The “remote area Microgrids” being developed in remote areas of far NW West Australia consist of basically a zone substation supplying a local town supply, a long distribution feeder of poor reliability which supplies a small remote town some distance from the main zone substation supply. The remote town system is arranged in a normally open local ring.
MV: Group A=11 kV, Group B=13.8 kV, Group C=16.8 kV; balanced 3-phase.
F1, F2, F3, F4 are fault locations. Fault level on zone substation MV bus = Group A 200 MVA, Group B 250 MVA, Group C 300 MVA for balanced 3-phase; and Group A 200 MVA, Group B 250 MVA, Group C 350 MVA for single-phase to earth faults.
Line segments: Line from Bus 1to Bus 2: 1 km of impedance = 0.27 + j0.31 ohms/km; Line from Bus 2 to Bus 3: 10 km of impedance = Group A 0.38 + j0.32, Group B 0.475 + j0.40, Group C 0.57 + j0.48 ohms/km; each arm of remote microgrid ring (i.e. Bus 3 to Bus 4): 1 km of impedance = Group A 0.38 + j0.32, Group B 0.475 + j0.40, Group C 0.57 + j0.48 ohms/km. These are positive sequence impedances. Assume negative sequence impedances equal positive sequence and zero sequence impedances are 2.5 times the positive sequence.
Line loading: Line from Bus 1to Bus 2 (town distribution network) group A 1,000 kVA; group B 1,250 kVA; group C 1,500 kVA. Line from Bus 2 to Bus 3: Group A 500kVA; Group B 625kVA; Group C 750kVA; each arm of remote microgrid ring (i.e. Bus 3 to Bus 4):group A 500kVA; Group B 625kVA; Group C 750kVA each, total 1,000/1250/1500 kVA. All loads are at 0.9 PF lagging and evenly distributed along the line segments.
The distributed generators (DG’s) in the remote microgrid are all solar PV types. Peak output equals the peak load in the microgrid. The DG inverter fault levels are regulated by the inverter controls to 2.0 times full load current for both three-phase and single-phase to earth faults. Internal impedance appears to the circuit to be highly resistive.
Main system protection: Overcurrent and earth fault relays are provided at CB3, CB4 and both CB1’s.
Please undertake the following analyses:
Calculate the 3-phase fault levels on Bus 2, Bus 3 and Bus 4 with the main supply connected but DG’s disconnected. Then calculate the fault levels on Bus 3 and Bus 4 with the microgrid islanded (synch switch open). To do this, assume that there is a total of (group A/B/C) 500/625/750 kW of DG output in the centre of each arm of the
Zero sequence impedance:
Positive sequence impedance:
Negative sequence impedance:
Assume line to line fault between lines b and c:
The first step in solving questions 2-5 is to determine the zero, negative and positive sequence impedance when looked from bus 2. We then draw the sequence diagram which will assist us in calculating the equivalent Thevanin’s impedance. We then use the formulas in the lecture notes to determine the sequence currents.
