Project Execution Planning and Management of Refurbishing Project by MICC Enterprise.
Execution time of a project is the considered as the baseline while developing the document as well as governing the document of project operation as well as management. The Project Execution Plan (PEP) helps to establish the proper terms that are to be included for meeting the scope of the project and fulfil all the contractual requirements of a project. This PEP report helps to describe particular plan of a project strategically that helps to address all the effective methods as well as maximize the efficiency while executing a project (Kermanshachi et al. 2016). The specific actions of a project helps to comply the goals of a project and achieve the objectives of a project, clear the work scope as well as fulfils all other critical responsibilities that are agreed in project contract. An execution plan also addresses the risk management plan of the project that includes the risks associated, all the mitigation plan that can be addressed and also evaluated the project proposal stage and the actions that are planned for a project execution.
This project consists of Project Execution Plan for a refurbishing project that is to be conducted by the MICC Enterprise. The details of the project is elaborated in the next section of the project as the overview of the project. This project also states the best delivery method that MICC enterprise can adopt for delivering the refurbishing project successfully. This project also states the best financial type of contract that can be implemented for completing the project successfully. The best procurement method is also suggested for the MICC Enterprise that addressed all the criteria of the project and accomplish the objective of the project. The risk that are associated with the project is also stated in this report along with the risk mitigation plan needed to be implemented in the project.
The project that is considered for this particular report is refurbishing project of removing the sandstones from the external surface of NIM main building. This project is actually being established to keep the safety concern in mind and refurbishing the main building of NIM to enhance the strength of the building. The contract that has been signed with MICC stated that the enterprise has eight months for completing the project from the date of signing. For making the project successful, the first decision that is to be made is dividing the external plot given into different working zones. The plot can be divided in to 14 working fronts having 2000 in each plot. The internal surface that was given to MICC was of 24,400 that can be further divided in to another 14 working fronts having 1743 in each plot. For removing the sandstones, the method that can be used by MICC is scaffolding it can be planned can 2000 scaffolding is enough for completing the project successfully.
Review meeting can be done after one month completion of the work with the administration of NIM. In the review meeting, the progress of the project can be discussed and work that is yet to be completed should also be discussed so that there is no lag at the end of completing the project. As interior work is independent from the exterior work of painting as well as scaffolding, both the works can be done simultaneously and progress should be noted. There should be proper planning process that is to be carried out for this project to finish the project in 8 months tenure (Lin et al. 2016). All through the planning process, there should be clear management so that they can complete the project on time. There should be proper project schedule and cost control included in the project. The project should have a project delivery method that will help MICC to complete the project without any delay. The next section of the report will state the best deliver method that can be implemented in the project for successful completion of project.
Project Charter
GENERAL PROJECT INFORMATION |
|
Project Name: |
Clearing sandstone and refurbishing the exterior wall and painting the wall. |
Project Sponsor: |
NIM Administration |
Organizational Unit: |
Construction Department |
Process Impacted: |
The construction process is impacted while carrying out this project. |
Expected Start Date: |
Expected start date of the project is 15th April, 2019 |
Expected Completion Date: |
Expected Completion date of the project is 15th, December 2019. |
Expected Savings: |
Expected savings of the project $100,000 |
Estimated Costs: |
The estimated cost of the project is $450,000 |
PROBLEM, ISSUE, GOALS, OBJECTIVES, DELIVERABLES |
|
Problem or Issue: |
The problem that might occur while carrying out not completing the project within the time schedule. |
Purpose of Project: |
The main propose of the project is to conduct a project of clearing the sandstones in the exterior of main building of NIM and refurbishing the wall of the main building and painting the walls. |
