In this report, it mainly discussed about the detailed information related with the RALS Roistering project that mainly undertaken by Virtucon from Globex.
Measurable Organizational Value
The Rivererina Agriculture and Lifestyle Show held by BT & Sons Farming Equipments on November 2009. This particular show is mainly pre-arranged to display different agricultural equipments, products and so forth. From few years, RALS increases the business much in size and also requires having the active participation of numbers of volunteers to have successful demonstration. Numbers of professionals appointed by Globex managed all the data and information that mainly linked with all volunteers manually. On the other hand, managing all information becomes more time consuming process as volunteer numbers get increased in rapid manner. Hence, Globex undertook all tasks to develop the roistering system to store all details of volunteers who are participating in RALS.
The impact of project that observed in this project is mainly discussed below:
Sl. No |
Value |
Project Attribute |
1 |
Better |
Quality concern of project Data security |
2 |
Faster |
Response time |
3 |
Cheaper |
Resource cost |
4 |
Do more |
Storing of contact details of volunteers Storage of previous work experience of volunteers |
The following table provides an extensive analysis all the stakeholders associated with the project
Sl. No |
Stakeholder |
Target |
Expectation |
Organizational head |
Increase of business profit, retention of employees |
More profit outcomes |
|
Project Management team |
Proper management of project resources, time management to deliver the project on-time |
Proper delivery of the project depending on given time, costs etc |
|
Volunteers |
Customers |
Helps them to have the proper understanding about the Roistering system |
|
Employees |
Business |
Take active part to run the business and also in the earning of profit under guidance of project management team |
The estimated required time frame to achieve the measurable organizational value provided in the below table:
Task Name |
Duration |
Start |
Finish |
RALS Roster Project |
260 days |
Mon 01/02/17 |
Fri 12/29/17 |
Project starts |
0 days |
Mon 01/02/17 |
Mon 01/02/17 |
Phase 1: Project Startup |
25 days |
Mon 01/02/17 |
Fri 02/03/17 |
Phase 2: Solution Requirements Analysis |
36 days |
Mon 02/06/17 |
Mon 03/27/17 |
Phase 3: Solution Design |
47 days |
Tue 03/28/17 |
Wed 05/31/17 |
Phase 4: Prototype |
38 days |
Thu 06/01/17 |
Mon 07/24/17 |
Phase 5: Iteration 1 |
35 days |
Tue 07/25/17 |
Mon 09/11/17 |
Phase 6: Iteration 2 |
18 days |
Tue 09/12/17 |
Thu 10/05/17 |
Phase 7:Iteration 3 |
18 days |
Fri 10/06/17 |
Tue 10/31/17 |
Phase 8: Final Release |
10 days |
Wed 11/01/17 |
Tue 11/14/17 |
Phase 9: Project Completion |
33 days |
Wed 11/15/17 |
Fri 12/29/17 |
End of project |
0 days |
Fri 12/29/17 |
Fri 12/29/17 |
The below table mainly discussed about the summarization of MOV of the selected project:
Sl. No |
Measurable Organizational Value |
Attribute |
1 |
Goal of the project |
Development of an automated roster system to record all volunteers details who mainly participated in the RALS |
2 |
Area of impact |
Operational impact, Strategy, Financial, customer, society |
3 |
Stakeholder |
All employees of Globex including the organizational heads manage the all records of volunteers who mainly participated in RALS, and also the project team that mainly appointed by Virtucon |
4 |
Time schedule to achieve the MOV value |
260 day |
Scope of the Project
In Scope |
Includes |
System Functions |
The system mainly designed that allows to maintain the volunteers records who participated in RALS based on the below aspects: i. Names of Volunteers ii. Contact details iii. The organization who offers the services iv. Qualifications of volunteers |
System Documentation |
