Discuss about the Linking Project Management Performance And Project.
The main goal of the program is to increase the productivity and considerably reduce the waste associated with the manufacturing process in order to improve the sustainability and error reduction in the production lines. Furthermore, the program aims at reducing the staff’s which is on an average is 32% per annum to 20% per annum. This aims at improving the skills levels and the efficiency of the firm by reducing the cost of recruitment and training of the new staffs. Reducing the employees’ turnover will only be possible by increasing the job satisfaction of the employees.
In order to achieve the set goal, the authorities have decided to divide the workers into five different teams. These teams will be responsible for manufacturing of five different product lines. This will ensure that each team is working on their specialty line only. This roster will be altered timely in order to enable every staffs to work on different lines.
In order to make the regular work more interesting John the production manager of the firm has suggested the teams to work in a particular goal or objective that is set for a particular product line. This goal will be based on reducing the error rate to only 4% from a rate of 22%. Along with this, it is essential that the productivity of the firm to be increased by 40% within 24 months.
The main activity of the program further includes the closing of the production lines for 48 hours. This time is needed for re tooling. The activities of re tooling include staff retraining. The retraining process will incorporate technical training, motivational training, training on quality control along with clear definition of goal and objectives. This will help in reducing the error in the production and manufacturing work and will keep the staffs and employees motivated as well.
The main objective of the transition is to redesign the production and the manufacturing process. This will help in increasing the productivity of the firm. Waste reduction is further essential for which it is essential to design an error free product. The objective of this program is to reduce the error lines up to 20% in order to reduce the sustainability.
The firm has seen quite a huge number of employee losses in recent years. Therefore the secondary objective of the program is to reduce the staff turnover from a rate of 32% per annum to 20% per annum. This objective aims at reducing the costs of recruiting and training of new staffs every year.
Another significant objective of this program is to close the production lines for 48 hours for retooling. In this period, the staffs will be retrained in order to improve their skills and knowledge.
The key performance indicators of the program will be reduction in the error rate in order to reduce the wastes associated with the manufacturing process. The current error rate is 22% which must be reduced to 4% for improving the sustainability of the organization. The staff workers are divided into five teams in order to ensure that each work supervised by them is done with perfection. Since a team will be working on a single speciality line, it would be easier for them to manage the production works. The rosters that are keeping a track of the team members will be altered on a regular basis in order to ensure that each member of the organization are getting to work on every speciality line.
Therefore the key performance indicator or the measures of the success of the transition would definitely be the reduction in the error rates, the increase in the production and reduction of the wastes and reduction in the employee turnover after a timeline of 24 months.
In order to improve the efficiency of the team members, each team member is allocated a team and the team will be responsible for manufacturing of five product lines. The rosters for the teams will be altered during a 12-hour shift. The main objective of the program is to reduce the error rates and increase in the productivity by bringing certain modifications in the process. Fir this, a time frame of 24 months is set. Furthermore in order to bring certain modifications in the process the production lines will remain closed for a time frame of 48 hours in order to provide certain essential training to the staffs. This training program is expected to improve the skills and knowledge of the workers that is essential in order to increase the productivity.
The employees will be trained and motivated in order to increase their interest in the job and reduce the employee turnover.
In order to reduce the negative impact on the people, a feedback path was established in order to review the perspectives of the workers associated with the new transition.
The activities of the communication include regular follow up with the employees and staffs in order to understand their views about the implementation of new process.
The objective of the communication is to improve the productivity of the employees by keeping them motivated and assigning them with a particular speciality line to work with.
The key performance indicator for the communication plan includes increase in the jiob satisfaction of the employees and reduction in employees’ turnover.
The activities that are undertaken in order to promote the process and regular sustainability are to arrange regular meetings so that the issues of the employees are addressed.
In order to ensure that the transition and communication has no negative impact on people, it was ensured that regular follow up with the members of a particular speciality line is taken.
One of the significant implementation uses is that the workers may not be interested in the process and might feel bored about managing a particular speciality line. This might in turn reduce the production by a considerable amount. As a contingency plan, the employees can be motivated to set a realistic goals and not lectured about their mistake. A proper leadership should be ensured in order to make the implementation successful.
