The paper mainly reflects on the implementation of CRM system for the organization “TOSIG” that generally engages in offering insurance to the suppliers of Tier one for making improvements related with fencing, storage silos, stock yards and more. It is identified that currently, the organization is facing lot of challenges and issues due to the process of re-entering information within the system of the organization by the insurance agents after inspecting the property. This process is time consuming and TOSIG realizes that they are missing the opportunities of selling more insurance. Thus in order to resolve the issues ad challenges, the organization wants to upgrade their entire information system by implementing the CRM system. It is found that by upgrading the information system the organization will get opportunity of selling more number of insurances to the customers.
The main goal of the organization is to resolve the challenges that TOSIG is facing due to its current system of re-entering information within the database by updating the information system of the organization with the implementation of the CRM system. In addition to tis, it is found that with the implementation of CRM system, the organization also get the opportunity of selling more number of insurances to the customers.
The objectives of the projects are as follows:
The deliverables of the project are listed below:
The project “implementation of CRM system “within the organization TOSIG is done by aligning the needs of the organization with the system. It is found that the system is mainly implemented in order to achieve the objectives as well as goals of the organization. The demands as well as needs of the organization are identified and as per the need, the project is aligned with the demands of the organization so that the implementation of the CRM system will become helpful for the entire organization.
The milestones for the project “implementation of the CRM system” are reflected in the table below:
Task Name |
Completion date |
Milestone 1: Completion of project initiation phase |
Mon 28-05-18 |
Milestone 2: Completion of planning phase |
Thu 14-06-18 |
Milestone 3:Completion of execution phase |
Fri 07-09-18 |
Milestone 4: Completion of project closure phase |
Thu 13-09-18 |
The main requirements of the project are listed below:
Software: The software requirements of the project mainly includes
Hardware: The software requirements of the project mainly include the following:
Human resources: The human resources that are needed for the project are as follows:
The limits and exclusions of the project are listed below:
Work process breakdown schedule is defined as one of the spine of project management that helps in reflecting clear performance expectation for the project so that the entire objectives of the project can be properly achieved. The work process breakdown schedule for the project “implementation of CRM system” is provided below:
WBS |
Task Name |
0 |
Implementation of CRM system |
1 |
Project initiation phase |
1.1 |
Developing the business plan |
1.2 |
Identification of requirements |
1.3 |
Cost benefit analysis |
1.4 |
Identifying activities of project |
1.5 |
Project charter establishment |
1.6 |
Team members appointment |
1.7 |
Milestone 1: Completion of project initiation phase |
2 |
Planning phase of the project |
2.1 |
Developing the project plan |
2.2 |
Creating project resource plan |
2.3 |
Creating financial plan |
2.4 |
Developing quality plan |
2.5 |
Creating acceptance plan |
2.6 |
Developing communication plan |
2.7 |
Milestone 2: Completion of planning phase |
3 |
Execution phase of the project |
