The following assignment has been made for the development of the improved analysis and project management for the utilization of the effective management of the work and aligning the functional management of activities. The following report would involve the completeness of the work and cohesive management of activities.
Task Name |
Predecessors |
Duration |
Start |
Successors |
Finish |
Identify mission and Objectives, Create Project Charter |
7 days |
Mon 10/8/18 |
4, 5 |
Tue 10/16/18 |
|
Create Business Plan and Issue |
3 |
5 days |
Wed 10/17/18 |
7 |
Tue 10/23/18 |
Create Project Initiation Document and Issue |
3 |
12 days |
Wed 10/24/18 |
Fri 11/9/18 |
|
Soil Investigation |
4 |
3 days |
Wed 10/24/18 |
8, 9 |
Fri 10/26/18 |
Architectural |
7 |
60 days |
Mon 10/29/18 |
Fri 2/1/19 |
|
Structural |
7 |
15 days |
Mon 10/29/18 |
10 |
Fri 11/16/18 |
Mechanical |
9 |
10 days |
Mon 11/19/18 |
11 |
Fri 11/30/18 |
Electrical |
10 |
15 days |
Mon 12/3/18 |
14, 17 |
Fri 12/21/18 |
Survey |
11 |
5 days |
Mon 12/24/18 |
15 |
Fri 12/28/18 |
Excavation |
14 |
10 days |
Mon 12/31/18 |
Fri 1/11/19 |
|
Grading |
11 |
5 days |
Mon 12/24/18 |
18, 19 |
Fri 12/28/18 |
Water Control |
17 |
29 days |
Mon 12/31/18 |
20 |
Thu 2/7/19 |
Erosion control |
17 |
29 days |
Mon 12/31/18 |
20 |
Thu 2/7/19 |
Underground utilities |
18, 19 |
10 days |
Fri 2/8/19 |
23 |
Thu 2/21/19 |
Piles (Precast) |
20 |
14 days |
Fri 2/22/19 |
25, 26, 49 |
Wed 3/13/19 |
Columns (Basement – Floor 2) |
23 |
28 days |
Thu 3/14/19 |
32 |
Tue 4/30/19 |
Columns (Floor 3 – 4) |
23 |
10 days |
Thu 3/14/19 |
28 |
Wed 3/27/19 |
Columns (Floor 5 – 6) |
28 |
20 days |
Thu 4/11/19 |
30 |
Tue 5/14/19 |
Columns (Floor 7 – 9) |
26 |
10 days |
Thu 3/28/19 |
27 |
Wed 4/10/19 |
Slab -Beams (Basement – Floor 2) |
27 |
12 days |
Wed 5/15/19 |
31 |
Thu 5/30/19 |
Slab-Beams (Floor 3- 4) |
30 |
8 days |
Fri 5/31/19 |
32 |
Tue 6/11/19 |
Slab-Beams (Floor 5 – 6) |
25, 31 |
8 days |
Wed 6/12/19 |
33 |
Fri 6/21/19 |
Slab-Beams (Floor 7 – 9) |
32 |
8 days |
Mon 6/24/19 |
35 |
Wed 7/3/19 |
Roofing Trusses |
33 |
5 days |
Thu 7/4/19 |
36 |
Wed 7/10/19 |
Roofing Cover |
35 |
3 days |
Wed 8/28/19 |
72, 73, 74 |
Fri 8/30/19 |
Columns (Basement – Floor 2) |
21 |
5 days |
Mon 9/2/19 |
40 |
Fri 9/6/19 |
Columns Floor( 3 – 4) |
39 |
5 days |
Mon 9/9/19 |
41, 44, 45 |
Fri 9/13/19 |
Columns Floor( 5 – 6) |
40 |
5 days |
Mon 9/16/19 |
42 |
Fri 9/20/19 |
Columns Floor( 7 – 9) |
