The primary objectives of the project are:
However, it is worth mentioning that the project would not include the regular update of research related contents/
information on the web application.
Task Name |
Milestone date |
Web application project for researcher centre |
Fri 10-11-17 |
Project starts |
Mon 10-04-17 |
Research And Planning Phase |
Thu 04-05-17 |
Requirement Gathering and Analysis of The Project |
Fri 21-04-17 |
Creating the project scope document |
Fri 21-04-17 |
Project Planning |
Thu 04-05-17 |
Developing the Project Plans (project charter) |
Thu 04-05-17 |
Conducting the kick off meeting |
Thu 04-05-17 |
Solution Design Phase |
Fri 18-08-17 |
Procurement |
Fri 26-05-17 |
Developing the Site-map the website |
Fri 09-06-17 |
Creating the website Wire-frame |
Fri 23-06-17 |
Designing the Database |
Fri 11-08-17 |
Develop the Requirement Specification |
Fri 18-08-17 |
Developing of the Admin Login Sections |
Tue 05-09-17 |
Admin Settings development |
Fri 08-09-17 |
Content Manager settings development |
Tue 05-09-17 |
Member Manager settings development |
Fri 08-09-17 |
TESTING |
|
Internal Testing (Functional/Security) |
Fri 15-09-17 |
User Acceptance Test |
Fri 29-09-17 |
Developing test reports |
Fri 06-10-17 |
GO LIVE |
Fri 10-11-17 |
Deployment Activities |
Fri 27-10-17 |
Uploading Files/ Contents |
Fri 27-10-17 |
Setup Database |
Fri 13-10-17 |
Copy Database |
Fri 20-10-17 |
Other Miscellaneous Setting Activities |
Fri 10-11-17 |
Project ends |
Fri 10-11-17 |
The stakeholders associated with the project are:
The following lessons have been learnt from the project:
Signature: Please insert Date:
Print Name: Please insert
Title: Please insert
Role: Please insert
Signature: Please insert Date:
Print Name: Please insert
Title: Please insert
Role: Please insert
Signature: Please insert Date:
Print Name: Please insert
Title: Please insert
Role: Please insert
The communication plan being discussed in the following section of the report have been developed primarily with the aim of formalizing the tools and techniques to be utilized in communicating with all the members/ stakeholders of the project team. It is worth mentioning that the plan supports both upwards and downwards communication strategies.
Sl. no |
Stakeholder |
Information to be shared |
Frequency of information exchange |
Location of information exchange |
Purpose of communication |
Mechanism for communication |
1 |
The managerial authorities of the reassert center |
Progress reports of the project |
Once in each month |
Administrative office of the research center |
To communicate the progress made by the team |
Physical meeting |
2 |
The project manager
|
Progress reports of the project |
Once in each week |
Project manager’s office |
To highlight the weekly progress of the project |
Physical meetings and emails |
3 |
The account manager
|
Information to be uploaded in the website |
Once, before commissioning the project |
NA |
To facilitate the content development phase |
Detailed reports |
4 |
The project team (website development, data base designing, testing team)
|
Any changes requested by the client |
As and when required |
Project manager’s office |
To highlight any deviation from the initial project plan |
Physical meetings and official reports |
In case changes are to be included in the project (in terms of project schedule, scope or resources), the process outlined in the following section has to be followed:
Step 1: Change request documentation: The changes requested by the stakeholders associated with the project have to be documented in a formal manner, indicating the reason behind making the request, the possible outcomes of the changes and the effect of including the changes on the progress so far made in the project. The documents have to submitted to the project manager through appropriate channels.
Step 2: Decision making: The project manager, along with the other members of the executive board has to take decision regarding the inclusion of the change based on the information included in the change request document.
Step 4: Communicating the decision: The last step of the process is essentially associated with communicating the outcomes of the change request process. In case, decisions are made in favor of the change request, the same has to be communicated to all the stakeholders in an appropriate manner. On the other hand, unfavorable decisions would be communicated to be the proposer only.