3.1 |
Development of project prototype |
3.2 |
Configuration plan |
3.3 |
transferring data |
3.4 |
Connecting with database |
3.5 |
Query testing |
3.6 |
Response time testing |
3.7 |
Software testing |
3.8 |
Acceptance testing |
3.9 |
Data warehouse testing |
3.10 |
Connection testing |
3.11 |
Milestone 3:Completion of execution phase |
4 |
Closure phase |
4.1 |
Post project review |
4.2 |
Sign off from the project stakeholders |
4.3 |
Go live |
4.4 |
Milestone 4: Completion of project closure phase |
It is identified that the time of the project is mainly tracked easily with the help of the schedule. The project manager utilizes the schedule of the project that is created in the planning phase for ensuring that they are on the right path. The entire schedule for the project is provided below:
WBS |
Task Name |
Duration |
Start |
Finish |
0 |
Implementation of CRM system |
94 days |
Mon 07-05-18 |
Thu 13-09-18 |
1 |
Project initiation phase |
16 days |
Mon 07-05-18 |
Mon 28-05-18 |
1.1 |
Developing the business plan |
4 days |
Mon 07-05-18 |
Thu 10-05-18 |
1.2 |
Identification of requirements |
2 days |
Fri 11-05-18 |
Mon 14-05-18 |
1.3 |
Cost benefit analysis |
2 days |
Tue 15-05-18 |
Wed 16-05-18 |
1.4 |
Identifying activities of project |
3 days |
Thu 17-05-18 |
Mon 21-05-18 |
1.5 |
Project charter establishment |
3 days |
Tue 22-05-18 |
Thu 24-05-18 |
1.6 |
Team members appointment |
2 days |
Fri 25-05-18 |
Mon 28-05-18 |
1.7 |
Milestone 1: Completion of project initiation phase |
0 days |
Mon 28-05-18 |
Mon 28-05-18 |
2 |
Planning phase of the project |
15 days |
Tue 29-05-18 |
Mon 18-06-18 |
2.1 |
Developing the project plan |
3 days |
Tue 29-05-18 |
Thu 31-05-18 |
2.2 |
Creating project resource plan |
2 days |
Fri 01-06-18 |
Mon 04-06-18 |
2.3 |
Creating financial plan |
3 days |
Tue 05-06-18 |
Thu 07-06-18 |
2.4 |
Developing quality plan |
2 days |
Fri 08-06-18 |
Mon 11-06-18 |
2.5 |
Creating acceptance plan |
3 days |
Tue 12-06-18 |
Thu 14-06-18 |
2.6 |
Developing communication plan |
2 days |
Fri 15-06-18 |
Mon 18-06-18 |
2.7 |
Milestone 2: Completion of planning phase |
0 days |
Thu 14-06-18 |
Thu 14-06-18 |
3 |
Execution phase of the project |
59 days |
Tue 19-06-18 |
Fri 07-09-18 |
3.1 |
Development of project prototype |
9 days |
Tue 19-06-18 |
Fri 29-06-18 |
3.2 |
Configuration plan |
9 days |
Mon 02-07-18 |
Thu 12-07-18 |
3.3 |
transferring data |
5 days |
Fri 13-07-18 |
Thu 19-07-18 |
3.4 |
Connecting with database |
9 days |
Fri 20-07-18 |
Wed 01-08-18 |
3.5 |
Query testing |
6 days |
Thu 02-08-18 |
Thu 09-08-18 |
3.6 |
Response time testing |
4 days |
Fri 10-08-18 |
Wed 15-08-18 |
3.7 |
Software testing |
6 days |
Thu 16-08-18 |
Thu 23-08-18 |
3.8 |
Acceptance testing |
6 days |
Fri 24-08-18 |
Fri 31-08-18 |
3.9 |
Data warehouse testing |
4 days |
Mon 03-09-18 |
Thu 06-09-18 |
3.10 |
Connection testing |
1 day |
Fri 07-09-18 |
Fri 07-09-18 |
3.11 |
Milestone 3:Completion of execution phase |
0 days |
Fri 07-09-18 |
Fri 07-09-18 |
4 |
Closure phase |
4 days |
Mon 10-09-18 |
Thu 13-09-18 |
4.1 |
Post project review |
2 days |
Mon 10-09-18 |
Tue 11-09-18 |
4.2 |
Sign off from the project stakeholders |
1 day |
Wed 12-09-18 |
Wed 12-09-18 |
4.3 |
Go live |
1 day |
Thu 13-09-18 |
Thu 13-09-18 |
4.4 |
Milestone 4: Completion of project closure phase |
0 days |
Thu 13-09-18 |
Thu 13-09-18 |
In order to manage the cost of the project, it is very much necessary for the project manager to focus on the cost related plan that is created by the project manager in the planning phase. The plan that is created after assumptions requires to be followed for tracking project budget.
