Describe about the global retail solutions group?
The Global Retail Solutions Group (GRS) requires the software which will help for point of the sale and also for control system of stock for DSE for the outlets which are in form of retail across the areas of Australia (as we are analyzing GRS impact in the area of Australia). This system of transaction processing will be used for applying the modern code of RFID which is scanning at some point of sale and it will give control over automatic inventory. The system which we are using should also be competent enough in relieving the store personnel from their task which are monotonous for generating the performance and sales reports as it needed by the head office of the Australia. We did the investigation based on the requirements and we can state that based on this analysis we are giving this plan of the project which contains all milestones, sheet of the resource and project cost and schedule of the project which is required to execute it.
Below are the objectives which are used for creating the transaction processing system:
Below we have listed all the major milestones which are needed for the system project of transaction processing. In the below list may we have not included the milestones which are smaller and didn’t have much impact but we have considered them in Work Breakdown Structure and Schedule of the project so that those can be tracked and be noticed. The dates which we have used is total based on assumption on the time which we think the project milestone should get to perform better.
Milestone |
Date |
Transaction Processor of project |
03/25/15 |
File for Inventory and Price and inventory |
09/10/15 |
Inventory management of the project |
10/10/15 |
Communications done in the project |
11/26/15 |
Documentation done for the project |
12/26/15 |
Alpha test which was done on the project |
01/30/16 |
Beta Test which was done on project |
04/01/16 |
The system project of transaction processing will contain work sets under work breakdown structure which will not exceed 4 hours of work in the project. The work sets which are used will be developed by the close collaboration among the project team members and the stakeholders. Without their support and input we cant do it, it also need input from the functional managers and all researches happened in the past projects. With all these data we can get better idea and help in executing and planning the current project.
In the Dictionary of the Work Breakdown Structure it will describe all the work sets which are required in the system projects of transaction processing. These all definitions which are there in WBs will include all resources details, task details and its timeline and all the project deliverables. All of the work set which is used in the project and in Work Breakdown Structure is defined in the dictionary of WBS. This will help in planning of the resource in project, completion of task and also making sure that all the deliverables which are handing to the customer should meet project requirements and standards.
WBS |
Task of the project |
1.1DSE |
Transaction processor of the project |
1.1.1DSE |
User Interface of the project |
1.1.2DSE |
Peripheral Interface of project |
1.1.3DSE |
Price Look-up |
1.1.4DSE |
Order Control of project |
1.1.5DSE |
Resolution of the Payment |
1.1.6DSE |
Resolution of the Transaction |
1.1.7DSE |
Printing the Receipt which are used in project |
1.2DSE |
Files for inventory and Price and inventory |
1.2.1DSE |
Design of the Database |
1.2.2DSE |
Access library of the Database |
1.2.3DSE |
Maintenance library of the Database |
1.2.4DSE |
Report Generation of the Database |
1.3DSE |
Inventory management of the project |
1.3.1DSE |
Report of the Daily Status |
1.3.2DSE |
Report of the Item History |
1.3.3DSE |
Generation of the Order |
1.3.4DSE |
Communication of the Order |
1.3.5DSE |
Processor of the Receipt |
1.3.6DSE |
Update the project Inventory |
1.4DSE |
Communications of the project |
1.4.1DSE |
Banking Network Interface |
1.4.2DSE |
State Network Interface |
1.4.3DSE |
Communications Command Interpreter |
1.4.4DSE |
Report Generator |
1.5DSE |
Documentation |
1.5.1DSE |
Help for Transaction Processor of the project |
1.5.2DSE |
Help for Inventory and Price Modules of the project |
1.5.3DSE |
Help for Management of the Inventory of project |
1.5.4DSE |
Help for Communications of the project |
1.6DSE |
Alpha test of the project |
1.6.1DSE |
Test based on the project |
1.6.2DSE |
Support of the project Developer |
1.7DSE |
Beta Test of the project |
1.8DSE |
Start roll-out of the project |
Management Plan of Communications will be established the project framework for the communications to the project which we have used. It will serve as the Key point for the communications of the project during the life cycle of the project and it will be reorganized as the project communication has some changes of the requirements. This plan of the project will recognizes and it will be describes the major roles of the members of the project team as it will relate to the communications of the project. The requirements of the projects will be documented in below Matrix of Communications. The Matrix of the Communications will be observed as guide for what the information to be communicate for the project, who is to do communicating of the project, when to be communicate about the project, and to whom to be communicate at the time of issues and problems.
