WBS |
Task Name |
0 |
Project Execution Plan for Building Community Centre |
1 |
Project Initiation of Execution |
1.1 |
Preparation of Project development plan |
1.2 |
Project charter presentation |
1.3 |
Project Agenda setting |
1.4 |
Finalization of project objectives |
1.5 |
Finalization of project resources |
1.6 |
Finalization of project contract signing |
2 |
Project Planning for Execution |
2.1 |
Project plan development |
2.2 |
Selection sites |
2.3 |
Preparation of contract signing |
2.4 |
Phased plan for construction |
2.5 |
Selection of contractors |
2.6 |
Construction plot booking |
2.7 |
Segmentation of areas for building centre |
3 |
Project Execution Processes |
3.1 |
Analysis of sites |
3.2 |
Storage selection |
3.3 |
design of hall |
3.4 |
Arrangements for hall |
3.5 |
Preparation in building piece of arts within hall |
3.6 |
Building of stage |
3.7 |
Garden building |
3.8 |
Construction of parking lot |
3.9 |
Building of site models |
3.10 |
Construction of Restrooms |
3.11 |
Construction of playground |
3.12 |
Construction of basket ball corner |
3.13 |
Arrangement for halls and flooding zones for guests |
4 |
Project closure |
4.1 |
Project charter sign off |
4.2 |
Final Presentation preparation |
4.3 |
Reviewing and testing of planned schedules |
4.4 |
Finalization of project phases |
4.5 |
End of project |
WBS |
Task Name |
Duration |
Start |
Finish |
Predecessors |
Resource Names |
0 |
Project Execution Plan for Building Community Centre |
430 days |
01-05-2017 |
21-12-2018 |
||
1 |
Porject Initiation of Execution |
102 days |
01-05-2017 |
19-09-2017 |
||
1.1 |
Preparation of Project development plan |
30 days |
01-05-2017 |
09-06-2017 |
Project Manager ,Project Planner |
|
1.2 |
Project charter presentation |
20 days |
12-06-2017 |
07-07-2017 |
2 |
Project Manager |
1.3 |
Project Agenda setting |
10 days |
10-07-2017 |
21-07-2017 |
3 |
Project Manager |
1.4 |
Finalization of project objectives |
15 days |
24-07-2017 |
11-08-2017 |
4,3 |
Project Manager ,Project Planner |
1.5 |
Finalization of project resoruces |
13 days |
14-08-2017 |
30-08-2017 |
5 |
Project Manager |
1.6 |
Finalization of project contract signing |
14 days |
31-08-2017 |
19-09-2017 |
6 |
Project Planner |
2 |
Project Planning for Execution |
101 days |
20-09-2017 |
07-02-2018 |
||
2.1 |
Project plan development |
20 days |
20-09-2017 |
17-10-2017 |
7 |
Project Manager ,Project Planner |
2.2 |
Selection sites |
13 days |
18-10-2017 |
03-11-2017 |
9 |
Construction head ,Designer |
2.3 |
Preparation of contract signning |
15 days |
06-11-2017 |
24-11-2017 |
10,9 |
Architect ,Designer |
2.4 |
Phased plan for construction |
12 days |
27-11-2017 |
12-12-2017 |
11 |
Project sponsor ,Site engineers |
2.5 |
Selection of contractors |
16 days |
13-12-2017 |
03-01-2018 |
12 |
Clients ,Construction head |
2.6 |
Construction plot booking |
20 days |
04-01-2018 |
31-01-2018 |
13,12 |
Construction head |
2.7 |
Segmentation of areas for building centre |
5 days |
01-02-2018 |
07-02-2018 |
14 |
Designer ,Project sponsor |
3 |
Project Execution Processes |
177 days |
01-02-2018 |
05-10-2018 |
||
3.1 |
Analysis of sites |
10 days |
01-02-2018 |
14-02-2018 |
14 |
Hardware head ,Project Manager |
3.2 |
Storage selection |
12 days |
15-02-2018 |
02-03-2018 |
17 |
Construction head ,Site engineers |
3.3 |
design of hall |
15 days |
05-03-2018 |
23-03-2018 |
18 |
Designer ,Hardware head |
3.4 |
Arrangements for hall |
14 days |
26-03-2018 |
12-04-2018 |
19 |
Construction head ,Site engineers |
3.5 |
Preparation in building piece of arts within hall |
18 days |
13-04-2018 |
08-05-2018 |
20 |
Construction head ,Designer |
3.6 |
Building of stage |
12 days |
09-05-2018 |
24-05-2018 |
21 |
Site engineers |
3.7 |
Garden building |
14 days |
25-05-2018 |
13-06-2018 |
22 |
Project Planner |
3.8 |
Construction of parking lot |
13 days |
14-06-2018 |
02-07-2018 |
23 |
Construction head |
3.9 |
Building of site models |
15 days |
03-07-2018 |
23-07-2018 |
24 |
