Desired area of impact: The project area of impact is generally mentioned in various areas that include customer, financial, social, strategy as well as operational. It is identified that the project is mainly required in order to develop online booking system for RAILS, therefore the area as per the priority order include operational, customer, strategy, social as well as financial.
Project values: Depending on the point of view of RAILS as well as requirements of Globex, the project is mainly expected for bringing faster as well as better value within the organization. The organization wants to improve the system of ticketing by implementing the rostering system within the show. Furthermore, it is identified that the client generally needs faster as well as more efficient in ticket sales as well as management of crowd without delaying the tickets.
Appropriate metric: It is identified that the metric is mainly selected as:
Appropriate timeframe: The target metric must be gained within the time-period of six months after the entire project is completed properly. The metric of the stakeholder must be properly achieved by the project end so that the performance of the project can be accessed easily.
The project scope is to develop online ticket booking as well as sales procedure so that various types of issues as well as challenges like crowd management, delay in queues must be resolved. It is identified that online ticketing system must be operational for performing the ticketing procedure properly. The various requirements of the resources must be listed properly:
Type of resources |
Roles of resources |
Responsibilities |
People |
1. Project manager 2.Business analyst 3.Developer 4. Frontend developer 5.Lead analyst 6.Tester |
1. The stakeholders of the project mainly engages in managing the entire project, assist in team building as well as responsible of making proper decision. 2. They generally ensure that all the requirements of the project are documented properly. 3. Properly works in order to resolve issues as well as for suggesting various types of architectural changes. 4. They helps in ensuring that the deadlines of the Sla are met, databases are properly interfaced as well as UI are properly designed. 5. Estimates the entire testing procedure for planning the testing objectives 6. Escalating various types of issues as well as risks that assist in providing proper necessary updates |
Facilities |
CXA, Angular JS3, CSS3, Java 8 OCp |
The technologies are very much useful in developing the entire ticketing sale as well as booking system. |
Technologies |
Deployment as well as development department |
It assists in providing proper tools of development, infrastructure for implementing as well as for designing the online application |
Others |
Training of the team members |
It is identified that proper training is mainly needed for the employees of the organization. |
It is identified that the scheduling of the activity is mainly performed with the help of MS project software. In order to achieve appropriate allocation of time and activities, it is found that the scheduling table includes all the resources that are utilized for executing the project successfully. Furthermore, it is identified that the Work breakdown structure is prepared from the Gantt chart.
Task Name |
Duration |
Start |
Finish |
Development of RAILS Project |
185 days |
Tue 10/3/17 |
Mon 6/18/18 |
Project initiation phase |
35 days |
Tue 10/3/17 |
Mon 11/20/17 |
Preparation of project charter |
5 days |
Tue 10/3/17 |
Mon 10/9/17 |
Scope determination of project |
4 days |
Tue 10/10/17 |
Fri 10/13/17 |
Resource gathering |
3 days |
Mon 10/16/17 |
Wed 10/18/17 |
Requirement analysis |
4 days |
Thu 10/19/17 |
Tue 10/24/17 |
Creating schedule |
3 days |
Wed 10/25/17 |
Fri 10/27/17 |
Development of results |
4 days |
Mon 10/30/17 |
Thu 11/2/17 |
CPM application |
3 days |
Fri 11/3/17 |