WBS |
Task Name |
Duration |
Start |
Finish |
Predecessors |
Resource Names |
Cost |
0 |
Implementation of CRM system |
94 days |
Mon 07-05-18 |
Thu 13-09-18 |
$ 49,760.00 |
||
1 |
Project initiation phase |
16 days |
Mon 07-05-18 |
Mon 28-05-18 |
$ 8,320.00 |
||
1.1 |
Developing the business plan |
4 days |
Mon 07-05-18 |
Thu 10-05-18 |
Business analysts |
$ 1,600.00 |
|
1.2 |
Identification of requirements |
2 days |
Fri 11-05-18 |
Mon 14-05-18 |
2 |
Project manager |
$ 1,360.00 |
1.3 |
Cost benefit analysis |
2 days |
Tue 15-05-18 |
Wed 16-05-18 |
3 |
Business analysts |
$ 800.00 |
1.4 |
Identifying activities of project |
3 days |
Thu 17-05-18 |
Mon 21-05-18 |
4 |
Project manager |
$ 2,040.00 |
1.5 |
Project charter establishment |
3 days |
Tue 22-05-18 |
Thu 24-05-18 |
5 |
Project manager |
$ 2,040.00 |
1.6 |
Team members appointment |
2 days |
Fri 25-05-18 |
Mon 28-05-18 |
6 |
Administration officer |
$ 480.00 |
1.7 |
Milestone 1: Completion of project initiation phase |
0 days |
Mon 28-05-18 |
Mon 28-05-18 |
7 |
$ 0.00 |
|
2 |
Planning phase of the project |
15 days |
Tue 29-05-18 |
Mon 18-06-18 |
$ 7,080.00 |
||
2.1 |
Developing the project plan |
3 days |
Tue 29-05-18 |
Thu 31-05-18 |
7 |
Project manager |
$ 2,040.00 |
2.2 |
Creating project resource plan |
2 days |
Fri 01-06-18 |
Mon 04-06-18 |
10 |
Business analysts |
$ 800.00 |
2.3 |
Creating financial plan |
3 days |
Tue 05-06-18 |
Thu 07-06-18 |
11 |
Business analysts |
$ 1,200.00 |
2.4 |
Developing quality plan |
2 days |
Fri 08-06-18 |
Mon 11-06-18 |
12 |
Administration officer |
$ 480.00 |
2.5 |
Creating acceptance plan |
3 days |
Tue 12-06-18 |
Thu 14-06-18 |
13 |
Business analysts |
$ 1,200.00 |
2.6 |
Developing communication plan |
2 days |
Fri 15-06-18 |
Mon 18-06-18 |
14 |
Project manager |
$ 1,360.00 |
2.7 |
Milestone 2: Completion of planning phase |
0 days |
Thu 14-06-18 |
Thu 14-06-18 |
14 |
Project manager |
$ 0.00 |
3 |
Execution phase of the project |
59 days |
Tue 19-06-18 |
Fri 07-09-18 |
$ 31,280.00 |
||
3.1 |
Development of project prototype |
9 days |
Tue 19-06-18 |
Fri 29-06-18 |
15 |
Graphical user interface deveoper,Programmer_2 |
$ 7,200.00 |
3.2 |
Configuration plan |
9 days |
Mon 02-07-18 |
Thu 12-07-18 |
18 |
Database developer |
$ 3,600.00 |
3.3 |
transferring data |
5 days |
Fri 13-07-18 |
Thu 19-07-18 |
19 |
Database developer,Programmer_1 |
$ 4,000.00 |
3.4 |
Connecting with database |
9 days |
Fri 20-07-18 |
Wed 01-08-18 |
20 |
Database developer |
$ 3,600.00 |
3.5 |
Query testing |
6 days |
Thu 02-08-18 |
Thu 09-08-18 |
21 |
Tester |
$ 1,920.00 |
3.6 |
Response time testing |
4 days |
Fri 10-08-18 |
Wed 15-08-18 |
22 |
Tester |
$ 1,280.00 |
3.7 |
Software testing |
6 days |
Thu 16-08-18 |
Thu 23-08-18 |
23 |
Tester, Administration officer |
$ 3,360.00 |
3.8 |
Acceptance testing |
6 days |
Fri 24-08-18 |
Fri 31-08-18 |
24 |
Tester,Programmer_2 |
$ 4,320.00 |
3.9 |
Data warehouse testing |
4 days |
Mon 03-09-18 |
Thu 06-09-18 |
25 |
Tester |
$ 1,280.00 |
3.10 |
Connection testing |
1 day |
Fri 07-09-18 |
Fri 07-09-18 |
26 |
Programmer_1,Tester |
$ 720.00 |
3.11 |
Milestone 3:Completion of execution phase |
0 days |
Fri 07-09-18 |
Fri 07-09-18 |
27 |
$ 0.00 |
|
4 |
Closure phase |
4 days |
Mon 10-09-18 |
Thu 13-09-18 |
$ 3,080.00 |
||
4.1 |
Post project review |
2 days |
Mon 10-09-18 |
Tue 11-09-18 |
27 |
Project manager |
$ 1,360.00 |
4.2 |
Sign off from the project stakeholders |
1 day |
Wed 12-09-18 |
Wed 12-09-18 |
30 |
Administration officer |
$ 240.00 |
4.3 |
Go live |
1 day |
Thu 13-09-18 |
Thu 13-09-18 |
31 |
Database developer,Programmer_1, Project manager |
$ 1,480.00 |
4.4 |
Milestone 4: Completion of project closure phase |
0 days |
Thu 13-09-18 |
Thu 13-09-18 |
32 |
$ 0.00 |
