This project depicts the importance of project management tools and technologies in the “Rock and Bands” project. Including the project manager all the members of the project are required to act proper roles responsibilities as well. Not only this but also the project management company is specializes in managing project professionally with a minimum rate of cost and time well. Due to proper management activities, the project management team members will be able to make all the possible and successful applications to meet the requirements of the consumers. Apart from this the project management team members and the project manager are required to have proper knowledge regarding managing the project.
The project report demonstrates and explains a list of project management actions those must be applied for completing the project successfully. In addition to this, lists of knowledge are provided hose are required for the successful completion of the project. Besides the management knowledge the project manager must identify proper and important tools and technologies those are also elaborated this project. After considering all the rules and regulations, the project manager is required to segment the activities properly so that, work burden gets reduced absolutely. A Gantt chart has been developed by the project manager to allot the tasks to all the team members considering the given conditions.
In order to complete the Rock sand Band project the project manger is required to allot proper project time and budget as well. Work Breakdown Structure (WBS) is the main activity that must be done by the project manager. In order to complete the task within estimated budget and lesser amount of time the list of activities that has been assigned by the project manager includes the below:
Name of the activities |
Project initiation |
Proper understanding of the project |
Development of project budget |
Resource assessment |
Data gathering |
Data analysis |
Contract negotiation with the selected groups of music |
Finding the construction firm and stage build up |
Project planning |
Developing the project activities |
Time allotment |
Contract negotiation with a roadie |
Risk assessment |
Screening and hiring the security personnel |
Arrangement of ticket distribution |
Organization of brochure for advertisement |
Printing the souvenir programs |
Arrangement of proper logistics for the music group transportation |
Arrangement of sound groups |
Project execution |
For the international participants processing travel visa |
Hiring parking staffs and making parking arrangement |
Distribution of the media passes and arrangement for the MTV recording |
Arrangement for the concession sales and restroom facilities for the participants |
Project closure |
Stakeholder signoff |
Development of a secured relationship between the project manager and the project team members |
Post project analysis |
In order to execute this project in term of musical event organization, the project manager and the members of the project team are required to possess certain professional knowledge. The list of knowledge those the project managers are required to possess include:
Communication: The Company must use proper open communication so that all the members of the project and the project manager both could communicate with other properly. With the help of the open communication the employees and the managers will be able to communicate with each other without any sort of hesitation. The project manager should consider the skills and ideas of all the other team members so that the project could be executed absolutely successfully.
Leadership: Leadership is another feature that the project manager should strictly possess in order to execute the project successfully in the company. With the help of proper leadership approaches the team members will feel motivated and due to the motivation they will be able to complete the task within the allotted time phase and budget as well.
Team management: Team management is another important aspect that is needed to be considered by the project manager before executing the project professionally within actual time and budget as well. With the help of the feasibility study the project budget could be estimated properly. From the strategic perspectives it has been found that the project manager needs to manage the project from the operational point of view. With proper team work the issues of intra and inter organizational conflict could be completely mitigated.
Security development: Security is another important thing about which the project manager must possess certain knowledge as in this particular project many musical groups will take art thus their personnel details are required to be secured from the external attackers. With the help of encryption approach none of the external users will be able to access information from the server and even if any data is found to be important to get transferred then also the data transfer channels are needed to keep secured from the external attackers.
Risk management: Before executing the project all the risks should be considered and their possible mitigation approaches are needed to be installed by the project manager and the members of the project team.
For successful completion of a project certain tools and technologies are there those are required to be considered for this particular project. With the help of these tools the primary features of a project could be reached by the project manager. The features are as follows:
The tools needed to complete the project includes: PERT chart and Gantt chart.
These tools have certain importance and those are as follows:
Task Name |
Duration |
Start |
Finish |
Predecessors |
Project initiation |
177 days |
Mon 6/26/17 |
Tue 2/27/18 |
|
Proper understanding of the project |
64 days |
Mon 6/26/17 |
Thu 9/21/17 |
|
Development of project budget |
2 days |
Mon 6/26/17 |
Tue 6/27/17 |
|
Resource assessment |
2 days |
Wed 6/28/17 |
Thu 6/29/17 |
2 |
Data gathering |
2 days |
Fri 6/30/17 |
Mon 7/3/17 |
3 |
Data analysis |
2 days |
Tue 7/4/17 |
Wed 7/5/17 |
4 |
Contract negotiation with the selected groups of music |
21 days |
Thu 7/6/17 |
Thu 8/3/17 |
5 |
Finding the construction firm and stage build up |