i. Use case models of system ii. Elaborated functional descriptions of system iii. Various hardware requirements to run the system |
The project will not provide:
Out of Scope |
Includes |
System support and enhancements |
Provide after sales support to client (installation of system) |
Training |
Giving training to all Globex employees who use the roistering system |
System maintenance |
The proper maintenance of system where the roster system are installed will not be taken in consideration within the scope of project |
Table 1: Resources required for the project
Resource Name |
Type |
Material Label |
Initials |
Group |
Max. Units |
Std. Rate |
Project Manager |
Work |
P |
100% |
$150.00/hr |
||
Business analyst |
Work |
B |
200% |
$80.00/hr |
||
System designer |
Work |
S |
500% |
$70.00/hr |
||
System developer |
Work |
S |
1,000% |
$70.00/hr |
||
System Tester |
Work |
S |
600% |
$70.00/hr |
||
Technical writers |
Work |
T |
300% |
$50.00/hr |
||
Hardware components required for developing the ICT system |
Material |
H |
$10,000.00 |
|||
Software components required for developing the ICT system |
Work |
S |
100% |
$0.00/hr |
||
Testing manager |
Work |
T |
100% |
$105.00/hr |
||
Development manager |
Work |
D |
100% |
$105.00/hr |
Work breakdown structure of the project
Table 1: Work breakdown structure of the project
Outline Number |
Task Name |
Duration |
Start |
Finish |
Predecessors |
Resource Names |
Cost |
0 |
RALS Rostering Project |
260 days |
Mon 01/02/17 |
Fri 12/29/17 |
$290,600.00 |
||
1 |
Project starts |
0 days |
Mon 01/02/17 |
Mon 01/02/17 |
Project Manager |
$0.00 |
|
2 |
Phase 1: Project Startup |
25 days |
Mon 01/02/17 |
Fri 02/03/17 |
$19,840.00 |
||
2.1 |
Gathering information regarding the client requirements |
5 days |
Mon 01/02/17 |
Fri 01/06/17 |
1 |
Business analyst |
$3,200.00 |
2.2 |
Developing a project charter |
3 days |
Mon 01/09/17 |
Wed 01/11/17 |
3 |
Business analyst, Technical writers |
$3,120.00 |
2.3 |
Developing an initial management plan of the project |
5 days |
Thu 01/12/17 |
Wed 01/18/17 |
4 |
Business analyst, Technical writers |
$5,200.00 |
2.4 |
Identification of the resources that would be required for the project |
4 days |
Thu 01/19/17 |
Tue 01/24/17 |
5 |
Business analyst |
$2,560.00 |
2.5 |
Estimation of budgetary requirements |
4 days |
Wed 01/25/17 |
Mon 01/30/17 |
6 |
Business analyst, Technical writers |
$4,160.00 |
2.6 |
Estimation of time requirements |
4 days |
Tue 01/31/17 |
Fri 02/03/17 |
7 |
Technical writers |
$1,600.00 |
2.7 |
End of project startup phase |
0 days |
Fri 02/03/17 |
Fri 02/03/17 |
8 |
$0.00 |
|
3 |
Phase 2: Solution Requirements Analysis |
36 days |
Mon 02/06/17 |
Mon 03/27/17 |
$41,240.00 |
||
3.1 |
Communication with the representatives of the client to gather information regarding the specific requirements of the client |
7 days |
Mon 02/06/17 |
Tue 02/14/17 |
9 |
Project Manager, System designer, System developer |
$16,240.00 |
3.2 |
Developing use case models of the system |
7 days |
Wed 02/15/17 |
Thu 02/23/17 |
11 |
System designer |
$3,920.00 |
3.3 |
Review of the use case models by the representatives of the client |
10 days |
Fri 02/24/17 |
Thu 03/09/17 |
12 |
Project Manager |
$12,000.00 |
3.4 |
Developing the test strategy to be utilized after the rostering system has been implemented |
7 days |
Fri 03/10/17 |
Mon 03/20/17 |
13 |
Testing manager |
$5,880.00 |
3.5 |
Updating the project plan |
5 days |
Tue 03/21/17 |
Mon 03/27/17 |
14 |
Business analyst |
$3,200.00 |
3.6 |
End of requirement analysis phase |
0 days |
Mon 03/27/17 |
Mon 03/27/17 |
15 |
$0.00 |
|
4 |
Phase 3: Solution Design |
47 days |
Tue 03/28/17 |
Wed 05/31/17 |
$35,000.00 |
||
4.1 |
Developing the architectural plan of the proposed system |
7 days |
Tue 03/28/17 |
Wed 04/05/17 |
16 |
Development manager, System designer |
$9,800.00 |
4.2 |
Architectural plan reviewed by the representatives of the client |