Type of Communication |
Description about the communication |
Frequency |
Format |
Participants/ Distribution |
Deliverable |
Report which contains the Weekly Status |
Summary on the Email about the status of the project |
Weekly basis |
Email format |
Stakeholders, Project team and Project Sponsor |
Report of the Status |
Project Team Meeting on Weekly basis |
Review Meeting which contains the status of the project |
Weekly basis |
In Person format |
Team of the Project |
Action Register will be Updated |
Review of the Monthly project Report (PMR) |
Provide current status of the project and metrics to sponsors and team of the project |
Monthly basis |
In Person format |
Stakeholders, team and Sponsors of the Project |
Presentation based on Metric and Status |
Review of Technical Design Document of the Project |
Review the technical designs of the project or work which are associated with the project |
As Needed |
In Person format |
Team of the Project |
Package of the Technical Design Document |
Name |
Title of the project |
Email of the project |
Office Phone number |
Cell Phone number |
Joni Parker |
Sponsor of the Project |
xxx-xxx-xxxx |
xxx-xxx-xxxx |
|
Mark Brown |
Manager of the Project |
xxx-xxx-xxxx |
xxx-xxx-xxxx |
|
Richard |
Programmer of the project |
xxx-xxx-xxxx |
xxx-xxx-xxxx |
|
Elizabeth |
Programmer of the project |
xxx-xxx-xxxx |
xxx-xxx-xxxx |
|
Harry |
Programmer of the project |
xxx-xxx-xxxx |
xxx-xxx-xxxx |
|
Sam |
Programmer of the project |
xxx-xxx-xxxx |
xxx-xxx-xxxx |
|
Ellie |
Programmer of the project |
xxx-xxx-xxxx |
xxx-xxx-xxxx |
|
Jenny |
Programmer of the project |
xxx-xxx-xxxx |
xxx-xxx-xxxx |
|
Barry |
Test Engineer of the project |
xxx-xxx-xxxx |
xxx-xxx-xxxx |
There are various resources of the project needed to develop the whole application of the project except Manager of the Project. Below we have provided list of the key resources which are needed to develop the project software with the project Cost per hour.
Resource Name |
Initials |
Max. Units |
Std. Rate |
Richard |
R |
100% |
$200.00/hr |
Elizabeth |
E |
100% |
$100.00/hr |
Harry |
H |
100% |
$100.00/hr |
Sam |
S |
100% |
$200.00/hr |
Ellie |
E |
100% |
$90.00/hr |
Jenny |
J |
100% |
$100.00/hr |
Barry |
B |
100% |
$100.00/hr |
Other Internal resource |
O |
100% |
$120.00/hr |
The Project Cost is considered as the major aspects for project. Below we are providing the development cost of the project for each of the milestone of the project; these are the approximate values which we think it should include in the project:
Task Name |
Cost |
Transaction processor of the project |
$33,000.00 |
File for inventory and Price of the project |
$42,340.00 |
Management of the Inventory of the project |
$22,000.00 |
Communications of the project |
$26,250.00 |
Documentation involved in the project |
$19,450.00 |
Alpha test based on the project |
$39,842.00 |
Beta Test based on the project |
$0.00 |
Total Cost involved in the project |
182,882.00 |
As per the current scenario of the company which we selected we have analyze thoroughly and we can find below the risk which can be proceed during the development of the software of the project:
Building the diagram of the network also termed as the logic diagram, is the great way for initializing to visualize and to understand how the project has to be preceded. These will use in the telecommunication of the computers which will used to draw the graphical chart of the network. Here we are attaching the Network Diagram and Gantt chart which is required in this project which contains all relevant data. If you need any other content in this document then feel to add and comment so that we can incorporate the changes which are need in this project.
