High Quality Institute (HQI) is an educational firm that provides the students with many different courses in the field of Information Technology. With the advancement of technology and increase in the number of students, HQI has decided to implement a new technological system called Technical and Learning System (TLS). This will comprise of a learning system for undergraduate and postgraduate courses and there will be many features and functionalities that will be implemented in the system.
The primary aim of the project is to provide the students with an advanced and automated teaching and learning system with improved quality and streamlining of activities.
The project will have the following objectives:
The report covers the functional and non-functional requirements of the project along with a Work Breakdown Structure (WBS) supported by the table describing project activities and their duration. Project budget, poster and recommendations have also been covered in the report.
WBS |
Task Name |
Duration |
Predecessors |
1 |
High Quality Institute – Teaching and Learning System (TLS) |
89 days |
|
1.1 |
TLS Initiation |
5 days |
|
1.1.1 |
Feasibility Analysis – Operational Aspect |
2 days |
|
1.1.2 |
Feasibility Analysis – Technical Aspect |
2 days |
|
1.1.3 |
Feasibility Analysis – Economical and Environmental Aspect |
2 days |
|
1.1.4 |
Results compilation and project chartering |
4 days |
|
1.1.5 |
Charter submission and project startup |
1 day |
3,4,5,6 |
1.1.6 |
Milestone One: Project Charter |
0 days |
7 |
1.2 |
TLS Planning |
11 days |
|
1.2.1 |
Scope determination and Management |
5 days |
8 |
1.2.2 |
Project Estimates – Budget, Schedule and Risks |
8 days |
8 |
1.2.3 |
Team planning, allocation and communication |
5 days |
8 |
1.2.4 |
Project approach and methodology |
3 days |
10,11,12 |
1.2.5 |
Milestone Two: Project Plan Document |
0 days |
13 |
1.3 |
TLS Execution |
53 days |
|
1.3.1 |
UI /UX aspects for undergraduate and postgraduate systems |
10 days |
14 |
1.3.2 |
Design diagrams and system behavior |
6 days |
16 |
1.3.3 |
System development – Source code |
31 days |
17 |
1.3.4 |
Unit testing of the two sub-systems |
5 days |
18 |
1.3.5 |
Review and release to the test team |
1 day |
19 |
1.3.6 |
Milestone Three: Developed System |
0 days |
20 |
1.4 |
TLS Testing & Implementation |
11 days |
|
1.4.1 |
System Integration |
4 days |
21 |
1.4.2 |
System, Regression, Security and Performance Testing |
6 days |
21 |
1.4.3 |
Implementation and management of changes |
5 days |
23,24 |
1.4.4 |
Milestone Four: Test Report |
0 days |
25 |
1.5 |
Closure – Project Phase 5 |
9 days |
|
1.5.1 |
User Trainings |
4 days |
26 |
1.5.2 |
Acceptance and Lessons Learned |
2 days |
26 |
1.5.3 |
System Documentation |
7 days |
26 |
1.5.4 |
Submission of the closure report |
2 days |
28,29,30 |
1.5.5 |
Milestone Five: Closure Report |
0 days |
31 |
The Work Breakdown Structure and its supported table displayed above illustrate the project tasks and activities and the duration that will be required for the accomplishment of every task. The project will be completed in five phases as displayed in the WBS above. TLS has been kept at the top most level followed by the five phases and then comes the sub-activities that will be covered under every phase. The five phases that have been displayed above include initiation, planning, execution, testing & implementation and closure (Miyahara, 2011).
The 3-level WBS shows the project activities in a hierarchical manner so that the project tasks and activities are completed and accomplished with much ease and the determination of project estimates is also easier (Hans, 2013).
The critical tasks are highlighted in yellow color:
Task Name |
Results compilation and project chartering |
Charter submission and project start-up |
Milestone One: Project Charter |
Project Estimates – Budget, Schedule and Risks |
Project approach and methodology |
Milestone Two: Project Plan Document |
UI /UX aspects for undergraduate and postgraduate systems |
Design diagrams and system behaviour |
System development – Source code |
Unit testing of the two sub-systems |
Review and release to the test team |
Milestone Three: Developed System |
System, Regression, Security and Performance Testing |
Implementation and management of changes |
Milestone Four: Test Report |
System Documentation |
Submission of the closure report |
Milestone Five: Closure Report |
The project will involve many costs and there will also be many benefits that will be earned as a result. On the 5-year return on investment of the project, the net present value and its calculation has been described below.