10 days |
Thu 04/06/17 |
Wed 04/19/17 |
18 |
Development manager |
$8,400.00 |
4.3 |
Developing detailed architectural plans |
15 days |
Thu 04/20/17 |
Wed 05/10/17 |
19 |
System designer |
$8,400.00 |
4.4 |
Developing the test plan in details |
15 days |
Thu 05/11/17 |
Wed 05/31/17 |
20 |
System Tester |
$8,400.00 |
4.5 |
End of solution design phase |
0 days |
Wed 05/31/17 |
Wed 05/31/17 |
21 |
Project Manager |
$0.00 |
5 |
Phase 4: Prototype |
38 days |
Thu 06/01/17 |
Mon 07/24/17 |
$64,320.00 |
||
5.1 |
Developing a prototype of the proposed solution |
20 days |
Thu 06/01/17 |
Wed 06/28/17 |
22 |
Development manager, Software components required for developing the ICT system, System designer, System developer, Hardware components required for developing the ICT system[1] |
$49,200.00 |
5.2 |
Making the prototype available to the clients |
15 days |
Thu 06/29/17 |
Wed 07/19/17 |
24 |
Development manager |
$12,600.00 |
5.3 |
Client accepts system design after reviewing the prototype |
3 days |
Thu 07/20/17 |
Mon 07/24/17 |
25 |
Development manager |
$2,520.00 |
5.4 |
End of prototype phase |
0 days |
Mon 07/24/17 |
Mon 07/24/17 |
26 |
Project Manager |
$0.00 |
6 |
Phase 5: Iteration 1 |
35 days |
Tue 07/25/17 |
Mon 09/11/17 |
$50,600.00 |
||
6.1 |
Including all functionalities in the prototype accepted by the client |
30 days |
Tue 07/25/17 |
Mon 09/04/17 |
27 |
System designer, System developer, Hardware components required for developing the ICT system[1],Software components required for developing the ICT system |
$43,600.00 |
6.2 |
Designing the test cases that would be utilized for verifying the operational activities of the ICT system |
5 days |
Tue 09/05/17 |
Mon 09/11/17 |
29 |
System Tester, Testing manager, Software components required for developing the ICT system |
$7,000.00 |
6.3 |
End of iteration 1 |
0 days |
Mon 09/11/17 |
Mon 09/11/17 |
30 |
Project Manager |
$0.00 |
7 |
Phase 6: Iteration 2 |
18 days |
Tue 09/12/17 |
Thu 10/05/17 |
$23,520.00 |
||
7.1 |
Conducting tests on the ICT system based in adherence to the test cases defined in the last phase |
15 days |
Tue 09/12/17 |
Mon 10/02/17 |
31 |
System Tester, Testing manager, Software components required for developing the ICT system |
$21,000.00 |
7.2 |
Publishing the results of the test cases |
3 days |
Tue 10/03/17 |
Thu 10/05/17 |
33 |
Testing manager |
$2,520.00 |
7.3 |
End of Iteration 2 |
0 days |
Thu 10/05/17 |
Thu 10/05/17 |
34 |
Project Manager |
$0.00 |
8 |
Phase 7:Iteration 3 |
18 days |
Fri 10/06/17 |
Tue 10/31/17 |
35 |
$26,520.00 |
|
8.1 |
Including changes in the application in accordance to results of the test cases |
10 days |
Fri 10/06/17 |
Thu 10/19/17 |
System designer, System developer, Hardware components required for developing the ICT system[1],Software components required for developing the ICT system |
$21,200.00 |
|
8.2 |
Conducting tests on the application |
5 days |
Fri 10/20/17 |
Thu 10/26/17 |
37 |
System Tester, Software components required for developing the ICT system |
$2,800.00 |
8.3 |
Publishing the results of the testing activities |
3 days |
Fri 10/27/17 |
Tue 10/31/17 |
38 |
Testing manager |
$2,520.00 |
8.4 |
End of Iteration 3 |
0 days |
Tue 10/31/17 |
Tue 10/31/17 |
39 |
Project Manager |
$0.00 |
9 |
Phase 8: Final Release |
10 days |
Wed 11/01/17 |
Tue 11/14/17 |
$13,960.00 |
||
9.1 |
Developing all necessary documents |
7 days |
Wed 11/01/17 |
Thu 11/09/17 |
40 |
Business analyst, Testing manager |
$10,360.00 |
9.2 |
Delivering the application and project documents to the client |
3 days |
Fri 11/10/17 |
Tue 11/14/17 |
42 |
Project Manager |
$3,600.00 |
9.3 |
End of final release phase |
0 days |
Tue 11/14/17 |
Tue 11/14/17 |
43 |
Project Manager |
$0.00 |
10 |
Phase 9: Project Completion |
33 days |
Wed 11/15/17 |
Fri 12/29/17 |
$15,600.00 |
||
10.1 |
Developing evaluation reports for all resources associated with the project |