35 days |
Fri 8/4/17 |
Thu 9/21/17 |
6 |
Project planning |
76 days |
Fri 9/22/17 |
Fri 1/5/18 |
|
Developing the project activities |
4 days |
Fri 9/22/17 |
Wed 9/27/17 |
7 |
Time allotment |
4 days |
Thu 9/28/17 |
Tue 10/3/17 |
9 |
Contract negotiation with a roadie |
14 days |
Wed 10/4/17 |
Mon 10/23/17 |
10 |
Risk assessment |
5 days |
Tue 10/24/17 |
Mon 10/30/17 |
11 |
Screening and hiring the security personnel |
21 days |
Tue 10/31/17 |
Tue 11/28/17 |
12 |
Arrangement of ticket distribution |
7 days |
Wed 10/4/17 |
Thu 10/12/17 |
10 |
Organization of brochure for advertisement |
21 days |
Wed 11/29/17 |
Wed 12/27/17 |
13 |
Printing the souvenir programs |
7 days |
Fri 10/13/17 |
Mon 10/23/17 |
14 |
Arrangement of proper logistics for the music group transportation |
7 days |
Thu 12/28/17 |
Fri 1/5/18 |
15,16 |
Arrangement of sound groups |
21 days |
Wed 11/29/17 |
Wed 12/27/17 |
11,13 |
Project execution |
146 days |
Fri 8/4/17 |
Fri 2/23/18 |
|
For the international participants processing travel visa |
35 days |
Mon 1/8/18 |
Fri 2/23/18 |
17,18 |
Hiring parking staffs and making parking arrangement |
28 days |
Mon 1/8/18 |
Wed 2/14/18 |
7,22,17,18 |
Distribution of the media passes and arrangement for the MTV recording |
35 days |
Fri 8/4/17 |
Thu 9/21/17 |
6 |
Arrangement for the concession sales and restroom facilities for the participants |
14 days |
Thu 12/28/17 |
Tue 1/16/18 |
15 |
Project closure |
9 days |
Thu 2/15/18 |
Tue 2/27/18 |
|
Stakeholder signoff |
2 days |
Mon 2/26/18 |
Tue 2/27/18 |
20 |
Development of a secured relationship between the project manager and the project team members |
2 days |
Thu 2/15/18 |
Fri 2/16/18 |
21 |
Post project analysis |
2 days |
Mon 2/19/18 |
Tue 2/20/18 |
26 |
Table: Gantt chart for rock and Band Project
(Source: created by author)
Conclusion
From the overall discussion it can be concluded that proper decision making is the most important thing that is very much important to ensure the project has completed successfully. In order to complete the Rock and Bands project the project manager must use proper tools and technologies and also should divide the project activities evenly to complete the project within allotted time phase and within the estimated budget as well. According to the provided condition there are 12 activities and none of the activities, could start before the completion of other activities. The tools and technologies used in this project are demonstrated and the project must ensure that the project is being completed within the estimated budget and time as well. In addition to this, the list of knowledge those are needed to be acquired by the project managers and project management team members are also illustrated in this paper.
Braglia, M. and Frosolini, M., 2014. An integrated approach to implement project management information systems within the extended enterprise. International Journal of Project Management, 32(1), pp.18-29.
Burke, R., 2013. Project management: planning and control techniques. New Jersey, USA.
Fernandes, G., Ward, S. and Araújo, M., 2015. Improving and embedding project management practice in organisations—A qualitative study. International Journal of Project Management, 33(5), pp.1052-1067.
Flyvbjerg, B., 2013. Quality control and due diligence in project management: Getting decisions right by taking the outside view. International Journal of Project Management, 31(5), pp.760-774.
Hwang, B.G. and Ng, W.J., 2013. Project management knowledge and skills for green construction: Overcoming challenges. International Journal of Project Management, 31(2), pp.272-284.
Ika, L.A., 2015. Opening the black box of project management: Does World Bank project supervision influence project impact?. International Journal of Project Management, 33(5), pp.1111-1123.
Kerzner, H., 2013. Project management: a systems approach to planning, scheduling, and controlling. John Wiley & Sons.
Larson, E.W. and Gray, C., 2013. Project Management: The Managerial Process with MS Project. McGraw-Hill.
Leach, L.P., 2014. Critical chain project management. Artech House.
Mir, F.A. and Pinnington, A.H., 2014. Exploring the value of project management: linking project management performance and project success. International journal of project management, 32(2), pp.202-217.
Schwalbe, K., 2015. Information technology project management. Cengage Learning.
Serra, C.E.M. and Kunc, M., 2015. Benefits realisation management and its influence on project success and on the execution of business strategies. International Journal of Project Management, 33(1), pp.53-66.
Verzuh, E., 2015. The fast forward MBA in project management. John Wiley & Sons.
Walker, A., 2015. Project management in construction. John Wiley & Sons.
Essay Writing Service Features
Our Experience
No matter how complex your assignment is, we can find the right professional for your specific task. Contact Essay is an essay writing company that hires only the smartest minds to help you with your projects. Our expertise allows us to provide students with high-quality academic writing, editing & proofreading services.Free Features
Free revision policy
$10Free bibliography & reference
$8Free title page
$8Free formatting
$8How Our Essay Writing Service Works
First, you will need to complete an order form. It's not difficult but, in case there is anything you find not to be clear, you may always call us so that we can guide you through it. On the order form, you will need to include some basic information concerning your order: subject, topic, number of pages, etc. We also encourage our clients to upload any relevant information or sources that will help.
Complete the order formOnce we have all the information and instructions that we need, we select the most suitable writer for your assignment. While everything seems to be clear, the writer, who has complete knowledge of the subject, may need clarification from you. It is at that point that you would receive a call or email from us.
Writer’s assignmentAs soon as the writer has finished, it will be delivered both to the website and to your email address so that you will not miss it. If your deadline is close at hand, we will place a call to you to make sure that you receive the paper on time.
Completing the order and download