 |
$ 39,270.00 |
$ 172,270.00 |
|
Less Working Capital Recovered |
-$ 30,000.00 |
||||
Total Cash Flows |
-$ 507,000.00 |
$ 67,270.00 |
$ 46,270.00 |
$ 39,270.00 |
$ 142,270.00 |
PVF @ 11% |
1.000 |
0.901 |
0.812 |
0.731 |
0.659 |
PV |
-$ 507,000.00 |
$ 60,603.60 |
$ 37,553.77 |
$ 28,713.89 |
$ 93,717.66 |
NPV |
-$ 286,411.09 |
References:
Bennouna, K., Meredith, G. G., & Marchant, T. (2010). Improved capital budgeting decision making: evidence from Canada. Management decision, 48(2), 225-247.
Finance Management. (2018). Why Net Present Value is the Best Measure for Investment Appraisal? Retrieved from: https://efinancemanagement.com/investment-decisions/why-net-present-value-is-the-best-measure-for-investment-appraisal
Management Study Guide. (2018). Problems With Using Internal Rate of Return (IRR) for Investment Decision Making. Retrieved from: https://www.managementstudyguide.com/problems-with-using-internal-rate-of-return.htm
Management Study Guide. (2018). What is Internal Rate of Return (IRR) ? Retrieved from: https://www.managementstudyguide.com/internal-rate-of-return.htm
Essay Writing Service Features
Our Experience
No matter how complex your assignment is, we can find the right professional for your specific task. Contact Essay is an essay writing company that hires only the smartest minds to help you with your projects. Our expertise allows us to provide students with high-quality academic writing, editing & proofreading services.Free Features
Free revision policy
$10Free bibliography & reference
$8Free title page
$8Free formatting
$8How Our Essay Writing Service Works
First, you will need to complete an order form. It's not difficult but, in case there is anything you find not to be clear, you may always call us so that we can guide you through it. On the order form, you will need to include some basic information concerning your order: subject, topic, number of pages, etc. We also encourage our clients to upload any relevant information or sources that will help.
Complete the order formOnce we have all the information and instructions that we need, we select the most suitable writer for your assignment. While everything seems to be clear, the writer, who has complete knowledge of the subject, may need clarification from you. It is at that point that you would receive a call or email from us.
Writer’s assignmentAs soon as the writer has finished, it will be delivered both to the website and to your email address so that you will not miss it. If your deadline is close at hand, we will place a call to you to make sure that you receive the paper on time.
Completing the order and download