Business Case: |
Refurbishing project of NIM building by MICC Enterprise. |
Goals/Metrics: |
The main goal is to complete the project within the time schedule and cost scheduled for the project. |
PROJECT SCOPE & SCHEDULE |
|
Within Scope |
Scope of the project is refurbish the main building of NIM building. Painting the walls with in the time scheduled is within the scope of the project. |
Outside of Scope |
Any accident or risk that might occur in the project is outside the scope of the project. |
PROJECT RESOURCES & COSTS |
|
Project Team |
Construction team of MICC is included in the project. |
Support Resources |
The resources needed are paints, brushes, brooms, raw materials, and machines. |
PROJECT RISKS, CONSTRAINTS, ASSUMPTIONS |
|
Risks: |
The project might not be completed within the scheduled time and scheduled budget for the project. |
Project Schedule
Task Name |
Duration |
Start |
Finish |
Predecessors |
Refurbishing Project |
111 days |
Mon 15/04/19 |
Mon 16/09/19 |
|
Project Initiation |
27 days |
Mon 15/04/19 |
Tue 21/05/19 |
|
Meeting with stakeholders |
2 days |
Mon 15/04/19 |
Tue 16/04/19 |
|
Collecting Information |
5 days |
Wed 17/04/19 |
Tue 23/04/19 |
2 |
Visiting Site |
8 days |
Wed 24/04/19 |
Fri 3/05/19 |
3 |
Finalizing the Document |
12 days |
Mon 6/05/19 |
Tue 21/05/19 |
4 |
Project Sign In |
0 days |
Tue 21/05/19 |
Tue 21/05/19 |
5 |
Development Phase |
4 days |
Wed 22/05/19 |
Mon 27/05/19 |
|
Meeting with contractors |
2 days |
Wed 22/05/19 |
Thu 23/05/19 |
6 |
Allocating work to contractors |
2 days |
Fri 24/05/19 |
Mon 27/05/19 |
8 |
Implementing Phase |
100 days |
Fri 19/04/19 |
Thu 5/09/19 |
|
Erection of Scaffolding |
10 days |
Fri 19/04/19 |
Thu 2/05/19 |
2SS+4 days |
Removal of stone |
10 days |
Fri 3/05/19 |
Thu 16/05/19 |
11 |
Removal of Plaster |
8 days |
Fri 17/05/19 |
Tue 28/05/19 |
12 |
Plaster Meshing |
15 days |
Fri 31/05/19 |
Thu 20/06/19 |
13FS+2 days |
Coating with Plaster |
15 days |
Thu 27/06/19 |
Wed 17/07/19 |
14FS+4 days |
Removal of Scaffolding |
6 days |
Thu 18/07/19 |
Thu 25/07/19 |
15 |
Primer of paint |
15 days |
Fri 26/07/19 |
Thu 15/08/19 |
16 |
Final Paint Coating |
15 days |
Fri 16/08/19 |
Thu 5/09/19 |
17 |
Project Closure |
7 days |
Fri 6/09/19 |
Mon 16/09/19 |
|
Monitoring the site |
6 days |
Fri 6/09/19 |
Fri 13/09/19 |
18 |
Making the payment |
1 day |
Mon 16/09/19 |
Mon 16/09/19 |
20 |
Project Sign Off |
0 days |
Mon 16/09/19 |
Mon 16/09/19 |
21 |
Design-Bid-Build- The main and the only reason for hiring a contractor that includes design-bid-process is completing the project with lowest construction price. With DBB delivery, the traditional method for delivering a project is carried out along with having a difference between the construction process and design process. DBB project hires an architect first for creating the documents with design. An architect first develops the project cost and the project schedule, and after the design being completed Request for Bids is conducted. The contractors then evaluate the documents and gives the price for the work.
Construction Manager at Risk- This project delivery method is a different type of delivery method. In this particular project, the owner of the project appoints the construction manager who will be responsible for the project (Benedetto and Germanà 2016). The manager of the project is selected having quality, proven track records, or should have detailed approach of project and should meet the schedule of the project. The Construction manager mainly provides items that includes project budget, cost estimating on construction and the project schedule.
Design-Build delivery method- In this method, the owner hires a company of a particular team in a contract who will be responsible for completing the given project. The construction project is to be delivered by the team or the company with the given period of time. The team itself is responsible for designing as well as construction and the prices are kept to minimum.
Criteria |
Total Weight |
Project Delivery Method |
|||||
Dbb |
Db |
Construction Manager at Risk |
|||||
Score |
Weight |
Score |
Weight |
Score |
Weight |
||
Speed of project Delivery |
45 |
4 |
150 |
6 |
500 |
8 |
200 |
Communication |
20 |
4 |
150 |
3 |
450 |
8 |
150 |
Control on Cost |
20 |
7 |
100 |
5 |
200 |
8 |
100 |
Working with Subcontracts |
15 |
7 |
50 |
5 |
100 |
5 |
50 |
Total |
100 |
450 |
8 |
1250 |
500 |
Recommended delivery method: The delivery method that suits best the taken case study is the Design build delivery method as its score is 1250 in the chart above. Contract is given to MICC Enterprise for delivering the project. As this method provides ability in delivering project in a package, the administration of NIM gives the package project to MICC for conducting the project.
Lump Sum Project Contract Type: This project mainly deals with the activities related to construction and this financial contract regulates the agreement of the total price that was fixed.
