1.Project Background
1.1. Project goal
Following are key goals of the proposed project:
1.2. Project objective
The key objective of project is to prepare a new information system to handle the increasing customer’s needs and allow agents to attract new clients who have high risk. The objectives are as follows:
1.3. Project Deliverable
Following are key deliverables of the proposed information system:
1.4. Strategic alignment of project
2.Project schedule
2.1.Milestones
Following are key milestones of the project:
Task Name |
Start |
Finish |
Milestone 1 – Sign off project plan |
Fri 06/07/18 |
Fri 06/07/18 |
Milestone 2 – CRM vendor selection |
Tue 24/07/18 |
Tue 24/07/18 |
Milestone 3 – Cloud vendor selection |
Tue 24/07/18 |
Tue 24/07/18 |
Milestone 4 – Finalize design document |
Mon 20/08/18 |
Mon 20/08/18 |
Milestone 7 – Developed code |
Wed 10/10/18 |
Wed 10/10/18 |
Milestone 8 – Tested system |
Tue 30/10/18 |
Tue 30/10/18 |
2.2. Project requirements
Following are key project or technical requirements of the project:
2.3. Limits and exclusions
Following are key limits and exclusion of the project (Yang & Tamir, 2015):
2.4. Work/ process breakdown schedule
WBS |
Task Name |
1 |
Automated System – TOSIG |
1.1 |
Project planning |
1.1.1 |
Define scope |
1.1.2 |
Define limits |
1.1.3 |
Define human resources |
1.1.4 |
Prepare project plan |
1.1.5 |
Milestone 1 – Sign off project plan |
1.2 |
Vendor selection |
1.2.1 |
CRM vendor selection |
1.2.1.1 |
Conduct market research |
1.2.1.2 |
Shortlist 3 vendors |
1.2.1.3 |
Select vendor |
1.2.1.4 |
Milestone 2 – CRM vendor selection |
1.2.2 |
Cloud solution vendor |
1.2.2.1 |
Conduct market research |
1.2.2.2 |
Shortlist 3 vendors |
1.2.2.3 |
Select vendor |
1.2.2.4 |
Milestone 3 – Cloud vendor selection |
1.3 |
Project development |
1.3.1 |
Design Document |
1.3.1.1 |
Wireframe Sketches |
1.3.1.2 |
Competitive Analysis |
1.3.1.3 |
Content Requirements |
1.3.1.4 |
Finalize Information Architecture |
1.3.1.5 |
Finalize Navigation Scheme |
1.3.1.6 |
Finalize Content Design |
1.3.1.7 |
Finalize Visual Design |
1.3.1.8 |
Milestone 4 – Finalize design document |
1.3.2 |
Prepare database |
1.3.2.1 |
Define creation query |
1.3.2.2 |
Execute database creation query |
1.3.3 |
Code Generation |
1.3.3.1 |
Develop business logic content |
1.3.3.2 |
Integrate CRM |
1.3.3.3 |
Integrate Cloud solution |
1.3.3.4 |
Milestone 7 – Developed code |
1.3.4 |
Testing |
1.3.4.1 |
Application testing |
1.3.4.2 |
System testing |
1.3.4.3 |
UAT |
1.3.4.4 |
Prepare testing bugs summary |
1.3.4.5 |
Milestone 8 – Tested system |
1.4 |
Go – Live |
3.Time and cost management 3.1.Time management
The project starts on 2nd July 2018 and ends on 1st November 2018 with total duration of 89 days. It consists of following sub-phases:
WBS |
Task Name |
Duration |
Start |
Finish |
1 |
Automated System – TOSIG |
89 days |
Mon 02/07/18 |
Thu 01/11/18 |
1.1 |
Project planning |
5 days |
Mon 02/07/18 |
Fri 06/07/18 |
1.2 |
Vendor selection |
12 days |
Mon 09/07/18 |
Tue 24/07/18 |
1.2.1 |
CRM vendor selection |
12 days |
Mon 09/07/18 |
Tue 24/07/18 |
1.2.2 |
Cloud solution vendor |
12 days |
Mon 09/07/18 |
Tue 24/07/18 |
1.3 |
Project development |
70 days |
Wed 25/07/18 |
Tue 30/10/18 |
1.3.1 |
Design Document |
19 days |
Wed 25/07/18 |
Mon 20/08/18 |
1.3.2 |
Prepare database |
7 days |
Tue 21/08/18 |
Wed 29/08/18 |
1.3.3 |
Code Generation |
30 days |
Thu 30/08/18 |
Wed 10/10/18 |
1.3.4 |
Testing |
14 days |
Thu 11/10/18 |
Tue 30/10/18 |
1.4 |
Go – Live |
2 days |
Wed 31/10/18 |
Thu 01/11/18 |
3.2. Cost management Cost and Billing Comparison for Cloud Vendors
Cloud Vendors for Data File Exchange (AdvisoryHQ, 2015)
Labour cost = $52,000
CRM license cost = $2000
Cloud cost = $200 1.Resource management
The management of resources can be depicted from RACI matrix (Mohapatra & Patnaik, 2011) as shown below :
Task Name |
PM |
GUI |
PG1 |
PG2 |
DBA |
TR |
AO |
BA |
Define scope |
RACI |
I |
I |
I |
I |
I |
I |
I |
Define limits |
RACI |
I |
I |
I |
I |
I |
I |
I |
Define human resources |
RACI |
I |
I |
I |
I |
I |
I |
I |
Prepare project plan |
RACI |
I |
I |
I |
I |
I |
I |
I |