Tue 11/7/17 |
cost management techniques applications |
4 days |
Wed 11/8/17 |
Mon 11/13/17 |
Analysis of project performance |
5 days |
Tue 11/14/17 |
Mon 11/20/17 |
Milestone: Completion of the initiation phase |
0 days |
Mon 11/20/17 |
Mon 11/20/17 |
Planning phase of the project |
47 days |
Tue 11/21/17 |
Wed 1/24/18 |
Cost management |
5 days |
Tue 11/21/17 |
Mon 11/27/17 |
Project plan for costing |
4 days |
Tue 11/28/17 |
Fri 12/1/17 |
Development of project plan |
4 days |
Mon 12/4/17 |
Thu 12/7/17 |
Time management plan |
6 days |
Fri 12/8/17 |
Fri 12/15/17 |
Change management plan |
5 days |
Mon 12/18/17 |
Fri 12/22/17 |
Estimation of budget |
4 days |
Mon 12/25/17 |
Thu 12/28/17 |
Cost benefit analysis |
3 days |
Fri 12/29/17 |
Tue 1/2/18 |
Risk management plan |
5 days |
Wed 1/3/18 |
Tue 1/9/18 |
Risk treatment plan |
4 days |
Wed 1/10/18 |
Mon 1/15/18 |
Procurement plan |
7 days |
Tue 1/16/18 |
Wed 1/24/18 |
Milestone: Completion of planning phase |
0 days |
Wed 1/24/18 |
Wed 1/24/18 |
Implementation phase |
78 days |
Thu 1/25/18 |
Mon 5/14/18 |
Activity development |
8 days |
Thu 1/25/18 |
Mon 2/5/18 |
Marketing |
7 days |
Tue 2/6/18 |
Wed 2/14/18 |
Administration |
9 days |
Thu 2/15/18 |
Tue 2/27/18 |
Testing |
8 days |
Wed 2/28/18 |
Fri 3/9/18 |
UX and UI design |
7 days |
Mon 3/12/18 |
Tue 3/20/18 |
Design of database |
6 days |
Wed 3/21/18 |
Wed 3/28/18 |
Design of functionality |
7 days |
Thu 3/29/18 |
Fri 4/6/18 |
System testing |
5 days |
Mon 4/9/18 |
Fri 4/13/18 |
Modification |
7 days |
Mon 4/16/18 |
Tue 4/24/18 |
Use case testing |
6 days |
Wed 4/25/18 |
Wed 5/2/18 |
Assessment of quality |
8 days |
Thu 5/3/18 |
Mon 5/14/18 |
Milestone: Completion of implementation phase |
0 days |
Mon 5/14/18 |
Mon 5/14/18 |
Maintenance phase |
20 days |
Tue 5/15/18 |
Mon 6/11/18 |
Maintenance of database |
5 days |
Tue 5/15/18 |
Mon 5/21/18 |
Maintenance of online application |
6 days |
Tue 5/22/18 |
Tue 5/29/18 |
Maintenance of operation |
5 days |
Wed 5/30/18 |
Tue 6/5/18 |
Learning and training sessions |
4 days |
Wed 6/6/18 |
Mon 6/11/18 |
Milestone: Completion of maintenance phase |
0 days |
Mon 6/11/18 |
Mon 6/11/18 |
Closure phase of the project |
5 days |
Tue 6/12/18 |
Mon 6/18/18 |
Sign-out of stakeholder |
1 day |
Tue 6/12/18 |
Tue 6/12/18 |
Post implementation review |
2 days |
Wed 6/13/18 |
Thu 6/14/18 |
Contract closure |
1 day |
Fri 6/15/18 |
Fri 6/15/18 |
Performance appraisal |
1 day |
Mon 6/18/18 |
Mon 6/18/18 |
Milestone: Completion of closure phase |
0 days |
Mon 6/18/18 |
Mon 6/18/18 |
Figure 1: Gantt chart
(Source: Created by Author)
Figure 2: Work Breakdown Structure
(Source: Created by Author)
It is identified that both planned risk management approaches as well as risk analysis is mainly followed in order to mitigate various types of risks that are associated with the project. The risks or challenges are generally based on different types of assumptions that include:
Risk management Plan: It is identified that the project faces number of issues as well as challenges, which must be mitigated appropriately by following proper risk mitigation plan. The different types of identified risks are as follows:
Budget Risk: It is found that the project may overrun the budget that is allocated. Thus, it is quite important for the managing authority of the project to consider appropriate contingency planning in order to adjust the project budget appropriately. The risk has catastrophic severity though its likelihood is high.
Timeline risk: It is identified that the project manager may face difficulty in completing the project within the time that is assumed. Thus, it is quite important for the project manager to consider additional slack in order to complete the project within time. The risk has medium severity, as its likelihood is medium. Therefore, it is quite significant to formulate proper mitigation plan in medium priority.