This Lump sum contracts are mostly used in the situations that has clear scope as well as define the schedule of the project that is accepted as well as negotiated. This contract is used where the scpe of the project is well defined and all the tenders are sought out with significant changes that are included in the requirements. The contractor is able to get the exact price and the work that is asked for the project.
Cost Plus Contracts: The contract having cost plus includes the actual cost, purchase cost and all other expenses that are included in the construction work (Liang and O’brien 2016). In cost plus contract project types, some particular amount of money is to be kept before starting the negotiation. The amount includes cost of raw material, and the labour cost that includes operation cost and the profit of the contractor. The cost that is included is the direct cost and the indirect cost.
Guaranteed Maximum Price: This is a type of contract that include legal agreements of maximum price for which an organization will pay for certain type of project. The contractor for example in a homebuilder provides the actual cost that includes fixed fee and the maximum amount that is needed.
Criteria |
Total Weight |
Project Delivery Method |
|||||
Lump Sum Project Contract Type |
Cost Plus Contracts |
Guaranteed Maximum Price |
|||||
Score |
Weight |
Score |
Weight |
Score |
Weight |
||
Speed of project Delivery |
50 |
5 |
100 |
4 |
100 |
8 |
200 |
Communication |
20 |
5 |
250 |
3 |
250 |
8 |
250 |
Control on Cost |
20 |
6 |
200 |
5 |
100 |
8 |
200 |
Working with Subcontracts |
10 |
4 |
100 |
5 |
50 |
5 |
100 |
Total |
100 |
650 |
8 |
500 |
750 |
The maximum score for the contract type is guaranteed maximum price that is 750. In this project, the owner need to provide the minimum costs that are included in the project.
Competitive procurement method: The competitive method of procurement mainly involves opening of all the processes in bid and include the tender for obtaining bets value (Gerçek et al. 2017). The competitive procurement mainly involves the buyer to receive the bids from the sellers as well as vendors and then evaluate the bids before to choose a particular supplier. In this competitive method, the company that provide goods or services can bid or can give proposal for the project. This creates high competition in the market.
Negotiated procurement method: The negotiated procurement is basically a method that is used for selecting a contractor without having formal advertising and having formal competition for the price (Nicholas and Steyn 2017). All rules and regulations that are involved in employing the method of negotiation mainly specifies the contractor selection which is the best advantage that is provided by the government.
Best Value procurement method: In this method of procurement, all the other factors excluding the price are taken into account. The factors that are taken are quality and the expertise for selecting the contractor or the vendor for doing the project.
In this method the procured value of goods or the services are compared as cost and as project benefit. All the vendors are researched in this type of procurement method.
Criteria |
Total Weight |
Project Delivery Method |
|||||
Competitive procurement |
Negotiated procurement |
Best Value procurement |
|||||
Score |
Weight |
Score |
Weight |
Score |
Weight |
||
Speed of project Delivery |
50 |
5 |
200 |
4 |
100 |
8 |
200 |
Control on Cost |
25 |
6 |
200 |
5 |
100 |
8 |
200 |
Working with Subcontracts |
25 |
4 |
150 |
5 |
50 |
5 |
200 |
Total |
100 |
550 |
8 |
250 |
600 |
Recommendation: The procurement method that is recommended for this project is best value procurement method. This procurement method selects the best vendor among all the vendors and selects one among themselves.
Risk Register
Risk Name |
Risk Probability |
Impact on the Project |
Consequences |
Risk Response |
Labour Shortage |
Medium |
Low impact of the project |
Work process may get slow |
Some other labour might be included |
Availability of raw materials |
High |
High impact on the project |
Work might not start |
Materials should be bought at high cost |
Issues with sub-contractors |
Low |
Medium impact on the project |
Work will not stop but might slow down |
Settle the issue |
Natural Disasters |
Medium |
High impact on the project |
Work process will totally stop |
Nothing can be done. |
Risk mitigation plan:
There are many risk mitigation plan that are to be involved in a project.
Conclusion
From the report elaborated above, it can be concluded that project planning and management is an important part in carrying out a project. There are many key participants that are included in a project and the key participants work under project manager. The PEP for a project is to be approved by management of the company before starting the project or applying to it. This is considered as a live document and is to be updated along with all the present as well as future project that includes plans for carrying out a project and procedures included.
The PEP (Project Execution Plan) is considered as an important document that are usually used by different parties such as the evaluator of the client, estimator, the project planner or the project manager. The document including the PEP mainly covers many detailed data of all the activities that are to be performed for executing a project.
