The different types of communication requirements, mediums and frequency are discussed in the table given below:
Stakeholder |
Communication requirement |
Medium of Communication |
Communication Frequency |
Project Manager |
Information regarding the progress of the project. |
Formal meetings and report presentations |
Once in each fortnight |
Contracts Admin |
Changes/variations in the contract |
Formal meetings, official mails |
As and when required |
Site Engineer |
1.Issues or problems encountered on the site 2. Progress made at site. |
Formal and informal meetings, mails |
-Do- |
Site Foreman |
1.Issues or problems encountered on the site 2. Progress made at site |
Formal and informal meetings, mails |
-Do- |
Accounts Clerk |
Budgetary requirements and/ or payments to be made to the contractor |
Formal and informal meetings, mails |
-Do- |
Community leader; |
Information regarding the progress of the project |
Formal meetings |
-Do- |
Council Member |
Information regarding the progress of the project. |
Formal meetings |
-Do- |
Superintendent |
1. Changes/ variations to be included 2. Payments to b made |
Formal meetings, official mails |
-Do- |
design engineer |
Design issues experienced at the project site |
Formal and informal meetings, mails |
-Do- |
local tennis club |
Information regarding the progress of the project |
Formal meetings. |
-Do- |
The following risks are associated with the project under consideration:
Project Risk |
Probability |
Impact |
Budget Risk |
medium |
High |
Risk related to project scope |
medium |
High |
Error in budget calculation |
medium |
medium |
Scheduling error |
medium |
medium |
Supply delay |
High |
High |
Risk regarding the quality of the raw materials |
Low |
High |
Work quality risk |
Low |
High |
Lack of proper skilled employees |
medium |
medium |
Proper permission from the government |
Low |
High |
Answer a:
The correspondence methodology for the powerful preparing of all advance installments on a month to month premise has been framework in the area underneath:
Step 1: The advance cases to be made for the venture must be submitted to the director : the composed reports much incorporate the points of interest of the WUC done and other due installments.
Step 2: Within 14 days of accepting the advance report, the administrator would issue the accompanying to the guideline and contractual worker: an advance declaration, an endorsement containing the confirmations of the evaluations made by the director himself in regards to the maintenance of cash and due sums.
Step 3: The Principal, inside 7 days of accepting the endorsements, would basically pay the sum said in the testament, in the wake of deducting the maintenance sum or potentially other set offs specified in the declaration.
The Building and Construction Industry Security of Payment Act 2002, which is otherwise called the SOP Act has been put into compel with the sole point of guaranteeing that all venture faculty related with the development business gets paid in a suitable way. Therefore one might say that the same enables the temporary workers to get their installment, as specified in the agreements, without the contribution of any legitimate board or counseling.
Answer b:
Proviso 8.1 of the AUD 4000 shows that any errors (seen by both of the gatherings) in the archives arranged for the development work, would need to be accounted for to the Superintendent in composing. The provision likewise expresses that if the temporary worker needs to acquire more constructional cost because of the inconsistencies in the first arranges and archives, the same would first be evaluated by the Superintend and afterward added to the agreement whole.
Extra claims for the blunders and ambiguities in the records were made in understanding to this specific condition.
Answer c:
Statement 8.1 of the AUD 4000 demonstrates that the Contractor is not permitted to incorporate any variety in the WUC aside from the same being asked for formally (in composing) by the customer. Be that as it may, the Superintendent has the privilege to guide certain varieties to the contractual worker before the date of handy finish o the venture, gave the varieties have a place with the accompanying sorts:
Since the customer has asked for the temporary worker upgrade the seats, the variety basically falls under those said in this specific condition. In this way, claims have been made in agreement to the same.
Answer d:
The distinguishing proof of the question of ancient times and the expulsion of the same was excluded in the WUC initially given to the contractual worker: consequently, this specific movement has been considered as a variety to the WUC and extra charges has been made by condition 8.1.
The Superintendent had managed the charges for extra time and work in understanding to proviso 25.2.
Answer e:
The utilization of stainless steel rushes rather than aroused iron jolts, in spite of the fact that suggested by the contractual worker himself, is basically variety or change in the nature of work to be directed. In this manner, as demonstrated in condition Clause 8.1 of the AS 4000, the Superintendent would need to give composed directions to temporary worker in regards to the same, after which the later may continue with the work.