The resource sheet that is required within the project for managing the resources that are associated with the project are mainly reflected in the table that is provided below:
Resource Name |
Type |
Material Label |
Initials |
Group |
Max. Units |
Std. Rate |
Ovt. Rate |
Cost/Use |
Accrue At |
Base Calendar |
Business analysts |
Work |
B |
100% |
$ 50.00/hr. |
$ 0.00/hr. |
$ 0.00 |
Prorated |
Standard |
||
Programmer_1 |
Work |
P |
100% |
$ 50.00/hr. |
$ 0.00/hr. |
$ 0.00 |
Prorated |
Standard |
||
Programmer_2 |
Work |
P |
100% |
$ 50.00/hr. |
$ 0.00/hr. |
$ 0.00 |
Prorated |
Standard |
||
Database developer |
Work |
D |
100% |
$ 50.00/hr. |
$ 0.00/hr. |
$ 0.00 |
Prorated |
Standard |
||
Graphical user interface developer |
Work |
G |
100% |
$ 50.00/hr. |
$ 0.00/hr. |
$ 0.00 |
Prorated |
Standard |
||
Tester |
Work |
T |
100% |
$ 40.00/hr. |
$ 0.00/hr. |
$ 0.00 |
Prorated |
Standard |
||
Administration officer |
Work |
A |
100% |
$ 30.00/hr. |
$ 0.00/hr. |
$ 0.00 |
Prorated |
Standard |
Risk |
Description |
Impact |
Probability |
Responsible person |
Mitigation strategies |
Budget shortfall |
IF the project budget is not utilized properly then there are chances of budget shortfall which further can create lot of financial challenges for the organization. |
High |
High |
Financial manager |
In order to mitigate this issue, it is necessary to conduct earned vale analysis so that the budget of the project can be tracked as well as managed effectively. |
Schedule slippage |
If the schedule of the project are not managed then the chances of slippage of project schedule is quite high. |
High |
Medium |
Project manager |
In order to resolve this issue, it is very much necessary to track the schedule of the project effectively. |
Improper management |
If the project is not managed effectively then the project manager faces lot of issues and challenges in finishing the project on time |
Medium |
Medium |
Hr. manager |
It is necessary to hire experienced project manager for the project. |
Inappropriate testing |
If the project that is developed is not properly tested then it can create lot of technical issues. |
High |
High |
Tester |
It is essential to undertake for testing for analyzing that the development of the system is done appropriately. |
Inappropriate configuration plan |
If the configuration plan for the project is not developed properly then it create lot of technical challenges. |
High |
High |
Administrator office, Database manager |
T is very much essential to creating the configuration plan for the project quite effectively. |
Inappropriate training |
It is found that due to absence of appropriate training facility, the team members of the organization cannot able to finish the activities of the project quite effectively. |
It is very much necessary to give proper facility of training to the team members of the project so that they can be able to finish the work of the project quite effectively. |
Audience |
Message |
Frequency |
Vehicle |
Owner |
Team members |
Information associated with the scope of the project are elaborated. |
Once |
Face to face |
Project manager |
Project planner |
Provide details about the status of time and cost of the project |
Weekly |
Face to face, conference |
Project team leaders |
Team leaders |
The issues and challenges faced b the members of the team are discussed |
Monthly |
Email, conference. |
Projects team members |
Financial manager |
The project manager discusses about the budget that is generally needed in order to complete the entire project on time. |
Whenever needed |
Email, face to face |
Project manager |
References
Badewi, A., 2016. The impact of project management (PM) and benefits management (BM) practices on project success: Towards developing a project benefits governance framework. International Journal of Project Management, 34(4), pp.761-778.