This project has detailed the PEP of the refurbishing project that includes clearing the sandstone in the exterior of the NIM main building as well as painting and refurbishing the exterior wall of the building for safety cause. Detailed project delivery method is explained in this project stating the project successful completion. The project needs a financial contract for completing the project and the contract type of the project has also been explained in this report stating the best financial contract that the project needs. Procurement method is stated as the non-competitive method that contains all the procuring entity including the goods and the services from a single provider. The procurement method used in this project is discussed elaborately in this project. All these method and management strategies should be used by MICC Enterprise to complete the refurbishing project successfully.
Abdi, A., Taghipour, S. and Khamooshi, H., 2018. Corrigendum to “A model to control environmental performance of project execution process based on greenhouse gas emissions using earned value management”[Int. J. Proj. Manag. 36 (3)(April 2018) 397-413]. International Journal of Project Management, 36(8), pp.1047-1049.
Ahmed, A., 2016. Software project management: A process-driven approach. Auerbach Publications.
Ameri, A. and Awad, T.Z., 2016. The Roles of the Project Management Office In The Execution of the Organizations Strategic Plan.
Andersen, E.S., 2016. Do project managers have different perspectives on project management?. International Journal of Project Management, 34(1), pp.58-65.
Bahi, M., El-Anwar, O. and Marzouk, M., 2016. Identifying the Optimal Execution Plan for Slum Infrastructure Upgrading Projects. In Construction Research Congress 2016 (pp. 2070-2078).
Brooks, B.D. and Lindner, H., 2018, September. Post-Construction ILI Execution Planning Guidelines for Pipeline Quality Verification. In 2018 12th International Pipeline Conference . American Society of Mechanical Engineers.
Cavka, H.B., Staub-French, S. and Poirier, E.A., 2017. Developing owner information requirements for BIM-enabled project delivery and asset management. Automation in construction, 83, pp.169-183.
Di Benedetto, G. and Germanà, M.L., 2016. Architecture of Culotta & Leone for the Historic Centre of Cefalù: plan, project, execution. TECHNE-Journal of Technology for Architecture and Environment, (12), pp.152-159.
Gerçek, B., Tokdemir, O.B., ?lal, M.E. and Günayd?n, H.M., 2017. BIM execution process of construction companies for building projects.
Kermanshachi, S., Dao, B., Shane, J. and Anderson, S., 2016. An empirical study into identifying project complexity management strategies. Procedia Engineering, 145, pp.603-610.
Liang, X. and O’brien, W.J., 2016. Analysis of the Criticality and Frequency of Alignment Elements in Project Execution Plans. In Construction Research Congress 2016 (pp. 140-149).
Lin, Y.C., Chen, Y.P., Huang, W.T. and Hong, C.C., 2016. Developing the Framework of BIM Execution Plan for Facility Management. Journal of Buildings, 6(1).
Lutchman, C., 2016. Project Execution: A Practical Approach to Industrial and Commercial Project Management. CRC Press.
McArthur, J.J. and Sun, X., 2015. Best practices for BIM Execution Plan development for a Public–Private Partnership Design-Build-Finance-Operate-Maintain Project. WIT Transactions on the Built Environment, 149, pp.119-130.
Nicholas, J.M. and Steyn, H., 2017. Project management for engineering, business and technology. Routledge.
Ward, G., 2016. The Project Manager’s Guide to Purchasing: Contracting for Goods and Services. Routledge.
Essay Writing Service Features
Our Experience
No matter how complex your assignment is, we can find the right professional for your specific task. Contact Essay is an essay writing company that hires only the smartest minds to help you with your projects. Our expertise allows us to provide students with high-quality academic writing, editing & proofreading services.Free Features
Free revision policy
$10Free bibliography & reference
$8Free title page
$8Free formatting
$8How Our Essay Writing Service Works
First, you will need to complete an order form. It's not difficult but, in case there is anything you find not to be clear, you may always call us so that we can guide you through it. On the order form, you will need to include some basic information concerning your order: subject, topic, number of pages, etc. We also encourage our clients to upload any relevant information or sources that will help.
Complete the order formOnce we have all the information and instructions that we need, we select the most suitable writer for your assignment. While everything seems to be clear, the writer, who has complete knowledge of the subject, may need clarification from you. It is at that point that you would receive a call or email from us.
Writer’s assignmentAs soon as the writer has finished, it will be delivered both to the website and to your email address so that you will not miss it. If your deadline is close at hand, we will place a call to you to make sure that you receive the paper on time.
Completing the order and download