Team meetings would be conducted throughout the lifecycle of the project according to the following rules:
The Work breakdown structure of the project is as follows:
Wbs |
Task Name |
1 |
Project Starts |
2 |
Research and Planning Phase |
2.1 |
Requirement Gathering and Analysis of The Project |
2.1.1 |
Creating the Project Scope Document |
2.2 |
Project Planning |
2.2.1 |
Developing the Project Plans (Project Charter) |
2.2.2 |
Conducting the Kick Off Meeting |
3 |
Solution Design Phase |
3.1 |
Procurement |
3.1.1 |
Identification of The Hardware and Software Elements Required for The Project |
3.1.2 |
Identifying the Vendors Capable of Supplying the Elements |
3.1.3 |
Procurement of Elements |
3.2 |
Developing the Site-Map the Website |
3.2.1 |
Creating the Website Site-Map |
3.2.2 |
Creating the Website Site-Map Documents |
3.3 |
Creating the Website Wire-Frame |
3.3.1 |
Creating the Front-End Wire-Frames of The Web Application |
3.3.2 |
Creating Back End Wire-Frames of The Web Application |
3.4 |
Designing the Database |
3.4.1 |
Developing the Database Schema |
3.4.2 |
Creating the Database |
3.4.3 |
Documenting the Database Schema Document |
3.5 |
Develop the Requirement Specification |
3.5.1 |
Creating the SRS Document |
4 |
Designing the Layout of The Database |
4.1 |
Developing the Home Page |
4.2 |
Developing the Content Pages |
4.3 |
Developing the Project Information Pages |
5 |
Development of The Front End of The Website |
5.1 |
Developing the Home Section |
5.2 |
Developing the Basic Search |
5.3 |
Developing the Advanced Search |
5.4 |
Developing the Project Listing Section |
6 |
Development of The Back End of The Website |
6.1 |
Developing of The Admin Login Sections |
6.2 |
Admin Settings Development |
6.3 |
Content Manager Settings Development |
6.4 |
Member Manager Settings Development |
7 |
Testing |
7.1 |
Internal Testing (Functional/Security) |
7.1.1 |
Functional Testing |
7.1.2 |
Security Testing |
7.2 |
User Acceptance Test |
7.3 |
Developing Test Reports |
8 |
Go Live |
9 |
Deployment Activities |
9.1 |
Uploading Files/ Contents |
9.2 |
Setup Database |
9.3 |
Copy Database |
10 |
Other Miscellaneous Setting Activities |
11 |
Project Ends |
The estimated schedule and budget of the project is as follows:
WBS |
Task Name |
Duration |
Start |
Finish |
Predecessors |
Resource Names |
Cost |
0 |
Web application project for researcher centre |
155 days |
Mon 10-04-17 |
Fri 10-11-17 |
$49,434.00 |
||
1 |
Project starts |
0 days |
Mon 10-04-17 |
Mon 10-04-17 |
Project Manager |
$0.00 |
|
2 |
RESEARCH AND PLANNING PHASE |
19 days |
Mon 10-04-17 |
Thu 04-05-17 |
$17,344.00 |
||
2.1 |
Requirement Gathering and Analysis of The Project |
10 days |
Mon 10-04-17 |
Fri 21-04-17 |
$13,024.00 |
||
2.1.1 |
Creating the project scope document |
10 days |
Mon 10-04-17 |
Fri 21-04-17 |
1 |
Project Manager, project team member 1, Fringe [1] |
$13,024.00 |
2.2 |
Project Planning |
9 days |
Mon 24-04-17 |
Thu 04-05-17 |
$4,320.00 |
||
2.2.1 |
Developing the Project Plans (project charter) |
9 days |
Mon 24-04-17 |
Thu 04-05-17 |
4 |
Project Manager, Project team member 2 |
$4,320.00 |
2.2.2 |
