In this modern world of technology, traffic congestions are one of the crucial factors for the people of China and needs to be eliminated for the proper travelling. This project proposal aims at the objectives related to the delivery of the flyover construction on the “Road Network in Ulaanbaata” in China by the China State Construction Engineering. This flyover will be helpful in reducing the traffic congestions and increase the mobility in that area.
The purpose of this report is to present a project charter and cover all the objectives related to the flyover protection with a practical example. This project charter consists of objectives related to the project, schedule and milestones of the activities involved in the whole project, risk management that will cover the identified risks based on the past experience, and stakeholder analysis.
2. Project charter
2.1 Objectives of the project
Following are the objectives of the project:
2.2 Importance of the project to the organization
This project aims at enhancing the life living of the people of China through eliminating the traffic jams facing by the citizens travelling at “Road Network in Ulaanbaata” in China. This project charter will be helpful in proper planning of the project and deliver a successful project with maximum efficiency. This will be a big project and hence the organization might be able to sustain its competitive position in the market.
2.3 Scope of the project
It can be subdivided into the followings:
In-scope: Following are the in-scope of the project:
Out- Scope: Following are the out- scope of the project:
Flyover will be of length 3 km (3000 metres) of 15 degree slope and will be having a turn of 25 degree with a slope of 13 degree. It is identified that the flyover that was proposed to be constructed consists of 25 degree slope and it is of length 500 meters. It is estimated that the entire project of flyover construction will be completed in 1 year (Roads and Maritime Services 2017). In addition to this, proper central lightening arrangement was also present on the flyover bridge.
2.5 Milestone and schedule
Task Name |
Duration |
Start |
Finish |
Flyover Construction Project |
216 days |
Mon 11/27/17 |
Mon 9/24/18 |
Concept Phase |
216 days |
Mon 11/27/17 |
Mon 9/24/18 |
Concept Phase Project Management |
30 days |
Mon 11/27/17 |
Fri 1/5/18 |
Concept Phase project |
25 days |
Mon 1/8/18 |
Fri 2/9/18 |
Project Manager appointment |
20 days |
Mon 2/12/18 |
Fri 3/9/18 |
Project Proposal |
56 days |
Mon 3/12/18 |
Mon 5/28/18 |
Functional Scope and Requirements |
29 days |
Mon 3/12/18 |
Thu 4/19/18 |
Produce Project Proposal |
27 days |
Fri 4/20/18 |
Mon 5/28/18 |
Developing analysis and option |
30 days |
Tue 5/29/18 |
Mon 7/9/18 |
Business Case |
55 days |
Tue 7/10/18 |
Mon 9/24/18 |
Project Estimate and Risk Register |
40 days |
Tue 7/10/18 |
Mon 9/3/18 |
Financial Approval |
15 days |
Tue 9/4/18 |
Mon 9/24/18 |
Milestone 1 Achieved |
0 days |
Mon 9/24/18 |
Mon 9/24/18 |
Development Phase |
217 days |
Tue 9/25/18 |
Wed 7/24/19 |
Development Phase-Project |
82 days |
Tue 9/25/18 |
Wed 1/16/19 |
Project Plan |
25 days |
Tue 9/25/18 |
Mon 10/29/18 |
Preparation of the Design |
30 days |
Tue 10/30/18 |
Mon 12/10/18 |
Community Engagement |
27 days |
Tue 12/11/18 |
Wed 1/16/19 |
Preliminary Design |
45 days |
Thu 1/17/19 |
Wed 3/20/19 |
Detailed Design |
35 days |
Thu 3/21/19 |
Wed 5/8/19 |
Contract Documents |
10 days |
Thu 5/9/19 |
Wed 5/22/19 |
Procurement |
45 days |
Thu 5/23/19 |
Wed 7/24/19 |
Engaging contract administrator |
10 days |
Thu 5/23/19 |
Wed 6/5/19 |
Procure contractor |
15 days |