The voltage magnitude and phase currents for each bus and corresponding phase are shown below;
Number |
Name |
Phase Volt B |
Phase Volt C |
Phase Ang A |
Phase Ang B |
Phase Ang C |
|
1 |
One |
0.64022 |
0.64022 |
0.64022 |
0 |
-120 |
120 |
2 |
Two |
0.51217 |
0.51217 |
0.51217 |
0 |
-120 |
120 |
3 |
Three |
0.69145 |
0.69145 |
0.69145 |
0 |
-120 |
120 |
4 |
Four |
0.20484 |
0.20484 |
0.20484 |
0 |
-120 |
120 |
5 |
Five |
0.79389 |
0.79389 |
0.79389 |
0 |
-120 |
120 |
6 |
Six |
0 |
0 |
0 |
0 |
0 |
0 |
7 |
Seven |
0.78108 |
0.78108 |
0.78108 |
0 |
-120 |
120 |
Table 4: Per unit bus voltage magnitude
Number of Bus |
Name of Bus |
Phase Cur A |
Phase Cur B |
Phase Cur C |
Phase Ang A |
Phase Ang B |
Phase Ang C |
5 |
Five |
0.64028 |
0.64028 |
0.64028 |
-90 |
150 |
30 |
6 |
Six |
4.375 |
4.375 |
4.375 |
-90 |
150 |
30 |
7 |
Seven |
0.89639 |
0.89639 |
0.89639 |
-90 |
150 |
30 |
Table 5: Per unit current values supplied by each generator
Number of Bus |
Name of Bus |
Phase Cur A |
Phase Cur B |
Phase Cur C |
Phase Ang A |
Phase Ang B |
Phase Ang C |
5 |
Five |
26787.18 |
26787.18 |
26787.18 |
-90 |
150 |
30 |
6 |
Six |
140328.2 |
140328.2 |
140328.2 |
-90 |
150 |
30 |
7 |
Seven |
25876.41 |
25876.41 |
25876.41 |
-90 |
150 |
30 |
Table 6: Actual current values(A) supplied by each generator
Calculate the voltage drop at Bus 3 with the main supply connected but DG’s disconnected at peak loading. Assume even loading; the volt drop is then equal to (half total load at the end of the line) * (line impedance). Then calculate the voltage drop at Bus3 and Bus 4 with the microgrid islanded, again at peak loading times. Although microgrid loads and DG’s are evenly spread around the whole microgrid ring, for the purposes of modelling assume that the total microgrid peak load of (group A/B/C) 1000/1250/1500 kW is met by the DG’s modelled as before as two of (group A/B/C) 500/625/750 kW sources, one in the middle of each arm of the microgrid.
When a fault is placed at Bus 2
The voltage magnitude and phase currents for each bus and corresponding phase are shown below;
Number |
Name |
Phase Volt A |
Phase Volt B |
Phase Volt C |
Phase Ang A |
Phase Ang B |
Phase Ang C |
1 |
One |
0.25 |
0.25 |
0.25 |
0 |
-120 |
120 |
2 |
Two |
0 |
0 |
0 |
0 |
0 |
0 |
3 |
Three |
0.35 |
0.35 |
0.35 |
0 |
-120 |
120 |
4 |
Four |
0.3663 |
0.3663 |
0.3663 |
0 |
-120 |
120 |
5 |
Five |
0.55 |
0.55 |
0.55 |
0 |
-120 |
120 |
6 |
Six |
0.61044 |
0.61044 |
0.61044 |
0 |
-120 |
120 |
7 |
Seven |
0.525 |
0.525 |
0.525 |
0 |
-120 |
120 |
Table 1: Per unit bus voltage magnitude
Number of Bus |
Name of Bus |
Phase Cur A |
Phase Cur B |
Phase Cur C |
Phase Ang A |
Phase Ang B |
Phase Ang C |
5 |
Five |
1.25 |
1.25 |
1.25 |
-90 |
150 |
30 |
6 |
Six |
1.8315 |
1.8315 |
1.8315 |
-90 |
150 |
30 |
7 |
Seven |
1.75 |
1.75 |
1.75 |
-90 |
150 |
30 |
Table 2: Per unit current values supplied by each generator
Number of Bus |
Name of Bus |
Phase Cur A |
Phase Cur B |
Phase Cur C |
Phase Ang A |
Phase Ang B |
Phase Ang C |
5 |
Five |
52296.22 |
52296.22 |
52296.22 |
-90 |
150 |
30 |
6 |
Six |
58745.45 |
58745.45 |
58745.45 |
-90 |
150 |
30 |
7 |
Seven |
50518.15 |
50518.15 |
50518.14 |
-90 |
150 |
30 |
Table 3:Actual current values(A) supplied by each generator
7.25: When the fault is placed at bus 6, the following results are obtained;