15 days |
Wed 11/15/17 |
Tue 12/05/17 |
44 |
Technical writers |
$6,000.00 |
10.2 |
Developing review reports |
15 days |
Wed 12/06/17 |
Tue 12/26/17 |
46 |
Technical writers |
$6,000.00 |
10.3 |
Releasing resources |
3 days |
Wed 12/27/17 |
Fri 12/29/17 |
47 |
Project Manager |
$3,600.00 |
10.4 |
End of project completion phase |
0 days |
Fri 12/29/17 |
Fri 12/29/17 |
48 |
Project Manager |
$0.00 |
11 |
End of project |
0 days |
Fri 12/29/17 |
Fri 12/29/17 |
49 |
Project Manager |
$0.00 |
The milestone of this project is mainly listed in the below table:
Project Milestone |
Deliverable |
Expected Date |
Project Start-up |
Project charter and project management plan |
3rd February, 2017 |
Solution Requirements |
Different requirement specifications (use cases or similar) Test cases restructured Project Plan |
27th March, 2017 |
Solution Design |
Fully implemented architecture as well as detailed design Detailed test plan |
31st May, 2017 |
Prototype |
Various components of solution |
24th July, 2017 |
Iteration |
Extra functionalities Test Cases |
11th September, 2017 |
Iteration |
Test results |
5th October, 2017 |
Iteration |
Test results |
31st October, 2017 |
Final Release |
Solutions including all documentations and rough work |
14th November, 2017 |
Project Completion |
Individual evaluation reports |
29th December, 2017 |
Assumptions
The plans and estimates for this project are based on the following assumptions:
Risk Assessment
All the associated risk of the project are mainly discussed below along with the raking of risks:
Risk Rating
(Note that the risks need to update as the project proceeds.)
Id |
Possible Unwelcome Event |
Likelihood (L) 1, 2, 3 |
Severity (S) 1,2,3 |
Ranking L * S |
1. |
Start-up Phase: Improper budget estimation |
2 |
3 |
6 |
2. |
Analysis Phase: Exact requirements of this project are mainly not identified in proper manner. |
1 |
3 |
3 |
3. |
Design Phase: In-complete test plan |
1 |
2 |
2 |
4. |
Prototype Phase: Prototype may not get approved by clients |
2 |
3 |
6 |
5. |
Iteration Phase: different irregularities that may not get revealed by the testing phase |
3 |
3 |
9 |
1 is a low risk, 9 high risk.
Id |
Event |
Risk mitigation or contingency |
1 |
Start-up Phase |
All budget requirements need to get updated based on the project progression |
2 |
Analysis Phase |
Numbers of meetings occurred with the project representatives |
3 |
Design Phase |
All test plans are revised before doing the finalization |
4 |
Prototype Phase |
All types of changes are mainly included in prototype according to the instruction that mainly provided by customers |
5 |
Iteration Phase |
All final test activities are needed to be conducted to do the final review of the project |
Philosophy of the team
The prime objective of this project management team is to offer better quality system solutions to clients so that all specific requirements of project are met.
Ensuring quality
A set of verification activities
Annotated Bibliography
Article 1: “Project Management: The Managerial Process with MS Project”
The article has been written by Larson and Gray (2013) and kit has covered the impact of the management process for the development of project operations. The analysis of the project integration would form the smart analysis of the project analysis and its system development for the operational processing. The managerial process of the project management is employed for forming the use of MS Project software for implying the accurate and effective processing of the organization. The improvisation of the project planning with the help of project integration and development would be helpful for developing the smarter operations for the project analysis. The evaluation of the project plan in terms of the effective management strategies would comprise of developing the formation of the system integration.
