Corwin Corporation was taking up a new project for the development of the specialized product which for the first time included R&D work for a client, Peters Corporation. The company had been very stringent while taking up the projects earlier and always abiding by their policies that allowed the teams to take only those projects with potential of same margins as other products, possibility of follow up contracts, ability to develop a new product line, and causing minimum disruption to the existing product lines. The Peter company’s product did offer an option to create a new product line as well as possibility of follow up contracts (Michigan Department of Transportation, 2005).
However, the margins were tight and the project could not be done with a minimum disruption. Major changes were required to be done. The company was sitting on the holiday season where most senior level employees were on leave and when the company had to take fast decisions, they decided to involve people from manufacturing department for handling project unlike the earlier projects that were previously handled by people from marketing departments. Also, because of addition of an in-house representative from the client organization, there was a cultural clash. In this situation, the company was required to establish some change control processes.
Adoption of the new project needed several changes to be made in the way organization worked on previous projects. These changes included:
Choice of Project Manager from Engineering Department left the new person in lack of control as he was not used to dealing with project management. Because of this lack of control, Ray could take over the control and decide on project direction. Because of Ray taking control over the decision and adding new tests to the project. This increased the scope of the project in the due time (PM4DEV, 2016).
With the entry of the new person and the conflicts cause between the project manager West and in-house representative Ray, the project changed direction twice with new tests introduction that needed modification of the test matrix. With new tests, satisfactory results could still not be obtained and the project got delayed in its delivery on time. By the time, the project had already reached the initial deadline, the company was only planning for new matrix to introduce to get the project back on track (Wickboldt, 2011).
With no previous clarity on the tests to be added and the freedom taken by Ray, new tests were introduced that needed new environment to be developed for testing. Because of this change, the cost increased for the company and the project could not be completed on the budget as the company got into a cost overrun situation (SAEO, 2015).
As the two people working on the project were from different companies, they had different specifications for tests. There was no clarity on what tests to be performed and no preparation for how they would deliver the right results. This resulted into dissatisfactory results of the tests performance and thus, the quality of the project suffered (Michigan Department of Transportation, 2005).
A number of different management techniques could be used for bringing and controlling change in the organization such as:
Change Request Form
Project Name |
New Rubber Product Material R&D and Production |
Date |
17/08/2018 |
Project Number |
1 |
Requestor |
Patrick Ray |
Project Manager |
Dan West |
Project Owner |
B. Royce |
Describe the Requested Change |
|
Addition of 5 new tests |
|
Creation of new test environment for new tests |
|
Procurement of new materials for setting up test environment |
Describe the Reason for the Request |
|
Previous tests did not deliver desired results |
|
the project need a change in direction |
|
Demanded by client |
|
Describe Alternative Options |
|
Risk Identification/Analysis |
|
The new tests can still fail and not deliver satisfactory results |
|
If new tests do not give desired results, the project would need another change in direction with addition of other tests |
|
If project costs get escalated, extra cots would be borne by Corwin |
|
Impact Analysis |
|
Work Products to be Modified |
Version Number |
1. Test procedures & Environment |
1 |
2. Project schedule |
1 |
3. Materials to procure for test (Quigley, 2017) |
1 |
Describe the impact of the suggested change to work that is already complete. |
Quality Impact |
|||
Additional Quality Assurance or Quality Control Activities |
|||
1. Review meeting between project manager and stakeholders to verify requirements |
|||
2. Change register to record changes, their approval status, responsible person, and impact on project |
|||
3. QA Review to check project progress |
|||
Describe the impact of the change to quality assurance activities and quality control activities. |
|||
Schedule Impact |
|||
New Deliverables Description |
Effort Hours |
Date Required |
Impact to Other Delivery Dates |
1. New 5 tests to be added |
50 |
20th Aug 2018 |
Delays added |
2. Changes in the testing procedures |
10 |
30th Aug 2018 |
Delays added |
3. Project needing new testing environment to be set up |
20 |
20th Sept 2018 |
Delays added |
Based on the impact, state the estimated date for implementing the requested change. State the new estimated project completion date. |
Budget Impact |
|||
New Deliverables Description |
Lessen or Eliminate Other Expenses? Please describe. |
Cost of New Deliverable |
Total |
1. New 5 tests to be added |
$30,000 already invested |
$30,000 |
|
2. Changes in the testing procedures |
$12,000 would be added |
$12,000 |
|
3. Project needing new testing environment to be set up |
$6,700 added |
$6,700 |
|
Describe the overall impact to budget/cost. |
Decision |
||||
Approved |
Rejected |
|||
Approved with modifications |
Deferred |
|||
Justifications |
||||
Additional Comments |
Conclusions
This report discusses the case of Corwin Corporation that had taken up a new project for the development of the specialized product from a big client, Peters Corporation. The company had been very stringent while taking up the projects earlier but this time it relaxed some of its rules and made an urgent call on the project. However, the project got intro troubles with changes happening in the organization. The report discussed the needed changes that included change in project scope, change in control structure, and change in working style. The company needed to adopt change control procedures to be able to tackle these issues which it did not. Some of the change management tools that could have helped the organization were identified including RACI matrix for resource management, WBS for task management, and risk matrix for risk management. it was found that with appropriate change control planning, many issues could have been avoided and the project could have succeeded.
References
Ali Heydari. (2013). Types of contract in Project management. RoyalPoolir .
Galway, L. (2004). Quantitative Risk Analysis for Project Management. Rand Corporation.
Michigan Department of Transportation. (2005). Quality Assurance and Quality Control Process Guide For Project Managers. MDOT Trunkline Projects.
PM4DEV. (2016). Project Quality Management: PROJECT MANAGEMENT FOR DEVELOPMENT ORGANIZATIONS. PM4DEV.
Quigley, R. (2017). Quality Assurance/ Quality Control. FDOT.
Resuriz, R., & Elizondo, T. (2010). Quality Assurance/Quality Control Plan. ASARCO .
SAEO. (2015). Cost Estimating Manual for Projects . SAEO.
State of Kansas. (2011). Change Control Process Guide. Department of Administration, Division of Information Systems and Communications (DISC).
Wickboldt, J. A. (2011). A framework for risk assessment based on analysis of historical information of workflow execcution in IT systems. LUME.
Essay Writing Service Features
Our Experience
No matter how complex your assignment is, we can find the right professional for your specific task. Contact Essay is an essay writing company that hires only the smartest minds to help you with your projects. Our expertise allows us to provide students with high-quality academic writing, editing & proofreading services.Free Features
Free revision policy
$10Free bibliography & reference
$8Free title page
$8Free formatting
$8How Our Essay Writing Service Works
First, you will need to complete an order form. It's not difficult but, in case there is anything you find not to be clear, you may always call us so that we can guide you through it. On the order form, you will need to include some basic information concerning your order: subject, topic, number of pages, etc. We also encourage our clients to upload any relevant information or sources that will help.
Complete the order formOnce we have all the information and instructions that we need, we select the most suitable writer for your assignment. While everything seems to be clear, the writer, who has complete knowledge of the subject, may need clarification from you. It is at that point that you would receive a call or email from us.
Writer’s assignmentAs soon as the writer has finished, it will be delivered both to the website and to your email address so that you will not miss it. If your deadline is close at hand, we will place a call to you to make sure that you receive the paper on time.
Completing the order and download