The voltage magnitude and phase currents for each bus and corresponding phase are shown below;
Number |
Name |
Phase Volt A |
Phase Volt B |
Phase Volt C |
Phase Ang A |
Phase Ang B |
Phase Ang C |
1 |
One |
0.64022 |
0.64022 |
0.64022 |
0 |
-120 |
120 |
2 |
Two |
0.51217 |
0.51217 |
0.51217 |
0 |
-120 |
120 |
3 |
Three |
0.69145 |
0.69145 |
0.69145 |
0 |
-120 |
120 |
4 |
Four |
0.20484 |
0.20484 |
0.20484 |
0 |
-120 |
120 |
5 |
Five |
0.79389 |
0.79389 |
0.79389 |
0 |
-120 |
120 |
6 |
Six |
0 |
0 |
0 |
0 |
0 |
0 |
7 |
Seven |
0.78108 |
0.78108 |
0.78108 |
0 |
-120 |
120 |
Table 4: Per unit bus voltage magnitude
Number of Bus |
Name of Bus |
Phase Cur A |
Phase Cur B |
Phase Cur C |
Phase Ang A |
Phase Ang B |
Phase Ang C |
5 |
Five |
0.64028 |
0.64028 |
0.64028 |
-90 |
150 |
30 |
6 |
Six |
4.375 |
4.375 |
4.375 |
-90 |
150 |
30 |
7 |
Seven |
0.89639 |
0.89639 |
0.89639 |
-90 |
150 |
30 |
Table 5: Per unit current values supplied by each generator
Number of Bus |
Name of Bus |
Phase Cur A |
Phase Cur B |
Phase Cur C |
Phase Ang A |
Phase Ang B |
Phase Ang C |
5 |
Five |
26787.18 |
26787.18 |
26787.18 |
-90 |
150 |
30 |
6 |
Six |
140328.2 |
140328.2 |
140328.2 |
-90 |
150 |
30 |
7 |
Seven |
25876.41 |
25876.41 |
25876.41 |
-90 |
150 |
30 |
Table 6: Actual current values(A) supplied by each generator
7.26: When fault is placed midway between buses 2 and 3;
This is done by right setting the location at 50%
The voltage magnitude and phase currents for each bus and corresponding phase are shown below;
Number |
Bus Name |
Phase Volt A |
Phase Volt B |
Phase Volt C |
Phase Ang A |
Phase Ang B |
Phase Ang C |
1 |
One |
0.43151 |
0.43151 |
0.43151 |
0 |
-120 |
120 |
2 |
Two |
0.23823 |
0.23823 |
0.23823 |
0 |
-120 |
120 |
3 |
Three |
0.21 |
0.21 |
0.21 |
0 |
-120 |
120 |
4 |
Four |
0.52142 |
0.52142 |
0.52142 |
0 |
-120 |
120 |
5 |
Five |
0.66344 |
0.66344 |
0.66344 |
0 |
-120 |
120 |
6 |
Six |
0.71017 |
0.71017 |
0.71017 |
0 |
-120 |
120 |
7 |
Seven |
0.42 |
0.21 |
0.21 |
0 |
180 |
180 |
8 |
Faultpt |
0.00000 |
0.00000 |
0.00000 |
0.00 |
0.00 |
0.00 |
Table 7: Per unit bus voltage magnitude
Number of Bus |
Name of Bus |
Phase Cur A |
Phase Cur B |
Phase Cur C |
Phase Ang A |
Phase Ang B |
Phase Ang C |
5 |
Five |
0.96639 |
0.96639 |
0.96639 |
-90 |
150 |
30 |
6 |
Six |
1.41595 |
1.41595 |
1.41595 |
-90 |
150 |
30 |
7 |
Seven |
2.1 |
2.1 |
2.1 |
-90 |
150 |
30 |
Table 8: Per unit current values supplied by each generator
Number of Bus |
Name of Bus |
Phase Cur A |
Phase Cur B |
Phase Cur C |
Phase Ang A |
Phase Ang B |
Phase Ang C |
5 |
Five |
40430.75 |
40430.75 |
40430.75 |
-90 |
150 |
30 |
6 |
Six |
45416.71 |
45416.71 |
45416.71 |
-90 |
150 |
30 |
7 |
Seven |
60621.78 |
60621.78 |
60621.78 |
-90 |
150 |
30 |
Table 9: Actual current values(A) supplied by each generator
For protection purposes, overcurrent and earth-fault relays are installed at CB’s CB3, CB4 and each CB1. The overcurrent relays at each CB has a pick-up current, as reckoned in primary amps, of 200% of the peak load flowing at that point (the extra 100% is to prevent spurious tripping under peak load conditions). The single-phase to earth pickup currents can be set at 20% of the overcurrent (three-phase) setting on the corresponding overcurrent relay.