BAC: |
estimated project cost |
= |
640 |
AUD (Thousands) |
PV at the end of 6th month: |
task’s budget at completion (BAC) — the total amount budgeted for the task |
= |
-200 |
AUD (Thousands) |
EV at the end of 6th month: |
Earned Value = % of completed work X BAC |
= |
1693.125 |
AUD (Thousands) |
AC at the end of 6th month: |
actual cost of the project |
= |
840 |
AUD (Thousands) |
SV at the end of 6th month: |
EV – PV |
= |
1893.125 |
AUD (Thousands) |
CV at the end of 6th month: |
Earned Value – Actual Cost |
= |
853.125 |
AUD (Thousands) |
SPI at the end of 6th month: |
EV/PV |
= |
-8.465625 |
|
CVI at the end of 6th month: |
EV/AC |
= |
2.015625 |
EAC of project, if CPI is expected to be the same for the remainder of the project : |
EAC = BAC/CPI |
= |
317.51938 |
AUD (Thousands) |
EAC of project, future work will be accomplished at the planned rate: |
EAC=AC |
= |
840 |
AUD (Thousands) |
EAC of project, If both the CPI and SPI influence the remaining work : |
EAC = AC + [(BAC-EV) /CPI*SPI] |
= |
790.772189 |
AUD (Thousands) |
After six months of the project start, the current progress of the project has been sketched out in the segment underneath.
In the early period of the venture, a few blunders and errors have been recognized in the venture arrange for, which had in the end prompted the re-advancement of plans even before the genuine development work could begin. While an expected extra measure of $10,000 would be charged for the same, endeavors are being coordinated towards finishing the venture inside the foreordained time.
The advance of the venture has been set back by a numerous as 14 days as a question of times long past has been revealed amid the removal time frame . The expulsion of this protest has acquired an extra cost of $100,000. Other than this, amid the third month of the venture, we were asked for t o change the materials to be utilized for building up the seating offices at the structure. As we had effectively requested the same from our seller, an extra cost of $100,000 has been acquired.
Inferable from the set back amid the unearthing time frame just 40 percent of the first work has been finished over the most recent 6 months. The accompanying table has been incorporated into the answer to highlight the consumption profile of the venture.
Table: Expenditure profile of the project, all values in thousand AUD
Work |
Month 1 |
Month 2 |
Month 3 |
Month 4 |
Month 5 |
Month 6 |
Month 7 |
Month 8 |
Month 9 |
Month 10 |
Month 11 |
Month 12 |
Planned |
50 |
100 |
120 |
120 |
120 |
130 |
130 |
130 |
120 |
120 |
100 |
50 |
Actual |
60 |
150 |
250 |
120 |
130 |
130 |
Estimation of VOWD: |
|||||||
Particulars |
Total Quantity |
% of Completion |
Qty. Applied |
Rate |
Amount (USD) |
Exchange Rate |
Amount (AUD) |
Delivery of Pipes: |
|||||||
Upto 3rd Month |
10000 |
30% |
3000 |
300 |
900000 |
0.75 |
1200000 |
In the 4th Month |
10000 |
10% |
1000 |
300 |
300000 |
0.75 |
400000 |
Total Delivery of Pipes |
10000 |
40% |
4000 |
1200000 |
1600000 |
||
Lay of Pipes |
4000 |
20% |
800 |
120 |
96000 |
||
Testing of Pipes |
800 |
50% |
400 |
30 |
12000 |
||
Estimated Value of Work Done at the end of 4th month |
1708000 |
||||||
Estimated Accruals: |
|||||||
Particulars |
% of Completion |
Qty. Applied |
Rate |
Amount (AUD) |
|||
Delivery of Pipes |
10% |
1000 |
400000 |
||||
Lay of Pipes: |
|||||||
Upto 4th Month |
20% |
800 |
|||||
Less: Upto 3rd Month |
15% |
600 |
|||||
Accrued Lay of Pipes |
5% |
200 |
120 |
24000 |
|||
Testing of Pipes: |
|||||||
Upto 4th Month |
50% |
400 |
|||||
Less: Upto 3rd Month |
0% |
0 |
|||||
Accrued Testing of Pipes |
50% |
400 |
30 |
12000 |
|||
Total Accruals at the end of 4th month |
436000 |
References:
Aadal, H., Rad, K., & Fard, A. (2013). Implementing 3R Concept in Construction Waste Management at Construction Site. Journal of Applied Environmental and Biological Sciences, 3(10), 160–166. Retrieved from https://www.researchgate.net/publication/264232510_Implementing_3R_Concept_in_Construction_Waste_Management_at_Construction_Site
AlSehaimi, A., Koskela, L., & Tzortzopoulos, P. (2013). Need for alternative research approaches in construction management: Case of delay studies. Journal of Management in …, 29(4), 407–413. https://doi.org/10.1061/(ASCE)ME.1943-5479.0000148.