41 |
5 days |
Mon 9/23/19 |
46 |
Fri 9/27/19 |
Slab-Beams (Basement – Floor 2) |
40 |
4 days |
Mon 9/16/19 |
Thu 9/19/19 |
|
Slab-Beams Floor( 3 – 4) |
40 |
4 days |
Mon 9/16/19 |
Thu 9/19/19 |
|
Slab-Beams Floor( 5 – 6) |
42 |
4 days |
Mon 9/30/19 |
47 |
Thu 10/3/19 |
Slab-Beams Floor( 7 – 8) |
46 |
4 days |
Fri 10/4/19 |
Wed 10/9/19 |
|
Stairway (Basement – Floor 2) |
23 |
2 days |
Thu 3/14/19 |
50, 52, 56 |
Fri 3/15/19 |
Stairway Floor(3 – 4) |
49 |
2 days |
Mon 3/18/19 |
51 |
Tue 3/19/19 |
Stairway Floor( 5 -6) |
50 |
4 days |
Wed 3/20/19 |
Mon 3/25/19 |
|
Stairway Floor( 7 – 8) |
49 |
4 days |
Mon 3/18/19 |
53 |
Thu 3/21/19 |
Patios |
52 |
1 day |
Fri 3/22/19 |
Fri 3/22/19 |
|
Internal wall |
49 |
30 days |
Mon 3/18/19 |
57, 58 |
Fri 4/26/19 |
External wall |
56 |
45 days |
Mon 4/29/19 |
69 |
Fri 6/28/19 |
Screeding |
56 |
90 days |
Mon 4/29/19 |
60 |
Fri 8/30/19 |
Partitions |
57 |
55 days |
Mon 7/1/19 |
60 |
Fri 9/13/19 |
Dry wall |
58, 69 |
45 days |
Mon 9/16/19 |
62, 63, 65, 66 |
Fri 11/15/19 |
Interior doors |
60 |
20 days |
Mon 11/18/19 |
64 |
Fri 12/13/19 |
Windows |
60 |
30 days |
Mon 11/18/19 |
Fri 12/27/19 |
|
Security doors |
62 |
20 days |
Mon 12/16/19 |
67 |
Fri 1/10/20 |
Tiles |
60 |
90 days |
Mon 11/18/19 |
84 |
Fri 3/20/20 |
Glazing works |
60 |
40 days |
Mon 11/18/19 |
67 |
Fri 1/10/20 |
Decoration |
66, 64 |
30 days |
Mon 1/13/20 |
68 |
Fri 2/21/20 |
Carpeting |
67 |
50 days |
Mon 2/24/20 |
85 |
Fri 5/1/20 |
Plumbing systems (Main Line) |
36 |
15 days |
Mon 9/2/19 |
75 |
Fri 9/20/19 |
Plumbing systems (Floor. 1-2) |
36 |
10 days |
Mon 10/21/19 |
74 |
Fri 11/1/19 |
Plumbing systems (Floor. 3-4) |
36, 73 |
10 days |
Mon 11/4/19 |
81 |
Fri 11/15/19 |
Plumbing systems (Floor. 4-6) |
72 |
10 days |
Mon 9/23/19 |
76 |
Fri 10/4/19 |
Plumbing systems (Floor. 7-9) |
75 |
10 days |
Mon 10/7/19 |
78 |
Fri 10/18/19 |
Electrical Fixtures (Distribution) |
76 |
5 days |
Mon 10/21/19 |
79 |
Fri 10/25/19 |
Electrical Fixtures (Floor. 1-2) |
78 |
10 days |
Mon 10/28/19 |
80 |
Fri 11/8/19 |
Electrical Fixtures (Floor. 3-4) |
79 |
10 days |
Mon 11/11/19 |
81 |
Fri 11/22/19 |
Electrical Fixtures (Floor. 5-6) |
74, 80 |
10 days |
Mon 11/25/19 |
82 |
Fri 12/6/19 |
Electrical Fixtures (Floor. 7-9) |
81 |
10 days |
Mon 12/9/19 |
84 |
Fri 12/20/19 |
Systems Controls |
65, 82 |
10 days |
Mon 3/23/20 |
85 |
Fri 4/3/20 |
Fire alarms |
84, 68 |
10 days |
Mon 5/4/20 |
87, 91 |
Fri 5/15/20 |