Article 2: Project management: a systems approach to planning, scheduling, and controlling
The article was made by the Kerzner (2013) and it would form the involvement of the effective processing. The project management would be helpful for forming the development of the project scheduling and controlling. The role of the project for the scheduling and planning would help in development of the system integration for the management of the operations. The planning of the project is developed for critical evaluation of the improvised development method. The planning of the project is formed for the deployment of the improvised development method.
Article 3: A Guide to the Project Management Body of Knowledge: PMBOK (®) Guide
The project management is developed for the deployment of the improved processing and The managerial process of the project management is employed for forming the use of the accurate and effective processing of the organization. The improvisation of the project planning with the help of project integration and development would be helpful for developing the smarter operations for the project analysis. The evaluation of the project plan in terms of the effective management strategies would comprise of developing the formation of the system integration.
The project closure checklist includes,
Project charter and project management plan |
Checked |
Different requirement specifications (use cases or similar) Test cases restructured Project Plan |
þ |
Fully implemented architecture as well as detailed design Detailed test plan |
þ |
Various components of solution |
þ |
Extra functionalities Test Cases |
þ |
Test results |
þ |
Test results |
þ |
Solutions including all documentations and rough work |
þ |
Individual evaluation reports |
þ |
The evaluation plan consists of the following the following points,
References
Buch, V., PMP, D., & Sharma, A. K. (2014). Identification of Project Risks & Risk Breakdown Structure In Manufacture of Heavy Forgings. Journal of Engineering Research and Applications, 4(10), 26-30.
Chance, D. M., & Brooks, R. (2015). Introduction to derivatives and risk management. Cengage Learning.
Dwivedi, Y. K., Wastell, D., Laumer, S., Henriksen, H. Z., Myers, M. D., Bunker, D., … & Srivastava, S. C. (2015). Research on information systems failures and successes: Status update and future directions. Information Systems Frontiers, 17(1), 143-157.
Hopkin, P. (2017). Fundamentals of risk management: understanding, evaluating and implementing effective risk management. Kogan Page Publishers.
Lin, C. I., Kuo, F. Y., & Myers, M. D. (2015). Extending ICT4D studies: The value of critical research. Management Information Systems Quarterly, 39(3), 697-712.
Po?o?ski, M. (2015). Application of the work breakdown structure in determining cost buffers in construction schedules. Archives of Civil Engineering, 61(1), 147-161.
Pritchard, C. L., & PMP, P. R. (2014). Risk management: concepts and guidance. CRC Press.
Sandeep, M. S., & Ravishankar, M. N. (2014). The continuity of underperforming ICT projects in the public sector. Information & Management,
Sharon, A., & Dori, D. (2015). A Project–product model–based approach to planning work breakdown structures of complex system projects. IEEE Systems Journal, 9(2), 366-376.
Essay Writing Service Features
Our Experience
No matter how complex your assignment is, we can find the right professional for your specific task. Contact Essay is an essay writing company that hires only the smartest minds to help you with your projects. Our expertise allows us to provide students with high-quality academic writing, editing & proofreading services.Free Features
Free revision policy
$10Free bibliography & reference
$8Free title page
$8Free formatting
$8How Our Essay Writing Service Works
First, you will need to complete an order form. It's not difficult but, in case there is anything you find not to be clear, you may always call us so that we can guide you through it. On the order form, you will need to include some basic information concerning your order: subject, topic, number of pages, etc. We also encourage our clients to upload any relevant information or sources that will help.
Complete the order formOnce we have all the information and instructions that we need, we select the most suitable writer for your assignment. While everything seems to be clear, the writer, who has complete knowledge of the subject, may need clarification from you. It is at that point that you would receive a call or email from us.
Writer’s assignmentAs soon as the writer has finished, it will be delivered both to the website and to your email address so that you will not miss it. If your deadline is close at hand, we will place a call to you to make sure that you receive the paper on time.
Completing the order and download