And??jar-Montoya, M. D., Gilart-Iglesias, V., Montoyo, A., & Marcos-Jorquera, D. (2015). A construction management framework for mass customisation in traditional construction. Sustainability (Switzerland), 7(5), 5182–5210. https://doi.org/10.3390/su7055182
Arif, M., Bendi, D., Toma-Sabbagh, T., & Sutrisna, M. (2012). Construction waste management in India: an exploratory study. Construction Innovation: Information, Process, Management, 12(2), 133–155. https://doi.org/10.1108/14714171211215912
Cheng, E. W. L., Ryan, N., & Kelly, S. (2012). Exploring the perceived influence of safety management practices on project performance in the construction industry. Safety Science, 50(2), 363–369. https://doi.org/10.1016/j.ssci.2011.09.016
Cheong Yong, Y., & Emma Mustaffa, N. (2012). Analysis of factors critical to construction project success in Malaysia. Engineering, Construction and Architectural Management, 19(5), 543–556. https://doi.org/10.1108/09699981211259612
Chinowsky, P. (2012). Collaborative Working in Construction. Construction Management and Economics, (May 2013), 1–3. https://doi.org/10.1080/01446193.2012.667136
Colloquium on Humanities, Science and Engineering Research (pp. 325–330). https://doi.org/10.1109/CHUSER.2012.6504333
De Souza, D. V. S., & Koskela, L. (2012). On improvement in construction supply chain management. IGLC 2012 – 20th Conference of the International Group for Lean Construction, 44(0). Retrieved from https://www.scopus.com/inward/record.url?eid=2-s2.0-84874480256&partnerID=40&md5=1fc80f5abb5882706aa7d0475176a07a
Ding, L. Y., Zhou, Y., Luo, H. B., & Wu, X. G. (2012). Using nD technology to develop an integrated construction management system for city rail transit construction. Automation in Construction, 21(1), 64–73. https://doi.org/10.1016/j.autcon.2011.05.013
Hällgren, M. (2012). The construction of research questions in project management. International Journal of Project Management, 30(7), 804–816. https://doi.org/10.1016/j.ijproman.2012.01.005
Rawai, N. M., Fathi, M. S., Abedi, M., & Rambat, S. (2013). Cloud computing for green construction management. In Proceedings of the 2013 3rd International Conference on Intelligent System Design and Engineering Applications, ISDEA 2013 (pp. 432–435). https://doi.org/10.1109/ISDEA.2012.107
Udawatta, N., Zuo, J., Chiveralls, K., & Zillante, G. (2015). Improving waste management in construction projects: An Australian study. Resources, Conservation and Recycling, 101, 73–83. https://doi.org/10.1016/j.resconrec.2015.05.003
Wibowo, M. A., & Waluyo, R. (2015). Knowledge management maturity in construction companies. In Procedia Engineering (Vol. 125, pp. 89–94). https://doi.org/10.1016/j.proeng.2015.11.014
Xue, W., Wang, Y., & Man, Q. (2015). Research on information models for the construction schedule management based on the IFC standard. Journal of Industrial Engineering and Management, 8(3), 615–635. https://doi.org/10.3926/jiem.1283
Yang, R. J., & Shen, G. Q. P. (2015). Framework for Stakeholder Management in Construction Projects. Journal of Management in Engineering, 31(4), 1–14. https://doi.org/10.1061/(ASCE)ME.1943-5479.0000285.
Yu, Q. Z., Ding, L. Y., Zhou, C., & Luo, H. B. (2014). Analysis of factors influencing safety management for metro construction in China. Accident Analysis and Prevention, 68, 131–138. https://doi.org/10.1016/j.aap.2013.07.016
Zawdie, G. (2012). Construction Innovation through Change Management. In Construction Innovation and Process Improvement (pp. 19–44). https://doi.org/10.1002/9781118280294.ch2
Zhou, Y., Ding, L. Y., & Chen, L. J. (2013). Application of 4D visualization technology for safety management in metro construction. Automation in Construction, 34, 25–36. https://doi.org/10.1016/j.autcon.2012.10.011
Zhou, Z., Goh, Y. M., & Li, Q. (2015). Overview and analysis of safety management studies in the construction industry. Safety Science. https://doi.org/10.1016/j.ssci.2014.10.00
Essay Writing Service Features
Our Experience
No matter how complex your assignment is, we can find the right professional for your specific task. Contact Essay is an essay writing company that hires only the smartest minds to help you with your projects. Our expertise allows us to provide students with high-quality academic writing, editing & proofreading services.Free Features
Free revision policy
$10Free bibliography & reference
$8Free title page
$8Free formatting
$8How Our Essay Writing Service Works
First, you will need to complete an order form. It's not difficult but, in case there is anything you find not to be clear, you may always call us so that we can guide you through it. On the order form, you will need to include some basic information concerning your order: subject, topic, number of pages, etc. We also encourage our clients to upload any relevant information or sources that will help.
Complete the order formOnce we have all the information and instructions that we need, we select the most suitable writer for your assignment. While everything seems to be clear, the writer, who has complete knowledge of the subject, may need clarification from you. It is at that point that you would receive a call or email from us.
Writer’s assignmentAs soon as the writer has finished, it will be delivered both to the website and to your email address so that you will not miss it. If your deadline is close at hand, we will place a call to you to make sure that you receive the paper on time.
Completing the order and download