Cagliano, A.C., Grimaldi, S. and Rafele, C., 2015. Choosing project risk management techniques. A theoretical framework. Journal of Risk Research, 18(2), pp.232-248.
Calvo-Mora, A., Navarro-García, A. and Periañez-Cristobal, R., 2015. Project to improve knowledge management and key business results through the EFQM excellence model. International Journal of Project Management, 33(8), pp.1638-1651.
Chih, Y.Y. and Zwikael, O., 2015. Project benefit management: A conceptual framework of target benefit formulation. International Journal of Project Management, 33(2), pp.352-362.
Fernandes, G., Ward, S. and Araújo, M., 2015. Improving and embedding project management practice in organisations—A qualitative study. International Journal of Project Management, 33(5), pp.1052-1067.
Heldman, K., 2018. PMP: project management professional exam study guide. John Wiley & Sons.
Hornstein, H.A., 2015. The integration of project management and organizational change management is now a necessity. International Journal of Project Management, 33(2), pp.291-298.
Ika, L.A., 2015. Opening the black box of project management: Does World Bank project supervision influence project impact?. International Journal of Project Management, 33(5), pp.1111-1123.
Joslin, R. and Müller, R., 2015. Relationships between a project management methodology and project success in different project governance contexts. International Journal of Project Management, 33(6), pp.1377-1392.
Kucharska, W. and Kowalczyk, R., 2016. Trust, Collaborative Culture and Tacit Knowledge Sharing in Project Management–a Relationship Model.
Lientz, B. and Rea, K., 2016. Breakthrough technology project management. Routledge.
Marcelino-Sádaba, S., Pérez-Ezcurdia, A., Lazcano, A.M.E. and Villanueva, P., 2014. Project risk management methodology for small firms. International journal of project management, 32(2), pp.327-340.
Marcelino-Sádaba, S., González-Jaen, L.F. and Pérez-Ezcurdia, A., 2015. Using project management as a way to sustainability. From a comprehensive review to a framework definition. Journal of cleaner production, 99, pp.1-16.
Mir, F.A. and Pinnington, A.H., 2014. Exploring the value of project management: linking project management performance and project success. International journal of project management, 32(2), pp.202-217.
Riol, H. and Thuillier, D., 2015. Project management for academic research projects: balancing structure and flexibility. International Journal of Project Organisation and Management, 7(3), pp.251-269.
Too, E.G. and Weaver, P., 2014. The management of project management: A conceptual framework for project governance. International Journal of Project Management, 32(8), pp.1382-1394.
Essay Writing Service Features
Our Experience
No matter how complex your assignment is, we can find the right professional for your specific task. Contact Essay is an essay writing company that hires only the smartest minds to help you with your projects. Our expertise allows us to provide students with high-quality academic writing, editing & proofreading services.Free Features
Free revision policy
$10Free bibliography & reference
$8Free title page
$8Free formatting
$8How Our Essay Writing Service Works
First, you will need to complete an order form. It's not difficult but, in case there is anything you find not to be clear, you may always call us so that we can guide you through it. On the order form, you will need to include some basic information concerning your order: subject, topic, number of pages, etc. We also encourage our clients to upload any relevant information or sources that will help.
Complete the order formOnce we have all the information and instructions that we need, we select the most suitable writer for your assignment. While everything seems to be clear, the writer, who has complete knowledge of the subject, may need clarification from you. It is at that point that you would receive a call or email from us.
Writer’s assignmentAs soon as the writer has finished, it will be delivered both to the website and to your email address so that you will not miss it. If your deadline is close at hand, we will place a call to you to make sure that you receive the paper on time.
Completing the order and download