Conducting the kick off meeting |
0 days |
Thu 04-05-17 |
Thu 04-05-17 |
6 |
Project Manager |
$0.00 |
3 |
SOLUTION DESIGN PHASE |
76 days |
Fri 05-05-17 |
Fri 18-08-17 |
$13,050.00 |
||
3.1 |
Procurement |
16 days |
Fri 05-05-17 |
Fri 26-05-17 |
$4,250.00 |
||
3.1.1 |
Identification of the hardware and software elements required for the project |
5 days |
Fri 05-05-17 |
Thu 11-05-17 |
7 |
IT Consultant |
$1,200.00 |
3.1.2 |
Identifying the vendors capable of supplying the elements |
4 days |
Fri 12-05-17 |
Wed 17-05-17 |
10 |
project team member 1, Project team member 2 |
$960.00 |
3.1.3 |
Procurement of elements |
7 days |
Thu 18-05-17 |
Fri 26-05-17 |
11 |
Hardware elements [1], Project team member 2, Software and licensing [1] |
$2,090.00 |
3.2 |
Developing the Site-map the website |
10 days |
Mon 29-05-17 |
Fri 09-06-17 |
$1,600.00 |
||
3.2.1 |
Creating the Website Site-map |
5 days |
Mon 29-05-17 |
Fri 02-06-17 |
12 |
Web developer |
$800.00 |
3.2.2 |
Creating the Website Site-map Documents |
5 days |
Mon 05-06-17 |
Fri 09-06-17 |
14 |
Web developer |
$800.00 |
3.3 |
Creating the website Wire-frame |
10 days |
Mon 12-06-17 |
Fri 23-06-17 |
$1,600.00 |
||
3.3.1 |
Creating the Front-End Wire-frames Of the Web application |
5 days |
Mon 12-06-17 |
Fri 16-06-17 |
15 |
Web developer |
$800.00 |
3.3.2 |
Creating Back End Wire-frames Of the Web application |
5 days |
Mon 19-06-17 |
Fri 23-06-17 |
17 |
Web developer |
$800.00 |
3.4 |
Designing the Database |
35 days |
Mon 26-06-17 |
Fri 11-08-17 |
$4,800.00 |
||
3.4.1 |
developing the Database Schema |
10 days |
Mon 26-06-17 |
Fri 07-07-17 |
18 |
Data base developer |
$1,600.00 |
3.4.2 |
Creating the Database |
20 days |
Mon 10-07-17 |
Fri 04-08-17 |
20 |
Content developer |
$3,200.00 |
3.4.3 |
Documenting the Database Schema Document |
5 days |
Mon 07-08-17 |
Fri 11-08-17 |
21 |
$0.00 |
|
3.5 |
Develop the Requirement Specification |
5 days |
Mon 14-08-17 |
Fri 18-08-17 |
$800.00 |
||
3.5.1 |
Creating the SRS document |
5 days |
Mon 14-08-17 |
Fri 18-08-17 |
22 |
Content developer |
$800.00 |
4 |
DESIGNING THE LAYOUT OF THE DATABASE |
3 days |
Mon 21-08-17 |
Wed 23-08-17 |
$1,440.00 |
||
4.1 |
Developing the Home Page |
3 days |
Mon 21-08-17 |
Wed 23-08-17 |
24 |
Web developer |
$480.00 |
4.2 |
Developing the Content Pages |
3 days |
Mon 21-08-17 |
Wed 23-08-17 |
24 |
Web developer |
$480.00 |
4.3 |
Developing the project information pages |
3 days |
Mon 21-08-17 |
Wed 23-08-17 |
24 |
Web developer |
$480.00 |
5 |
DEVELOPMENT OF THE FRONT END OF THE WEBSITE |
6 days |
Thu 24-08-17 |
Thu 31-08-17 |
$1,280.00 |
||
5.1 |
Developing the Home Section |
2 days |
Thu 24-08-17 |
Fri 25-08-17 |
28 |
Web developer |
$320.00 |
5.2 |
Developing the Basic Search |
2 days |
Thu 24-08-17 |
Fri 25-08-17 |
28 |
Web developer |
$320.00 |
5.3 |
Developing the Advanced Search |
2 days |
Mon 28-08-17 |
Tue 29-08-17 |
31 |
Web developer |
$320.00 |
5.4 |
Developing the Project Listing Section |
2 days |
Wed 30-08-17 |
Thu 31-08-17 |
32 |
Web developer |
$320.00 |
6 |
DEVELOPMENT OF THE BACK END OF THE WEBSITE |
6 days |
Fri 01-09-17 |
Fri 08-09-17 |
$1,920.00 |