Thu 6/6/19 |
Wed 6/26/19 |
Contract Financial Approval |
20 days |
Thu 6/27/19 |
Wed 7/24/19 |
Milestone 2 Achieved |
0 days |
Wed 7/24/19 |
Wed 7/24/19 |
Implementation Phase |
130 days |
Thu 7/25/19 |
Wed 1/22/20 |
Project Plan Implementation |
10 days |
Thu 7/25/19 |
Wed 8/7/19 |
Stakeholders engagement |
15 days |
Thu 8/8/19 |
Wed 8/28/19 |
Regular audit and Meetings |
25 days |
Thu 8/29/19 |
Wed 10/2/19 |
Constructions |
50 days |
Thu 10/3/19 |
Wed 12/11/19 |
Stakeholders’ Roles and Responsibility |
25 days |
Thu 12/12/19 |
Wed 1/15/20 |
Official Opening |
5 days |
Thu 1/16/20 |
Wed 1/22/20 |
Milestone 3 Achieved |
0 days |
Wed 1/22/20 |
Wed 1/22/20 |
Finalizing Phase |
28 days |
Thu 1/23/20 |
Mon 3/2/20 |
Project Plan finalization |
5 days |
Thu 1/23/20 |
Wed 1/29/20 |
Defects liability period |
7 days |
Thu 1/30/20 |
Fri 2/7/20 |
Quality assurance |
10 days |
Mon 2/10/20 |
Fri 2/21/20 |
Documentation |
4 days |
Mon 2/24/20 |
Thu 2/27/20 |
Checking Initials on Each Paper |
2 days |
Fri 2/28/20 |
Mon 3/2/20 |
Milestone 4 Achieved |
0 days |
Mon 3/2/20 |
Mon 3/2/20 |
2.6 Risk Assessment
SL. No |
Threat/Risk Description |
Likelihood |
Impact |
Priority |
Mitigation |
R. 1 |
Increment in the budget: There are many causes of the increase in budget such as natural disaster or money spent for the contingencies. This will ultimately affect the whole project. |
M |
H |
M |
Budget Planning should be made considering all the factors that might affect the project. Contingency Plan should be saved up to 10 percent of the actual budget of the project. |
R. 2 |
Time Delay: Many unexpected events might occur during the execution of the project that might affect the scheduling of the project such as: no resources during winter season, terrorist attacks, fund withdrawals and many more. |
H |
VH |
H |
Leadership should be practiced in well and experienced manner |
R .3 |
Resources unavailability: There are the possibilities that during the execution of the project, resources are unavailable or not sufficient as compared to the strength of the staffs. |
L |
M |
VL |
Resource manager should take care of all the resource availability and should keep backup plan for the unavailability’s of the staffs or the resources. |
R. 4 |
Lack in Funding: Donors might fall back after committing to serve the project with donations. |
VL |
H |
L |
Proper documentation should be arranged at the very first stage of the project execution. Initials of the corresponding individuals should be taken on each paper. |
R. 5 |
Natural disaster: Many examples of the real world that can explain the severity of the damage that could be caused by such unwanted events. These events could affect the budget and schedule of the project. |
VL |
VH |
M |
These are unpredictable and unwanted events and contingency plan should cover these damages. |
R. 6 |
Improper managerial responsibilities: Managers might not be able control and motivate the employees to the respective goal of the organization. |
VL |
H |
VH |
Project manager should be chosen who is experienced and well qualified as per the need of the project. |
2.7 Required Resources
Following resources are required for the successful delivery of the project:
Human Resources: This will include unskilled and skilled labours such as: Project Manager, Labours, suppliers, donors, government, supervisors, and the civil engineers.
Financial Resources: The overall budget of the project will be AUD 300, 000. 00.
Material Resources: Sand, concrete, steel rods, vehicles for the transportation, work force, and many more materials are required for the completion of the project.