Mechanical Fixtures (Elevators etc) |
85 |
15 days |
Mon 5/18/20 |
88 |
Fri 6/5/20 |
Mechanical Fixtures (Floor 1- 4) |
87 |
30 days |
Mon 6/8/20 |
89 |
Fri 7/17/20 |
Mechanical Fixtures (Floor 5- 9) |
88 |
30 days |
Mon 7/20/20 |
Fri 8/28/20 |
|
Access roads |
85 |
14 days |
Mon 5/18/20 |
92, 93 |
Thu 6/4/20 |
Signages |
91 |
5 days |
Fri 6/5/20 |
96 |
Thu 6/11/20 |
Parking lot |
91 |
14 days |
Fri 6/5/20 |
96 |
Wed 6/24/20 |
Testing 1 |
92, 93 |
2 days |
Thu 6/25/20 |
97, 98, 99, 100, 101, 102, 103, 104, 105 |
Fri 6/26/20 |
Testing 2 |
96 |
2 days |
Mon 6/29/20 |
107 |
Tue 6/30/20 |
Testing 3 |
96 |
2 days |
Wed 7/1/20 |
108 |
Thu 7/2/20 |
Testing 4 |
96 |
2 days |
Fri 7/3/20 |
109 |
Mon 7/6/20 |
Testing 5 |
96 |
2 days |
Tue 7/7/20 |
Wed 7/8/20 |
|
Testing 6 |
96 |
2 days |
Thu 7/9/20 |
Fri 7/10/20 |
|
Testing 7 |
96 |
2 days |
Mon 7/13/20 |
Tue 7/14/20 |
|
Testing 8 |
96 |
2 days |
Wed 7/15/20 |
Thu 7/16/20 |
|
Testing 9 |
96 |
2 days |
Fri 7/17/20 |
Mon 7/20/20 |
|
Testing 10 |
96 |
2 days |
Tue 7/21/20 |
Wed 7/22/20 |
|
Inspections 1 |
97 |
1 day |
Wed 7/1/20 |
110 |
Wed 7/1/20 |
Inspections 2 |
98 |
1 day |
Fri 7/3/20 |
111 |
Fri 7/3/20 |
Inspections 3 |
99 |
1 day |
Tue 7/7/20 |
112 |
Tue 7/7/20 |
Inspections 4 |
107 |
1 day |
Thu 7/2/20 |
113 |
Thu 7/2/20 |
Inspections 5 |
108 |
1 day |
Mon 7/6/20 |
114 |
Mon 7/6/20 |
Inspections 6 |
109 |
1 day |
Wed 7/8/20 |
115 |
Wed 7/8/20 |
Inspections 7 |
110 |
1 day |
Fri 7/3/20 |
116 |
Fri 7/3/20 |
Inspections 8 |
111 |
1 day |
Tue 7/7/20 |
116 |
Tue 7/7/20 |
Inspections 9 |
112 |
1 day |
Thu 7/9/20 |
116 |
Thu 7/9/20 |
Inspections 10 |
113, 114, 115 |
1 day |
Fri 7/10/20 |
Fri 7/10/20 |
The project had been considered for the constructing the flat complex and the utilization of the construction project management principles for the alignment of the effective and improved management process. The project has been divided into phases of planning, basement and floor works, concrete works, electrical works, quality assessment, and inspections. The construction works would be required for making sure that works can be integrated with the alignment of the successful and effective management of construction works. The duration of the projects include the following phases,
Planning: the activities included in this phase are identify mission and objectives, create project charter, create business plan and issue, and create project initiation document and issue.