Design the overcurrent and earth fault relay settings (pick-up currents and time dial settings) at CB’s CB3, CB4 and each CB1 when the feeder is supplied by the main grid only. To do the design, start at the relays at CB1 and work your way up the feeder to the relays at CB3and CB4. Overcurrent relay pick-up currents will be set at 150% of load. The CB1relay time setting will be 0.1. Then, using time grading techniques (use 0.35 sec grading margin between relays) determine the settings for firstly overcurrent and then earth fault relays at CB2, CB3, and CB4. The earth fault relay pick-up current settings will be 20% of the corresponding overcurrent relay setting. Again, start off with a CB1 relay time setting of 0.1, and use the standard inverse (SI) characteristic. You can calculate directly from the SI relay formula, or use the overcurrent relay setting spreadsheet “Ocurrent.xls” which is provided for your use (or alternatively, make you own one!).
In questions 9-12 we are required to calculate the phase voltages at bus 3. Since we had already calculated the voltages at bus 2 we take the voltage sequence at bus 2 and sequence currents we then apply current divider rule to obtain currents flowing to or from bus 3. We then apply KVL to obtain the sequence voltages at bus 3 from where we convert the sequence voltage components to phase voltages.
Then analyse the situation in the microgrid when it is islanded. Will the overcurrent relays at each CB1 (Bus #3) detect microgrid faults when fed by the DG’s only? Suggest some solutions to the problem. As one possible solution, consider back-to-back directional overcurrent and earth fault relays at each CB1 and recommend settings for the backward direction.
No it will not detect the faults. Bus coupler and bus section circuit-breakers, are required to make and interrupt the maximum fault current associated with short-circuit infeeds from all connected circuits when energising a section of busbar which is still inadvertently earthed. The resultant direction of current flow in the substation is also indicated. The making onto such a fault also imposes maximum duty on substation infrastructure equipment.
Essay Writing Service Features
Our Experience
No matter how complex your assignment is, we can find the right professional for your specific task. Contact Essay is an essay writing company that hires only the smartest minds to help you with your projects. Our expertise allows us to provide students with high-quality academic writing, editing & proofreading services.Free Features
Free revision policy
$10Free bibliography & reference
$8Free title page
$8Free formatting
$8How Our Essay Writing Service Works
First, you will need to complete an order form. It's not difficult but, in case there is anything you find not to be clear, you may always call us so that we can guide you through it. On the order form, you will need to include some basic information concerning your order: subject, topic, number of pages, etc. We also encourage our clients to upload any relevant information or sources that will help.
Complete the order formOnce we have all the information and instructions that we need, we select the most suitable writer for your assignment. While everything seems to be clear, the writer, who has complete knowledge of the subject, may need clarification from you. It is at that point that you would receive a call or email from us.
Writer’s assignmentAs soon as the writer has finished, it will be delivered both to the website and to your email address so that you will not miss it. If your deadline is close at hand, we will place a call to you to make sure that you receive the paper on time.
Completing the order and download