Another implementation issue that can be faced is that the expected ROI does not match as the timeframe for all the reforms is too short.
As a contingency plan, it is suggested that the economic feasibility and NPV of the implementation of the transition project is done before the project initiation.
The review was done after eight weeks and the issues and failures of the new program are as follows-
After 16 weeks it was reviewed once again, the issues include-
The failures of the new program includes-
The amendments in the action plan are as follows-
The amendments in the contingency plans are as follows-
The schedule is prepared for a timeframe of 1 week which will be repeated every week expect the activity of employees’ training.
Task Name |
Duration |
Start |
Finish |
Predecessors |
Continuous Improvements |
9 days |
Tue 15-05-18 |
Fri 25-05-18 |
|
Employees training on specifications of the machines and their target goal |
2 days |
Tue 15-05-18 |
Wed 16-05-18 |
|
Follow up on project progress |
1 day |
Thu 17-05-18 |
Thu 17-05-18 |
1 |
Leader keeping his team motivated |
1 day |
Thu 17-05-18 |
Thu 17-05-18 |
1 |
change in shift time of the employees |
1 day |
Fri 18-05-18 |
Fri 18-05-18 |
3 |
regular meetings to address the issues of the employees |
1 day |
Fri 18-05-18 |
Fri 18-05-18 |
3 |
regular follow up on the progress report |
1 day |
Mon 21-05-18 |
Mon 21-05-18 |
5 |
Employee motivational programs |
2 days |
Fri 18-05-18 |
Mon 21-05-18 |
3 |
Quality check and quality improvement program |
4 days |
Tue 22-05-18 |
Fri 25-05-18 |
6 |
The schedule Gantt chart is represented below-
Figure 1: Representing the Gantt chart of the shifting project
(Source: Generated by Author using MS project)
The work activities marked in red in the Gantt chart above depict the critical path of the project
Burke, R. (2013). Project management: planning and control techniques. New Jersey, USA.
Harrison, F., & Lock, D. (2017). Advanced project management: a structured approach. Routledge.
Heagney, J. (2016). Fundamentals of project management. AMACOM Div American Mgmt Assn.
Kerzner, H., & Kerzner, H. R. (2017). Project management: a systems approach to planning, scheduling, and controlling. John Wiley & Sons.
Larson, E. W., & Gray, C. (2013). Project management: The managerial process with MS project. McGraw-Hill.
Leach, L. P. (2014). Critical chain project management. Artech House.
Mir, F. A., & Pinnington, A. H. (2014). Exploring the value of project management: linking project management performance and project success. International journal of project management, 32(2), 202-217.
Nicholas, J. M., & Steyn, H. (2017). Project management for engineering, business and technology. Taylor & Francis.
Snyder, C. S. (2014). A guide to the project management body of knowledge: PMBOK (®) guide. Project Management Institute: Newtown Square, PA, USA.
Yukl, G. A. (2013). Leadership in organizations. Pearson Education India.
Zulch, B. (2014). Leadership communication in project management. Procedia-Social and Behavioral Sciences, 119, 172-181.
Essay Writing Service Features
Our Experience
No matter how complex your assignment is, we can find the right professional for your specific task. Contact Essay is an essay writing company that hires only the smartest minds to help you with your projects. Our expertise allows us to provide students with high-quality academic writing, editing & proofreading services.Free Features
Free revision policy
$10Free bibliography & reference
$8Free title page
$8Free formatting
$8How Our Essay Writing Service Works
First, you will need to complete an order form. It's not difficult but, in case there is anything you find not to be clear, you may always call us so that we can guide you through it. On the order form, you will need to include some basic information concerning your order: subject, topic, number of pages, etc. We also encourage our clients to upload any relevant information or sources that will help.
Complete the order formOnce we have all the information and instructions that we need, we select the most suitable writer for your assignment. While everything seems to be clear, the writer, who has complete knowledge of the subject, may need clarification from you. It is at that point that you would receive a call or email from us.
Writer’s assignmentAs soon as the writer has finished, it will be delivered both to the website and to your email address so that you will not miss it. If your deadline is close at hand, we will place a call to you to make sure that you receive the paper on time.
Completing the order and download