Design: the design phase would include the activities of the soil investigation, architectural, structural, mechanical, and electrical.
Basement and Floors 1 – 9: The work required in basement and flooring include earthworks, survey, excavation, ground works, grading, water control, erosion control, underground utilities, structures, reinforcements, piles (precast), columns, columns (basement – floor 2), columns (floor 3 – 4), columns (floor 5 – 6), columns (floor 7 – 9), slab-beams, slab -beams (basement – floor 2), slab-beams (floor 3- 4), slab-beams (floor 5 – 6), slab-beams (floor 7 – 9), roofing, roofing trusses, roofing cover, concrete,
Columns: the columns of the flooring would be done by involving the following sub projects columns (basement – floor 2), columns floor (3 – 4), columns floor (5 – 6), columns floor (7 – 9).
Slab-Beams: the slam beams would include the slab-beams (basement – floor 2), slab-beams floor (3 – 4), slab-beams floor (5 – 6), slab-beams floor (7 – 8).
Stairway: Stairway construction would be sub sectioned into stairway (basement – floor 2), stairway floor (3 – 4), stairway floor (5 -6), and stairway floor (7 – 8).
Other works: some other construction works include patios, block wall-masonry, block wall, internal wall, external wall, screeding, interior –finishes, partitions, dry wall, insulation, interior doors, windows, security doors, tiles, glazing works, decoration, carpeting, mep systems
Plumbing: the plumbing works include plumbing systems (main line), plumbing systems (floor. 1-2), plumbing systems (floor. 3-4), plumbing systems (floor. 4-6), plumbing systems (floor. 7-9).
Electrical: the electrical works include electrical fixtures (distribution), electrical fixtures (floor. 1-2), electrical fixtures (floor. 3-4), electrical fixtures (floor. 5-6), electrical fixtures (floor. 7-9), sprinkler, systems controls, fire alarms, mechanical systems, mechanical fixtures (elevators etc), mechanical fixtures (floor 1- 4), mechanical fixtures (floor 5- 9).
Comments on Schedule: The project schedule has been developed using the adaptive framework and the implication of the works intrigued for the management of the operations. The project was schedule with 495 working days (summation of the duration of the critical activities). The work required for the completeness of the specific implication and management has been implied with the addition of the individual work packages. The summary tasks has been reduced to an optimum cost aligning the work developed for the consideration of the smart project completion. The total of the critical tasks duration were consider for the calculation of the work and implication of the work duration.