||
6.1 |
Developing of the Admin Login Sections |
3 days |
Fri 01-09-17 |
Tue 05-09-17 |
33 |
Web developer |
$480.00 |
6.2 |
Admin Settings development |
3 days |
Wed 06-09-17 |
Fri 08-09-17 |
35 |
Web developer |
$480.00 |
6.3 |
Content Manager settings development |
3 days |
Fri 01-09-17 |
Tue 05-09-17 |
33 |
Web developer |
$480.00 |
6.4 |
Member Manager settings development |
3 days |
Wed 06-09-17 |
Fri 08-09-17 |
37 |
Web developer |
$480.00 |
7 |
TESTING |
20 days |
Mon 11-09-17 |
Fri 06-10-17 |
$5,600.00 |
||
7.1 |
Internal Testing (Functional/Security) |
5 days |
Mon 11-09-17 |
Fri 15-09-17 |
$2,400.00 |
||
7.1.1 |
Functional Testing |
5 days |
Mon 11-09-17 |
Fri 15-09-17 |
38,36,27,26,30 |
System tester |
$1,200.00 |
7.1.2 |
Security Testing |
5 days |
Mon 11-09-17 |
Fri 15-09-17 |
38 |
System tester |
$1,200.00 |
7.2 |
User Acceptance Test |
10 days |
Mon 18-09-17 |
Fri 29-09-17 |
41,42 |
System tester |
$2,400.00 |
7.3 |
Developing test reports |
5 days |
Mon 02-10-17 |
Fri 06-10-17 |
43 |
Content developer |
$800.00 |
8 |
GO LIVE |
25 days |
Mon 09-10-17 |
Fri 10-11-17 |
$8,800.00 |
||
8.1 |
Deployment Activities |
15 days |
Mon 09-10-17 |
Fri 27-10-17 |
$6,400.00 |
||
8.1.1 |
Uploading Files/ Contents |
15 days |
Mon 09-10-17 |
Fri 27-10-17 |
44 |
Sonia Reed (application manager) |
$4,800.00 |
8.1.2 |
Setup Database |
5 days |
Mon 09-10-17 |
Fri 13-10-17 |
44 |
Data base developer |
$800.00 |
8.1.3 |
Copy Database |
5 days |
Mon 16-10-17 |
Fri 20-10-17 |
48 |
Data base developer |
$800.00 |
8.2 |
Other Miscellaneous Setting Activities |
10 days |
Mon 30-10-17 |
Fri 10-11-17 |
47,49 |
project team member 1, Project team member 2 |
$2,400.00 |
9 |
Project ends |
0 days |
Fri 10-11-17 |
Fri 10-11-17 |
50 |
Project Manager |
$0.00 |
The budgetary calculations of the project have been depicted in the above section of the report. In this section of the report, discussions would be made on the assumptions and constraints utilized for developing the budget.
Resource Name |
Type |
Material Label |
Initials |
Group |
Max. Units |
Std. Rate |
Ovt. Rate |
Cost/Use |
Accrue At |
Base Calendar |
Sonia Reed (application manager) |
Work |
S |
100% |
$40.00/hr |
$0.00/hr |
$0.00 |
Prorated |
Standard |
||
Project Manager |
Work |
P |
100% |
$45.00/hr |
$85.00/hr |
$0.00 |
Prorated |
Standard |
||
IT Consultant |
Work |
I |
400% |
$30.00/hr |
$45.00/hr |
$0.00 |
Prorated |
Standard |
||
Web developer |
Work |
W |
500% |
$20.00/hr |
$40.00/hr |
$0.00 |
Prorated |
Standard |
||
Data base developer |
Work |
D |
300% |
$20.00/hr |
$35.00/hr |
$0.00 |
Prorated |
Standard |
||
System tester |
Work |
S |
300% |
$30.00/hr |
$40.00/hr |
$0.00 |
Prorated |
Standard |
||
Content developer |
Work |
C |
100% |
$20.00/hr |
$30.00/hr |
$0.00 |
Prorated |
Standard |
||
project team member 1 |
Work |
p |
100% |
$15.00/hr |
$50.00/hr |
$0.00 |
Prorated |
Standard |
||
Project team member 2 |
Work |
P |
100% |
$15.00/hr |
$50.00/hr |
$0.00 |
Prorated |
Standard |
The resources associated with the project would work for 5 days a week, 8 hours a day. They would not be encouraged to work for additional hours.