Conduct market research |
ACI |
I |
I |
I |
I |
I |
I |
R |
Shortlist 3 vendors |
ACI |
I |
I |
I |
I |
I |
I |
R |
Conduct market research |
ACI |
I |
I |
I |
I |
I |
I |
R |
Shortlist 3 vendors |
ACI |
I |
I |
I |
I |
I |
I |
R |
Select vendor |
ACI |
I |
I |
I |
I |
I |
I |
R |
Wireframe Sketches |
ACI |
R |
I |
I |
I |
I |
I |
I |
Competitive Analysis |
ACI |
R |
I |
I |
I |
I |
I |
I |
Content Requirements |
ACI |
R |
I |
I |
I |
I |
R |
I |
Finalize Information Architecture |
ACI |
R |
I |
I |
I |
I |
I |
I |
Finalize Navigation Scheme |
ACI |
R |
I |
I |
I |
I |
I |
I |
Finalize Content Design |
ACI |
R |
I |
I |
I |
I |
I |
I |
Finalize Visual Design |
RACI |
I |
I |
I |
I |
I |
I |
I |
Define creation query |
ACI |
I |
I |
I |
R |
I |
I |
I |
Execute database creation query |
ACI |
I |
I |
I |
R |
I |
I |
I |
Develop business logic content |
ACI |
I |
R |
I |
I |
I |
I |
I |
Integrate CRM |
ACI |
I |
I |
R |
I |
I |
I |
I |
Integrate Cloud solution |
ACI |
I |
I |
R |
I |
I |
I |
I |
Application testing |
ACI |
I |
I |
I |
I |
R |
I |
I |
System testing |
ACI |
I |
I |
I |
I |
R |
I |
I |
UAT |
ACI |
I |
I |
I |
I |
R |
I |
I |
Prepare testing bugs summary |
ACI |
I |
I |
I |
I |
R |
I |
I |
Go – Live |
RACI |
I |
I |
I |
I |
I |
I |
I |
Resource allocation to each task activity is shown below:
Task Name |
Resource Names |
Define scope |
Project manager |
Define limits |
Project manager |
Define human resources |
Project manager |
Prepare project plan |
Project manager |
Conduct market research |
Business analyst |
Shortlist 3 vendors |
Business analyst |
Conduct market research |
Business analyst |
Shortlist 3 vendors |
Business analyst |
Select vendor |
Business analyst |
Wireframe Sketches |
Graphical user interface developer |
Competitive Analysis |
Graphical user interface developer |
Content Requirements |
Graphical user interface developer, Administration officer |
Finalize Information Architecture |
Graphical user interface developer |
Finalize Navigation Scheme |
Graphical user interface developer |
Finalize Content Design |
Graphical user interface developer |
Finalize Visual Design |
Project manager |
Define creation query |
Database developer |
Execute database creation query |
Database developer |
Develop business logic content |
Programmer 1 |
Integrate CRM |
Programmer 2 |
Integrate Cloud solution |
Programmer 2 |
Application testing |
Tester |
System testing |
Tester |
UAT |
Tester |
Prepare testing bugs summary |
Tester |
Go – Live |
Project manager |
(Mallery, 2011) 2.Risk management
Following are risks associated with the project
Risk |
Probability |
Impact |
Contingency plan |
Increase in the budget |
High |
Medium |
In case the project budget goes beyond the estimated budget then high management approval is required for additional budget. |
Deliverables deadlines are missed. |
Medium |
High |
Continuous monitoring of project is performed by the project manager using tools like Gantt chart, Minutes of Meetings, etc. This will help in delivering milestones / deliverables on time. |
Unexpected quality of deliverables |
Low |
High |
Project manager should ensure that testing is conducted as soon as code is developed to resolve all the likely and unlikely bugs before UAT. |
Variation in scope |
Medium |
High |
Company may change the scope after completion of project as per the changing needs. In this scenario, only those tasks should be accepted for which the agreement was made and rest of them should be rejected. |
Disputes among stakeholders |
Medium |
Medium |
Regular meetings with the stakeholders to resolve any conflicts and clarify their respective expectations so that confusion does not occur. |
Issues in the developed application |
Medium |
Medium |
Testing should be done at all levels to resolve the bugs and keep testing again to find any bug. |
Requirements are not |
Low |
High |
Involve clients throughout the project development and get the requirements verified from stakeholders. |
Risks related to scheduling |
Low |
Medium |
In order to resolve risks related to project scheduling, monitoring tools are used to keep the tasks on track which will made it easier for maintaining project resources. |