Task Name |
Planned Value – PV (BCWS) |
Earned Value – EV (BCWP) |
AC (ACWP) |
SV |
CV |
EAC |
BAC |
VAC |
Identify mission and Objectives, Create Project Charter |
$0.00 |
$0.00 |
$0.00 |
$0.00 |
$0.00 |
$0.00 |
$0.00 |
$0.00 |
Create Business Plan and Issue |
$0.00 |
$0.00 |
$0.00 |
$0.00 |
$0.00 |
$0.00 |
$0.00 |
$0.00 |
Create Project Initiation Document and Issue |
$0.00 |
$0.00 |
$0.00 |
$0.00 |
$0.00 |
$0.00 |
$0.00 |
$0.00 |
Soil Investigation |
$0.00 |
$0.00 |
$0.00 |
$0.00 |
$0.00 |
$17,496.00 |
$0.00 |
($17,496.00) |
Architectural |
$0.00 |
$0.00 |
$0.00 |
$0.00 |
$0.00 |
$25,416.00 |
$0.00 |
($25,416.00) |
Structural |
$0.00 |
$0.00 |
$0.00 |
$0.00 |
$0.00 |
$23,640.00 |
$0.00 |
($23,640.00) |
Mechanical |
$0.00 |
$0.00 |
$0.00 |
$0.00 |
$0.00 |
$18,072.00 |
$0.00 |
($18,072.00) |
Electrical |
$0.00 |
$0.00 |
$0.00 |
$0.00 |
$0.00 |
$23,640.00 |
$0.00 |
($23,640.00) |
Survey |
$0.00 |
$0.00 |
$0.00 |
$0.00 |
$0.00 |
$15,000.00 |
$0.00 |
($15,000.00) |
Excavation |
$0.00 |
$0.00 |
$0.00 |
$0.00 |
$0.00 |
$21,200.00 |
$0.00 |
($21,200.00) |
Grading |
$0.00 |
$0.00 |
$0.00 |
$0.00 |
$0.00 |
$24,360.00 |
$0.00 |
($24,360.00) |
Water Control |
$0.00 |
$0.00 |
$0.00 |
$0.00 |
$0.00 |
$4,200.00 |
$0.00 |
($4,200.00) |
Erosion control |
$0.00 |
$0.00 |
$0.00 |
$0.00 |
$0.00 |
$6,000.00 |
$0.00 |
($6,000.00) |
Underground utilities |
$0.00 |
$0.00 |
$0.00 |
$0.00 |
$0.00 |
$28,000.00 |
$0.00 |
($28,000.00) |
Piles (Precast) |
$0.00 |
$0.00 |
$0.00 |
$0.00 |
$0.00 |
$3,651,832.00 |
$0.00 |
($3,651,832.00) |
Columns (Basement – Floor 2) |
$0.00 |
$0.00 |
$0.00 |
$0.00 |
$0.00 |
$212,192.00 |
$0.00 |
($212,192.00) |
Columns (Floor 3 – 4) |
$0.00 |
$0.00 |
$0.00 |
$0.00 |
$0.00 |
$158,200.00 |
$0.00 |
($158,200.00) |
Columns (Floor 5 – 6) |
$0.00 |
$0.00 |
$0.00 |
$0.00 |
$0.00 |
$111,760.00 |
$0.00 |
($111,760.00) |
Columns (Floor 7 – 9) |
$0.00 |
$0.00 |
$0.00 |
$0.00 |
$0.00 |
$88,540.00 |
$0.00 |
($88,540.00) |
Slab -Beams (Basement – Floor 2) |
$0.00 |
$0.00 |
$0.00 |
$0.00 |
$0.00 |
$143,496.00 |
$0.00 |
($143,496.00) |
Slab-Beams (Floor 3- 4) |
$0.00 |
$0.00 |
$0.00 |
$0.00 |
$0.00 |
$105,734.00 |
$0.00 |
($105,734.00) |
Slab-Beams (Floor 5 – 6) |
$0.00 |
$0.00 |
$0.00 |
$0.00 |
$0.00 |
$75,524.00 |
$0.00 |
($75,524.00) |
Slab-Beams (Floor 7 – 9) |
$0.00 |
$0.00 |
$0.00 |
$0.00 |
$0.00 |
$60,419.00 |
$0.00 |
($60,419.00) |
