A construction company which is a small to medium size is working on WSI Blue mountains project. At present, this company is working on projects like commercial and residential construction, is presenting a quality management plan for the WSI Blue mountains college, for building the facilities like beauty therapy, complementary health classrooms and offices. Annually it has a turnover ranging more the $24 million.
This project aims to build a new facility for Beauty Therapy and Complementary Health Classrooms and Offices, in Western Sydney Institute (WSI). TAFE WSI is a provider of vocational education and training, to shape the future of student, community and industry. Perumal Pedavoli Architects (PPA) organization has won the tender for this project. It offers services like Civil, Structural, Mechanical and Electrical Construction. This company has a well-structured system and also has full third party certification for its Quality Management System, under ISO AS/NZS 9001:2008 standards, along with Davis Langdon Certification Services. It’s designed management and service framework ensures to reduce the risks during project management (Pp-a.com.au, 2018). The Australian Standards are recommended for this project. The project will be equipped with electrical services such as lighting, fire detection, power communication, security; hydraulic services, Mechanical Plans, Structural Plans, Arch Plans and civil plans. This project will help to furnish the needs of beauty and health facility, from its service which the students can get benefitted. The purpose of developing is to increase the capacity and facilities of wellness. It can be an opportunity for delivering training on health and beauty. The new facilities will contain related training spaces and Student Support Services. The Beauty Therapy facility will provide the training for the services like hand and foot therapies, waxing, electrical treatment, eye treatments, massage, nail enhancements, stone therapy, epilation and micro-dermabrasion. Whereas the complementary Therapies offer training for the treatments like massage, aromatherapy, stone therapy, remedial massage, advanced aromatherapy, advanced reflexology, reflexology, and head massage of different styles. It has the capacity to accommodate nearly 1000 students. The project will also provide lecture rooms, Teachers office, for providing student support services, for the Blue Mountains college. The Quality Management Plan is developed to ensure the following:
This project needs architects, electrical engineers, civil engineers, Quality management team, policy maintenance team, Project Manager, Steering Committee, Partner operations team and laborers.
Quality Policy
Generally, the Australian standards are followed for this project, where the following quality policy standards are adopted:
The company policies include:
The following are the major quality procedures extracted from ISO 9001:2008 (Leanman, 2018):
According to AS/NZS ISO 9001 Quality management systems – Requirements, the audit plan includes (Quality Management Systems Guidelines for Construction, 2013):
It is the internal and certification audits which gives the assurance for the customer that they can achieve the desired performance level, without extensive external auditing.
Generally, the audits process includes:
This refers to a process which decreases the budget of the project, with the help of several methods and replaces an alternative material that helps to decrease the project cost. The cost will be controlled based on previous construction information, discarding additional equipment and by decreasing material wastage and by replacement of alternative material preserving its quality (Bhimrao Kokate and Darade, 2018).
The client variation register contains specific matters which could result in adjustment of amount the Principal has to pay the Company.
Project: Construction of beauty therapy and Complementary Health Classrooms and Offices
Project Number: XYZ
Variation number |
Description |
Claim Value |
Date submitted |
Response Date |
Agreed date |
Agreed value |
1. |
The required amount of materials will be purchased and managed. |
12-05-2018 |
1-08-2018 |
1-07-2018 |
– |
|
2. |
Extra cranes will be discarded and the crane will be scheduled to meet the needs of construction. |
12-05-2018 |
2-08-2018 |
2-07-2018 |
– |
As per ISO 9001:2008, document control (4.2.3) refers to controlling both the approval and re-approval of procedures before the problem occurs. It makes sure to display the status of the current revision (Leanman, 2018).
According to Clause 4.r4, here there are no requirements for Design / drawing control (Sai Global, 2018). The drawings are used as instructions. This is to ensure that the structure is completed based on the provided measurements and is located at the right position.
The site instruction register helps to keep track of all the site instructions, which are raised for the project. The head contractor sets the directives for the contractors who are currently working on a project.
The required information is collected from the suppliers, for shortlisting potential suppliers. This helps to compare the businesses which offer the required products ad services that are needed to complete the project.
Based on ISO standards, an effective plan will be designed to test the designed plan. The following will be carried out:
It refers to a procedure which makes sure that the non-conforming product isn’t utilized and the action is taken. The quality audit team maintains non-conformance report. Project Design Form and Compliance Checklist; and Project Construction Form and Compliance Checklist help to find non-conformance in the project.
The Extension of time (EOT) is provided if required and the reason for the extension will be mentioned, so that the other processes are managed well without any harm.
The internal procedures will be documented clearly. This will be helpful even for future assessment.
From ISO 9001:2008, the Control of Records (4.2.4) will be used for filing. This refers to a procedure for controlling the storage, identification, retrieval, protection, retention and record disposal.
References
Bhimrao Kokate, P. and Darade, M. (2018). Cost Control Techniques for Construction Project. International Research Journal of Engineering and Technology (IRJET), 5(6).
Leanman, T. (2018). ISO 9001:2008 Procedures—6 Mandatory Procedures. [online] ToughNickel. Available at: https://toughnickel.com/business/ISO-9001-Procedures [Accessed 13 Aug. 2018].
Pp-a.com.au. (2018). Perumal Pedavoli Architects. [online] Available at: https://www.pp-a.com.au/quality-accreditation/ [Accessed 14 Aug. 2018].
Quality Management Systems Guidelines for Construction. (2013). NSW Government.
Sai Global. (2018). Quality system guidelines Guide to AS/NZS ISO 9001, AS/NZS ISO 9002, and AS/NZS ISO 9003 for construction. [online] Available at: https://infostore.saiglobal.com/en-au/standards/as-nzs-3905-2-1997-375473/ [Accessed 13 Aug. 2018].
Essay Writing Service Features
Our Experience
No matter how complex your assignment is, we can find the right professional for your specific task. Contact Essay is an essay writing company that hires only the smartest minds to help you with your projects. Our expertise allows us to provide students with high-quality academic writing, editing & proofreading services.Free Features
Free revision policy
$10Free bibliography & reference
$8Free title page
$8Free formatting
$8How Our Essay Writing Service Works
First, you will need to complete an order form. It's not difficult but, in case there is anything you find not to be clear, you may always call us so that we can guide you through it. On the order form, you will need to include some basic information concerning your order: subject, topic, number of pages, etc. We also encourage our clients to upload any relevant information or sources that will help.
Complete the order formOnce we have all the information and instructions that we need, we select the most suitable writer for your assignment. While everything seems to be clear, the writer, who has complete knowledge of the subject, may need clarification from you. It is at that point that you would receive a call or email from us.
Writer’s assignmentAs soon as the writer has finished, it will be delivered both to the website and to your email address so that you will not miss it. If your deadline is close at hand, we will place a call to you to make sure that you receive the paper on time.
Completing the order and download