Technical Risks |
Low |
High |
When bugs occur in the application, it can cause issues in the working of the developed system, hence it is important to ensure compatible between the necessary hardware and software before CRM-cloud based system is launched. |
Non-availability of necessary human resources |
Medium |
High |
Availability of resources should be ensure before starting the project. The industry experts should be consulted for resource hiring (Henderson, 2004). |
3.Communication management plan
The communication plan aims at making a plan to fulfil the requirement of communication among the team members, project owner and stakeholders. The plan consist of details of mode of communication and frequency of communication.
Stakeholder |
Data |
Frequency of communication |
Location of communication |
Aim of communication |
Communication mechanism |
Project Sponsor |
Project report |
Weekly |
SharePoint |
Status |
|
Project manager |
Project report |
Weekly |
SharePoint |
Status |
Email, face-to-face |
Project Manager |
Request for funds, Project change request, Project requirements, updates on team members |
At kickstart of project, daily and at the end of each project. |
SharePoint |
Status |
SharePoint, email and face-to-face |
Project Team members |
Project requirements, updates on team members |
At kickstart of project, daily and at the end of each project. |
SharePoint |
Status |
SharePoint, email and face-to-face |
Current clients |
Before starting the project |
Daily |
|
Status |
Emails |
Clients |
Final product |
Go-live |
SharePoint |
End-product |
Website and email (Marle, 2014) |
4.References
AdvisoryHQ,. (2015). 5 Best Small Business Accounting Software in Australia. AdvisoryHQ. Retrieved 11 September 2016, from
Henderson, L. (2004). Encoding and decoding communication competencies in project management ? an exploratory study. International Journal Of Project Management, 22(6), 469-476.
Mallery, M. (2011). Project Management Portal (PMP) from the University of Washington Information Technology Wiki –
Marle, F. (2014). Assisting project risk management method selection. International Journal Of Project Organisation And Management, 6(3), 254
Mohapatra, S., & Patnaik, A. (2011). Sustainability in HRIS implementation through effective project management. International Journal Of Project Organisation And Management, 3(1), 78.
Yang, Y., & Tamir, G. (2015). Offshore software project management: mapping project success factors. International Journal Of Project Organisation And Management, 7(2), 111
Essay Writing Service Features
Our Experience
No matter how complex your assignment is, we can find the right professional for your specific task. Contact Essay is an essay writing company that hires only the smartest minds to help you with your projects. Our expertise allows us to provide students with high-quality academic writing, editing & proofreading services.Free Features
Free revision policy
$10Free bibliography & reference
$8Free title page
$8Free formatting
$8How Our Essay Writing Service Works
First, you will need to complete an order form. It's not difficult but, in case there is anything you find not to be clear, you may always call us so that we can guide you through it. On the order form, you will need to include some basic information concerning your order: subject, topic, number of pages, etc. We also encourage our clients to upload any relevant information or sources that will help.
Complete the order formOnce we have all the information and instructions that we need, we select the most suitable writer for your assignment. While everything seems to be clear, the writer, who has complete knowledge of the subject, may need clarification from you. It is at that point that you would receive a call or email from us.
Writer’s assignmentAs soon as the writer has finished, it will be delivered both to the website and to your email address so that you will not miss it. If your deadline is close at hand, we will place a call to you to make sure that you receive the paper on time.
Completing the order and download