Roofing Trusses |
$0.00 |
$0.00 |
$0.00 |
$0.00 |
$0.00 |
$32,000.00 |
$0.00 |
($32,000.00) |
Roofing Cover |
$0.00 |
$0.00 |
$0.00 |
$0.00 |
$0.00 |
$5,312.00 |
$0.00 |
($5,312.00) |
Columns (Basement – Floor 2) |
$0.00 |
$0.00 |
$0.00 |
$0.00 |
$0.00 |
$25,565.00 |
$0.00 |
($25,565.00) |
Columns Floor( 3 – 4) |
$0.00 |
$0.00 |
$0.00 |
$0.00 |
$0.00 |
$13,060.00 |
$0.00 |
($13,060.00) |
Columns Floor( 5 – 6) |
$0.00 |
$0.00 |
$0.00 |
$0.00 |
$0.00 |
$13,060.00 |
$0.00 |
($13,060.00) |
Columns Floor( 7 – 9) |
$0.00 |
$0.00 |
$0.00 |
$0.00 |
$0.00 |
$14,860.00 |
$0.00 |
($14,860.00) |
Slab-Beams (Basement – Floor 2) |
$0.00 |
$0.00 |
$0.00 |
$0.00 |
$0.00 |
$18,704.00 |
$0.00 |
($18,704.00) |
Slab-Beams Floor( 3 – 4) |
$0.00 |
$0.00 |
$0.00 |
$0.00 |
$0.00 |
$29,466.50 |
$0.00 |
($29,466.50) |
Slab-Beams Floor( 5 – 6) |
$0.00 |
$0.00 |
$0.00 |
$0.00 |
$0.00 |
$13,681.50 |
$0.00 |
($13,681.50) |
Slab-Beams Floor( 7 – 8) |
$0.00 |
$0.00 |
$0.00 |
$0.00 |
$0.00 |
$24,341.50 |
$0.00 |
($24,341.50) |
Stairway (Basement – Floor 2) |
$0.00 |
$0.00 |
$0.00 |
$0.00 |
$0.00 |
$11,991.50 |
$0.00 |
($11,991.50) |
Stairway Floor(3 – 4) |
$0.00 |
$0.00 |
$0.00 |
$0.00 |
$0.00 |
$5,021.50 |
$0.00 |
($5,021.50) |
Stairway Floor( 5 -6) |
$0.00 |
$0.00 |
$0.00 |
$0.00 |
$0.00 |
$11,991.50 |
$0.00 |
($11,991.50) |
Stairway Floor( 7 – 8) |
$0.00 |
$0.00 |
$0.00 |
$0.00 |
$0.00 |
$11,991.50 |
$0.00 |
($11,991.50) |
Patios |
$0.00 |
$0.00 |
$0.00 |
$0.00 |
$0.00 |
$3,101.00 |
$0.00 |
($3,101.00) |
Internal wall |
$0.00 |
$0.00 |
$0.00 |
$0.00 |
$0.00 |
$375,000.00 |
$0.00 |
($375,000.00) |
External wall |
$0.00 |
$0.00 |
$0.00 |
$0.00 |
$0.00 |
$425,000.00 |
$0.00 |
($425,000.00) |
Screeding |
$0.00 |
$0.00 |
$0.00 |
$0.00 |
$0.00 |
$287,280.00 |
$0.00 |
($287,280.00) |
Partitions |
$0.00 |
$0.00 |
$0.00 |
$0.00 |
$0.00 |
$77,223.00 |
$0.00 |
($77,223.00) |
Dry wall |
$0.00 |
$0.00 |
$0.00 |
$0.00 |
$0.00 |
$85,000.00 |
$0.00 |
($85,000.00) |
Interior doors |
$0.00 |
$0.00 |
$0.00 |
$0.00 |
$0.00 |
$12,460.00 |
$0.00 |
($12,460.00) |
Windows |
$0.00 |
$0.00 |
$0.00 |
$0.00 |
$0.00 |
$18,080.00 |
$0.00 |
($18,080.00) |
Security doors |
$0.00 |
$0.00 |
$0.00 |
$0.00 |
$0.00 |
$12,400.00 |
$0.00 |
($12,400.00) |
Tiles |
$0.00 |
$0.00 |
$0.00 |
$0.00 |
$0.00 |
$107,605.00 |
$0.00 |
($107,605.00) |
Glazing works |
$0.00 |
$0.00 |
$0.00 |
$0.00 |
$0.00 |
$32,720.00 |
$0.00 |
($32,720.00) |
Decoration |
$0.00 |
$0.00 |
$0.00 |
$0.00 |
$0.00 |
$280,000.00 |
$0.00 |
($280,000.00) |
Carpeting |
$0.00 |
$0.00 |
$0.00 |
$0.00 |
$0.00 |