Resource Name |
Type |
Material Label |
Initials |
Group |
Max. Units |
Std. Rate |
Ovt. Rate |
Cost/Use |
Accrue At |
Base Calendar |
Hardware elements |
Material |
|
H |
|
|
$250.00 |
|
$0.00 |
Prorated |
|
Software and licensing |
Material |
S |
$1,000.00 |
$0.00 |
Prorated |
The constraints associated with the project are:
The entire project plan and budgeting activity has been completed based on the experience gathered from working on similar projects in the past. Thus, the level of confidence (on the effective execution of the project according to the plan) is considerably high.
The known knowns and the know unknowns of the project are being tabulated below:
Type |
Factor |
Budgeting strategy |
Known Knowns |
Salaries and wages of project team members |
Included in the budget as the cost associated with each project activity |
Known Unknowns |
Cost required for procurement of hardware elements to be utilized in the project. |
Estimated amount of 250.00 AUSD included in budget |
Cost required for procurement of software elements and licenses to be utilized in the project. |
Estimated amount of 1,000.00 AUSD included in budget |
|
Additional cost required in the project |
Included in the project in terms of cost associated with the project activity “Other Miscellaneous Setting Activities” |
The following matrix provides an insight into the risks associated with the project.
RISK MANAGEMENT LOG |
|
|
|
|
RISK MANAGEMENT LOG |
|
|
||||
Project Name: |
|
Web application project for researcher centre |
|
|
|
|
Project Name: |
Web application project for researcher centre |
|||
Project Manager Name: |
<required> |
Project Manager Name: |
<required> |
||||||||
Project Description: |
|
|
<required> |
|
|
|
|
Project Description: |
<required> |
|
|
ID |
Current |
Risk |
Probability of |
Risk |
Risk |
Project |
Risk Area |
Symptoms |
Triggers |
Risk Response |
Response Strategy |
1 |
Closed |
High |
High |
Closed |
Technical difficulties |
Project objectives would not be met |
Technology |
The project team experiences technical difficulties in designing and hosting the website |
The project team members do not have much experience with the tools and technologies used in the project |
Avoidance |
Onyx resources having significant experience of working with the chosen tools and platforms would be recruited |
2 |
Open |
Medium |
Medium |
Yellow |
High Staff turnover |
The project might not be completed within the deadline in case skilled resources leave the same. |
Project Management |
Skilled human resources associated with the project resign from their positons in large numbers |
Resources unhappy with pay/ prospects of the project |
Avoidance |
Develop legal contracts with resources before starting the project, thus restraining them from leaving the same within the estimated lifecycle. |
3 |
Open |
High |
Low |
Yellow |
Scope creep: Client end requests for functionalities or features that ae not covered in the initial requirement phase |
The project would take much longer to complete in case incorporation of the changes requested by the client demand restructuring/ redeveloping the website from scratch. |
Overall Project Failure |
Client suddenly makes requests of new sections to be added to the website |
The changes requested by the client are out of the scope identified in planning stage |
Avoidance |
The client should be informed of the fact that the requested changes are out of scope of the project |
4 |
Open |
Medium |
Low |
Green |
overscheduled project |
project is completed much before the planned end date |
Schedule |
Project activities require much less time than expected |
inefficient scheduling |
Acceptance |
utilize experience in next projects |
The quality management team associated with the project would be aimed at managing the project in a way such that that material and human resources of the project are harnessed in the most effective manner, thereby meeting all the project objectives in an efficient manner besides meeting the expectations of the stakeholder.