Construction head ,Designer |
3.10 |
Construction of Restrooms |
14 days |
24-07-2018 |
10-08-2018 |
25 |
Architect ,Designer ,Workers |
3.11 |
Construction of playground |
12 days |
13-08-2018 |
28-08-2018 |
26,24 |
Construction head ,Site engineers |
3.12 |
Construction of basket ball corner |
16 days |
29-08-2018 |
19-09-2018 |
27,26 |
Construction head ,Site engineers |
3.13 |
Arrangment for halls and fooding zones for guests |
12 days |
20-09-2018 |
05-10-2018 |
28 |
Construction head ,Designer |
4 |
Project closure |
55 days |
08-10-2018 |
21-12-2018 |
||
4.1 |
Project charter sign off |
12 days |
08-10-2018 |
23-10-2018 |
29 |
Project Manager ,Project Planner |
4.2 |
Final Presentatiion preparation |
10 days |
24-10-2018 |
06-11-2018 |
31 |
Project Manager |
4.3 |
Revewing and testing of planned schedules |
11 days |
07-11-2018 |
21-11-2018 |
32,29 |
Project Manager |
4.4 |
Finalization of project phases |
10 days |
22-11-2018 |
05-12-2018 |
33 |
Project Planner |
4.5 |
End of project |
12 days |
06-12-2018 |
21-12-2018 |
34 |
Project Manager |
References
Svejvig, P., & Andersen, P. (2015). Rethinking project management: A structured literature review with a critical look at the brave new world. International Journal of Project Management, 33(2), 278-290.
Takey, S. M., & de Carvalho, M. M. (2015). Competency mapping in project management: An action research study in an engineering company. International Journal of Project Management, 33(4), 784-796.
Teller, J., & Kock, A. (2013). An empirical investigation on how portfolio risk management influences project portfolio success. International Journal of Project Management, 31(6), 817-829.
Todorovi?, M. L., Petrovi?, D. ?., Mihi?, M. M., Obradovi?, V. L., & Bushuyev, S. D. (2015). Project success analysis framework: A knowledge-based approach in project management. International Journal of Project Management, 33(4), 772-783.
Too, E. G., & Weaver, P. (2014). The management of project management: A conceptual framework for project governance. International Journal of Project Management, 32(8), 1382-1394.
Turner, R. (2016). Gower handbook of project management. Routledge.
Verzuh, E. (2015). The fast forward MBA in project management. John Wiley & Sons.
Walker, A. (2015). Project management in construction. John Wiley & Sons.
Williams, S., El-Rawas, O., Green, P., & Boehm, B. (2013). Learning project management decisions: A case study with case-based reasoning versus data farming.
Essay Writing Service Features
Our Experience
No matter how complex your assignment is, we can find the right professional for your specific task. Contact Essay is an essay writing company that hires only the smartest minds to help you with your projects. Our expertise allows us to provide students with high-quality academic writing, editing & proofreading services.Free Features
Free revision policy
$10Free bibliography & reference
$8Free title page
$8Free formatting
$8How Our Essay Writing Service Works
First, you will need to complete an order form. It's not difficult but, in case there is anything you find not to be clear, you may always call us so that we can guide you through it. On the order form, you will need to include some basic information concerning your order: subject, topic, number of pages, etc. We also encourage our clients to upload any relevant information or sources that will help.
Complete the order formOnce we have all the information and instructions that we need, we select the most suitable writer for your assignment. While everything seems to be clear, the writer, who has complete knowledge of the subject, may need clarification from you. It is at that point that you would receive a call or email from us.
Writer’s assignmentAs soon as the writer has finished, it will be delivered both to the website and to your email address so that you will not miss it. If your deadline is close at hand, we will place a call to you to make sure that you receive the paper on time.
Completing the order and download