Year |
||||||
0 |
1 |
2 |
3 |
4 |
5 |
|
Undiscounted Flows |
||||||
Costs of TLS |
-$43,000 |
-$32,800 |
-$32,800 |
-$32,800 |
-$32,800 |
-$32,800 |
Benefits of TLS |
$0 |
$45,540 |
$45,540 |
$45,540 |
$45,540 |
$45,540 |
Net Cash Flow |
-$43,000 |
$12,740 |
$12,740 |
$12,740 |
$12,740 |
$12,740 |
Discount Factors |
||||||
Discount Rate Applied on the Project |
6.0% |
|||||
Base Year |
0 |
|||||
Year Index |
0 |
1 |
2 |
3 |
4 |
5 |
Discount Factor |
1.0000 |
0.9434 |
0.8900 |
0.8396 |
0.7921 |
0.7473 |
Discounted Flows |
||||||
Costs of TLS |
-$43,000 |
-$30,943 |
-$29,192 |
-$27,540 |
-$25,981 |
-$24,510 |
Benefits of TLS |
$0 |
$42,962 |
$40,530 |
$38,236 |
$36,072 |
$34,030 |
Net |
-$43,000 |
$12,019 |
$11,339 |
$10,697 |
$10,091 |
$9,520 |
Cumulative |
-$43,000 |
-$30,981 |
-$19,643 |
-$8,946 |
$1,145 |
$10,666 |
Net Present Value |
$10,666 |
|||||
Internal Rate of Return |
15% |
Conclusions and Recommendations
The project will be completed in five phases as displayed in the WBS section in the report. The overall duration of the project will be 108 days and the allocation of the schedule has been done on the basis of the effort that will be required for project completion. The project will earn an internal rate of return as 15% that shows that there will be considerable benefits that will come out of the project.
There will be many changes that will be introduced in HQI after the implementation of TLS. The management and administration must be ready to deal with such changes in terms of migration of the business activities to the new system, change in the business operations and many more. There shall be a change management plan that shall be designed in advance for this purpose (Lindberg, 2013). There may also be many of the risks that may emerge during the project. The primary category of these risks will be security risks and attacks. These risks may be introduced due to the increased access points and the operational errors executed by the users leading to enhancement of the security vulnerabilities. These risks shall be handled by using risk management procedure with adequate identification and analysis of the risks. The overall project management must also be efficiently done so that the project goals are met and there are no major risks involved (Kumar & Gregory, 2013).
References
Broy, M. (2015). Rethinking Nonfunctional Software Requirements. Computer, 48(5), 96-99. https://dx.doi.org/10.1109/mc.2015.139
Dabbagh, M., & Lee, S. (2014). An Approach for Integrating the Prioritization of Functional and Nonfunctional Requirements. The Scientific World Journal, 2014, 1-13. https://dx.doi.org/10.1155/2014/737626
Kumar, M., & Gregory, M. (2013). An exploration of risk management in global industrial investment. Risk Management, 15(4), 272-300. https://dx.doi.org/10.1057/rm.2013.8
Lindberg, D. (2013). Change Management Tools for Systemic Results. Change Management: An International Journal, 12(3), 1-6. https://dx.doi.org/10.18848/2327-798x/cgp/v12i03/50736
Miyahara, T. (2011). Scheduling and Management of Information System Implimentation Prosess: IT Project Management Based on Work Breakdown Structure. Japanese Journal Of Radiological Technology, 67(4), 393-399. https://dx.doi.org/10.6009/jjrt.67.393
Hans, R. (2013). Work Breakdown Structure: A Tool for Software Project Scope Verification. International Journal Of Software Engineering & Applications, 4(4), 19-25. https://dx.doi.org/10.5121/ijsea.2013.4402
Essay Writing Service Features
Our Experience
No matter how complex your assignment is, we can find the right professional for your specific task. Contact Essay is an essay writing company that hires only the smartest minds to help you with your projects. Our expertise allows us to provide students with high-quality academic writing, editing & proofreading services.Free Features
Free revision policy
$10Free bibliography & reference
$8Free title page
$8Free formatting
$8How Our Essay Writing Service Works
First, you will need to complete an order form. It's not difficult but, in case there is anything you find not to be clear, you may always call us so that we can guide you through it. On the order form, you will need to include some basic information concerning your order: subject, topic, number of pages, etc. We also encourage our clients to upload any relevant information or sources that will help.
Complete the order formOnce we have all the information and instructions that we need, we select the most suitable writer for your assignment. While everything seems to be clear, the writer, who has complete knowledge of the subject, may need clarification from you. It is at that point that you would receive a call or email from us.
Writer’s assignmentAs soon as the writer has finished, it will be delivered both to the website and to your email address so that you will not miss it. If your deadline is close at hand, we will place a call to you to make sure that you receive the paper on time.
Completing the order and download