The team associated with the project under consideration might experience the under mentioned quality issues:
The following checklist highlights the task that have to be completed before the closure of the project:
On the other hand, the following techniques would be utilized for the evaluation of the project:
Ahern, T., Leavy, B., & Byrne, P. J. (2014). Complex project management as complex problem solving: A distributed knowledge management perspective. International Journal of Project Management, 32(8), 1371-1381.
Beringer, C., Jonas, D., & Kock, A. (2013). Behavior of internal stakeholders in project portfolio management and its impact on success. International Journal of Project Management, 31(6), 830-846.
Bresnen, M. (2016). Institutional development, divergence and change in the discipline of project management. International journal of project management, 34(2), 328-338.
Burke, R. (2013). Project management: planning and control techniques. New Jersey, USA.
Hornstein, H. A. (2015). The integration of project management and organizational change management is now a necessity. International Journal of Project Management, 33(2), 291-298.
Joslin, R., & Müller, R. (2015). Relationships between a project management methodology and project success in different project governance contexts. International Journal of Project Management, 33(6), 1377-1392.
Kaiser, M. G., El Arbi, F., & Ahlemann, F. (2015). Successful project portfolio management beyond project selection techniques: Understanding the role of structural alignment. International Journal of Project Management, 33(1), 126-139.
Kerzner, H. (2013). Project management: a systems approach to planning, scheduling, and controlling. John Wiley & Sons.
Leach, L. P. (2014). Critical chain project management. Artech House.
Lock, M. D. (2014). The essentials of project management. Ashgate Publishing, Ltd..
Martinsuo, M. (2013). Project portfolio management in practice and in context. International Journal of Project Management, 31(6), 794-803.
Mir, F. A., & Pinnington, A. H. (2014). Exploring the value of project management: linking project management performance and project success. International Journal of Project Management, 32(2), 202-217.
Reiss, G. (2013). Project management demystified: Today’s tools and techniques. Routledge.
Svejvig, P., & Andersen, P. (2015). Rethinking project management: A structured literature review with a critical look at the brave new world. International Journal of Project Management, 33(2), 278-290.
Teller, J., & Kock, A. (2013). An empirical investigation on how portfolio risk management influences project portfolio success. International Journal of Project Management, 31(6), 817-829.
Todorovi?, M. L., Petrovi?, D. ?., Mihi?, M. M., Obradovi?, V. L., & Bushuyev, S. D. (2015). Project success analysis framework: A knowledge-based approach in project management. International Journal of Project Management, 33(4), 772-783.
Too, E. G., & Weaver, P. (2014). The management of project management: A conceptual framework for project governance. International Journal of Project Management, 32(8), 1382-1394.
Turner, J. R. (2014). The handbook of project-based management (Vol. 92). New York, NY: McGraw-hill.
Essay Writing Service Features
Our Experience
No matter how complex your assignment is, we can find the right professional for your specific task. Contact Essay is an essay writing company that hires only the smartest minds to help you with your projects. Our expertise allows us to provide students with high-quality academic writing, editing & proofreading services.Free Features
Free revision policy
$10Free bibliography & reference
$8Free title page
$8Free formatting
$8How Our Essay Writing Service Works
First, you will need to complete an order form. It's not difficult but, in case there is anything you find not to be clear, you may always call us so that we can guide you through it. On the order form, you will need to include some basic information concerning your order: subject, topic, number of pages, etc. We also encourage our clients to upload any relevant information or sources that will help.
Complete the order formOnce we have all the information and instructions that we need, we select the most suitable writer for your assignment. While everything seems to be clear, the writer, who has complete knowledge of the subject, may need clarification from you. It is at that point that you would receive a call or email from us.
Writer’s assignmentAs soon as the writer has finished, it will be delivered both to the website and to your email address so that you will not miss it. If your deadline is close at hand, we will place a call to you to make sure that you receive the paper on time.
Completing the order and download