$31,600.00 |
$0.00 |
($31,600.00) |
Plumbing systems (Main Line) |
$0.00 |
$0.00 |
$0.00 |
$0.00 |
$0.00 |
$9,760.00 |
$0.00 |
($9,760.00) |
Plumbing systems (Floor. 1-2) |
$0.00 |
$0.00 |
$0.00 |
$0.00 |
$0.00 |
$7,840.00 |
$0.00 |
($7,840.00) |
Plumbing systems (Floor. 3-4) |
$0.00 |
$0.00 |
$0.00 |
$0.00 |
$0.00 |
$7,840.00 |
$0.00 |
($7,840.00) |
Plumbing systems (Floor. 4-6) |
$0.00 |
$0.00 |
$0.00 |
$0.00 |
$0.00 |
$7,840.00 |
$0.00 |
($7,840.00) |
Plumbing systems (Floor. 7-9) |
$0.00 |
$0.00 |
$0.00 |
$0.00 |
$0.00 |
$7,840.00 |
$0.00 |
($7,840.00) |
Electrical Fixtures (Distribution) |
$0.00 |
$0.00 |
$0.00 |
$0.00 |
$0.00 |
$28,000.00 |
$0.00 |
($28,000.00) |
Electrical Fixtures (Floor. 1-2) |
$0.00 |
$0.00 |
$0.00 |
$0.00 |
$0.00 |
$18,840.00 |
$0.00 |
($18,840.00) |
Electrical Fixtures (Floor. 3-4) |
$0.00 |
$0.00 |
$0.00 |
$0.00 |
$0.00 |
$18,840.00 |
$0.00 |
($18,840.00) |
Electrical Fixtures (Floor. 5-6) |
$0.00 |
$0.00 |
$0.00 |
$0.00 |
$0.00 |
$18,840.00 |
$0.00 |
($18,840.00) |
Electrical Fixtures (Floor. 7-9) |
$0.00 |
$0.00 |
$0.00 |
$0.00 |
$0.00 |
$18,840.00 |
$0.00 |
($18,840.00) |
Systems Controls |
$0.00 |
$0.00 |
$0.00 |
$0.00 |
$0.00 |
$25,000.00 |
$0.00 |
($25,000.00) |
Fire alarms |
$0.00 |
$0.00 |
$0.00 |
$0.00 |
$0.00 |
$10,740.00 |
$0.00 |
($10,740.00) |
Mechanical Fixtures (Elevators etc) |
$0.00 |
$0.00 |
$0.00 |
$0.00 |
$0.00 |
$95,000.00 |
$0.00 |
($95,000.00) |
Mechanical Fixtures (Floor 1- 4) |
$0.00 |
$0.00 |
$0.00 |
$0.00 |
$0.00 |
$88,950.00 |
$0.00 |
($88,950.00) |
Mechanical Fixtures (Floor 5- 9) |
$0.00 |
$0.00 |
$0.00 |
$0.00 |
$0.00 |
$88,000.00 |
$0.00 |
($88,000.00) |
Access roads |
$0.00 |
$0.00 |
$0.00 |
$0.00 |
$0.00 |
$877,616.00 |
$0.00 |
($877,616.00) |
Signages |
$0.00 |
$0.00 |
$0.00 |
$0.00 |
$0.00 |
$2,000.00 |
$0.00 |
($2,000.00) |
Parking lot |
$0.00 |
$0.00 |
$0.00 |
$0.00 |
$0.00 |
$827,616.00 |
$0.00 |
($827,616.00) |
Testing 1 |
$0.00 |
$0.00 |
$0.00 |
$0.00 |
$0.00 |
$5,592.00 |
$0.00 |
($5,592.00) |
Testing 2 |
$0.00 |
$0.00 |
$0.00 |
$0.00 |
$0.00 |
$5,592.00 |
$0.00 |
($5,592.00) |
Testing 3 |
$0.00 |
$0.00 |
$0.00 |
$0.00 |
$0.00 |
$5,592.00 |
$0.00 |
($5,592.00) |
Testing 4 |
$0.00 |
$0.00 |
$0.00 |
$0.00 |
$0.00 |
$5,592.00 |
$0.00 |
($5,592.00) |
Testing 5 |
$0.00 |
$0.00 |
$0.00 |
$0.00 |
$0.00 |
$5,592.00 |
$0.00 |
($5,592.00) |
Testing 6 |
$0.00 |
$0.00 |
$0.00 |
$0.00 |
$0.00 |
$5,592.00 |
$0.00 |
($5,592.00) |
Testing 7 |
$0.00 |
$0.00 |
$0.00 |
$0.00 |
$0.00 |
$5,592.00 |
$0.00 |
($5,592.00) |
Testing 8 |
$0.00 |
$0.00 |