Training requirements: The employees as well as stakeholders of RAILS need proper training in order to handle the new system. Thus, it is found that extra expenses must be spent on this agenda. The risk has medium severity, though its likelihood is low.
Approval of MOV: The MOV may not be approved by the management of the organization, as it is generally dependent on the decision of the higher authority of the organization. Thus, it is quite challenging to meet various needs as well as requirements of time, resource terms as well as money. The project must be started properly by preparing new MOV document. The risk has almost certain severity, though its likelihood is low.
The statement of quality management is mainly prepared as to develop appropriate booking system for the committee of RAILS in order to provide proper shear quality in context to all the functions that are collected as well as analyzed prior to the initiation phase of the project.
Verification activities of the project are as follows:
Validation activities are mentioned below:
Closure checklist: The closure checklist must include proper activities that include stakeholder sign out, evaluation plan preparation, contract sign out, performance review as well as document preparation
Evaluation Plan: Evaluation plan must involve criteria that include meeting requirements, achieving appropriate level of deliverable, quality, meeting requirements and more.
The article mainly elaborates that the project management managerial procedure helps in offering proper controlling as well as resource utilization. The MS project can work properly with proper resources so that the entire project can be executed properly within the assumed time-period.
The article elaborates that project management is one of the systematic approach that helps in managing project effectively. It is identified that proper project management tools as well as techniques helps in controlling as managing the project effectively.
The article helps in reflecting various elements that generally assists in guiding the project successfully. It is identified that the elements are generally stated in an generalized manner so that the entire project can be successfully accomplished.
Besner, C., & Hobbs, B. (2012). An empirical identification of project management toolsets and a comparison among project types. Project Management Journal, 43(5), 24-46.
Besner, C., & Hobbs, B. (2013). Contextualized project management practice: A cluster analysis of practices and best practices. Project Management Journal, 44(1), 17-34.
Cook, D., Brown, D., Alexander, R., March, R., Morgan, P., Satterthwaite, G., & Pangalos, M. N. (2014). Lessons learned from the fate of AstraZeneca’s drug pipeline: a five-dimensional framework. Nature reviews. Drug discovery, 13(6), 419.
Crawford, J. K. (2014). Project management maturity model. CRC Press.
Marcelino-Sádaba, S., Pérez-Ezcurdia, A., Lazcano, A. M. E., & Villanueva, P. (2014). Project risk management methodology for small firms. International Journal of Project Management, 32(2), 327-340.
Martinelli, R. J., & Milosevic, D. Z. (2016). Project management toolbox: tools and techniques for the practicing project manager. John Wiley & Sons.
McLeod, L., Doolin, B., & MacDonell, S. G. (2012). A perspective?based understanding of project success. Project Management Journal, 43(5), 68-86.
Serra, C. E. M., & Kunc, M. (2015). Benefits realisation management and its influence on project success and on the execution of business strategies. International Journal of Project Management, 33(1), 53-66.
Essay Writing Service Features
Our Experience
No matter how complex your assignment is, we can find the right professional for your specific task. Contact Essay is an essay writing company that hires only the smartest minds to help you with your projects. Our expertise allows us to provide students with high-quality academic writing, editing & proofreading services.Free Features
Free revision policy
$10Free bibliography & reference
$8Free title page
$8Free formatting
$8How Our Essay Writing Service Works
First, you will need to complete an order form. It's not difficult but, in case there is anything you find not to be clear, you may always call us so that we can guide you through it. On the order form, you will need to include some basic information concerning your order: subject, topic, number of pages, etc. We also encourage our clients to upload any relevant information or sources that will help.
Complete the order formOnce we have all the information and instructions that we need, we select the most suitable writer for your assignment. While everything seems to be clear, the writer, who has complete knowledge of the subject, may need clarification from you. It is at that point that you would receive a call or email from us.
Writer’s assignmentAs soon as the writer has finished, it will be delivered both to the website and to your email address so that you will not miss it. If your deadline is close at hand, we will place a call to you to make sure that you receive the paper on time.
Completing the order and download