Please find attached the Diagram of Network.
The Gantt chart is mainly used for the project management; this is considered as most of the useful and popular ways which will show the activities which are displayed against the time. In chart it will display on the left side where there are list of activities and on top of the chart there is a time scale which is suitable for all of the activities. Each of these activities will be represented as a bar. Please find attached Gantt chart.
References:
1. GRS Team, 2012, A Plan for Restructuring and Updating the General Records Schedules, https://www.archives.gov/records-mgmt/grs/plan-2012.pdf
2. J. Phillips, 2015, Work Breakdown Structure, https://www.projectsmart.co.uk/work-breakdown-structure.php
3. NetMBA, 2010, Work Breakdown Structure, https://www.netmba.com/operations/project/wbs/
4. Mark, 2015, WORK BREAKDOWN STRUTURE (WBS), https://www.projectmanagementdocs.com/project-planning-templates/work-breakdown-structure-wbs.html
5. Robert, 2011, Research Office Implementation Communication Plan, https://www.csu.edu.au/__data/assets/pdf_file/0005/187430/Research-Office-Communications-Plan.pdf
6. Friendly, 2006, Project Communication Plan, https://www.pma.doit.wisc.edu/plan/3-1/what.html
7. Oracle, 2011, PROJECT RESOURCE MANAGEMENT, https://www.oracle.com/us/products/applications/057027.pdf
8. NetSuite, 2015, Resource Management, https://www.netsuite.com/portal/products/netsuite/psa/resource-management.shtml
9. John Reh, 2011, Project management 101, https://management.about.com/cs/projectmanagement/a/PM101b.htm
10. Cost management, 2004, Cost Management Plan, https://www2.parkland.edu/businesstraining/documents/CostMgmtPlan.pdf
11. Walter, 2014, Cost Management, https://www.definedlogic.com/blog/archive/cost-management-determining-project-cost-performance/
12. Tedero, 2011, Project Cost Management, https://www.cram.com/flashcards/pmbok-chapter-7-project-cost-management-1846193
13. Bart Jutte, 2015, 10 Golden Rules of Project Risk Management, https://www.projectsmart.co.uk/10-golden-rules-of-project-risk-management.php
14. Clean Air, 2015, Risk Management Plan (RMP) Rule, https://www2.epa.gov/rmp
15. Karol, 2011, What is gantt chart, https://www.gantt.com/
16. James, 2015, Gantt Charts, https://www.mindtools.com/pages/article/newPPM_03.htm
Essay Writing Service Features
Our Experience
No matter how complex your assignment is, we can find the right professional for your specific task. Contact Essay is an essay writing company that hires only the smartest minds to help you with your projects. Our expertise allows us to provide students with high-quality academic writing, editing & proofreading services.Free Features
Free revision policy
$10Free bibliography & reference
$8Free title page
$8Free formatting
$8How Our Essay Writing Service Works
First, you will need to complete an order form. It's not difficult but, in case there is anything you find not to be clear, you may always call us so that we can guide you through it. On the order form, you will need to include some basic information concerning your order: subject, topic, number of pages, etc. We also encourage our clients to upload any relevant information or sources that will help.
Complete the order formOnce we have all the information and instructions that we need, we select the most suitable writer for your assignment. While everything seems to be clear, the writer, who has complete knowledge of the subject, may need clarification from you. It is at that point that you would receive a call or email from us.
Writer’s assignmentAs soon as the writer has finished, it will be delivered both to the website and to your email address so that you will not miss it. If your deadline is close at hand, we will place a call to you to make sure that you receive the paper on time.
Completing the order and download