2.8 Stakeholder Analysis
Following is the list of internal and external stakeholders of the project:
Internal stakeholders
Site Engineer: He will be responsible for collecting the data and information related to the ongoing activities on the sites. He will also guide and motivate the unskilled labours to achieve the projected goal of the project.
Project Manager: It is the role of the project manager to manage the role and responsibilities of each stakeholder and motivate them towards the success of the project.
Civil Engineers: They will be responsible for designing and securing the designed model of the project.
Labours: They will contribute in the works those need to be done for the construction of the flyover such as, carrying beams, fixing concrete and many more.
Suppliers: Suppliers are the one who will be delivering the resources needed for the project.
External stakeholders
Common citizens of China: Citizens will be advantageous after the completion of the project
Donors: Donors will be funding for the project.
Chinese Government: Government will be funding the project.
2.9 Principles of the Teams
This will be emphasizing on the activities related to the proper communication between the team members, Completion of the project as per the scheduled budget and time, and proper utilization of the resources.
3.0 Conclusion
Based on the above charter it can be concluded that the project charter can be helpful in planning the project in an efficient and effective manner and deliver the project with enhanced output. The cost and activities represented in the project will be helpful for the manager in successfully delivering the project. The risk analysis is a better option for considering and identifying the risks in manner to execute them at the very early stage of the project.
Demirkesen, S., & Ozorhon, B. (2017). Impact of integration management on construction project management performance. International Journal of Project Management, 35(8), 1639-1654.
Fewings, P. (2013). Construction project management: an integrated approach. Routledge.
Fleming, Q. W., & Koppelman, J. M. (2016, December). Earned value project management. Project Management Institute.
Hajdu, M. (2013). Network scheduling techniques for construction project management (Vol. 16). Springer Science & Business Media.
Hegazy, T. (2013). Computer-Based Construction Project Management: Pearson New International Edition. Pearson Higher Ed.
Hwang, B. G., & Ng, W. J. (2013). Project management knowledge and skills for green construction: Overcoming challenges. International Journal of Project Management, 31(2), 272-284.
Kerzner, Harold. Project management: a systems approach to planning, scheduling, and controlling. John Wiley & Sons, 2013.
Nicholas, J. M., & Steyn, H. (2017). Project management for engineering, business and technology. Taylor & Francis.
Sears, S. K., Sears, G. A., Clough, R. H., Rounds, J. L., & Segner, R. O. (2015). Construction project management. John Wiley & Sons.
Sertyesilisik, B. (2014). Lean and agile construction project management: As a way of reducing environmental footprint of the construction industry. In Optimization and Control Methods in Industrial Engineering and Construction (pp. 179-196). Springer Netherlands.
Shen, Y., Tuuli, M. M., Xia, B., Koh, T. Y., & Rowlinson, S. (2015). Toward a model for forming psychological safety climate in construction project management. International Journal of Project Management, 33(1), 223-235
Walker, A. (2015). Project management in construction. John Wiley & Sons.
Essay Writing Service Features
Our Experience
No matter how complex your assignment is, we can find the right professional for your specific task. Contact Essay is an essay writing company that hires only the smartest minds to help you with your projects. Our expertise allows us to provide students with high-quality academic writing, editing & proofreading services.Free Features
Free revision policy
$10Free bibliography & reference
$8Free title page
$8Free formatting
$8How Our Essay Writing Service Works
First, you will need to complete an order form. It's not difficult but, in case there is anything you find not to be clear, you may always call us so that we can guide you through it. On the order form, you will need to include some basic information concerning your order: subject, topic, number of pages, etc. We also encourage our clients to upload any relevant information or sources that will help.
Complete the order formOnce we have all the information and instructions that we need, we select the most suitable writer for your assignment. While everything seems to be clear, the writer, who has complete knowledge of the subject, may need clarification from you. It is at that point that you would receive a call or email from us.
Writer’s assignmentAs soon as the writer has finished, it will be delivered both to the website and to your email address so that you will not miss it. If your deadline is close at hand, we will place a call to you to make sure that you receive the paper on time.
Completing the order and download