$0.00 |
$0.00 |
$0.00 |
$5,592.00 |
$0.00 |
($5,592.00) |
Testing 9 |
$0.00 |
$0.00 |
$0.00 |
$0.00 |
$0.00 |
$5,592.00 |
$0.00 |
($5,592.00) |
Testing 10 |
$0.00 |
$0.00 |
$0.00 |
$0.00 |
$0.00 |
$5,592.00 |
$0.00 |
($5,592.00) |
Inspections 1 |
$0.00 |
$0.00 |
$0.00 |
$0.00 |
$0.00 |
$7,064.00 |
$0.00 |
($7,064.00) |
Inspections 2 |
$0.00 |
$0.00 |
$0.00 |
$0.00 |
$0.00 |
$7,064.00 |
$0.00 |
($7,064.00) |
Inspections 3 |
$0.00 |
$0.00 |
$0.00 |
$0.00 |
$0.00 |
$7,064.00 |
$0.00 |
($7,064.00) |
Inspections 4 |
$0.00 |
$0.00 |
$0.00 |
$0.00 |
$0.00 |
$7,064.00 |
$0.00 |
($7,064.00) |
Inspections 5 |
$0.00 |
$0.00 |
$0.00 |
$0.00 |
$0.00 |
$7,064.00 |
$0.00 |
($7,064.00) |
Inspections 6 |
$0.00 |
$0.00 |
$0.00 |
$0.00 |
$0.00 |
$7,064.00 |
$0.00 |
($7,064.00) |
Inspections 7 |
$0.00 |
$0.00 |
$0.00 |
$0.00 |
$0.00 |
$7,064.00 |
$0.00 |
($7,064.00) |
Inspections 8 |
$0.00 |
$0.00 |
$0.00 |
$0.00 |
$0.00 |
$7,064.00 |
$0.00 |
($7,064.00) |
Inspections 9 |
$0.00 |
$0.00 |
$0.00 |
$0.00 |
$0.00 |
$7,064.00 |
$0.00 |
($7,064.00) |
Inspections 10 |
$0.00 |
$0.00 |
$0.00 |
$0.00 |
$0.00 |
$7,064.00 |
$0.00 |
($7,064.00) |
Cash flow Report- in the above diagrams it is clear that the implication of the resource estimation using the management of the works and the implication of the smart management processing. The resource management has been implied with the consideration for the management of the smart and effective implication development. The most of the resource expenditure has been done in the month of February-March of 2019 and May-June of 2020. The implication would also be resulted for the management of the activities for taking care of the work related to the implication of the work and forming the management process. The development of the factors and implication of works and it would allow the calculation of the effective management process. The resource usage has shown the cost estimates and the probable management of the factors aligning the work development and formation of the specific implication. The management has been implied with the consideration of the resource management and processing. The alignment would be effectively managed with the work developed and aligned with the significant development.
The resources of the project has been non-uniformly distributed across the timeline and work scheduled. The bar graphs have been helpful for aligning with the formation of the works and utilization of the smart project alignment. The non-uniform deposition of the specific resources over the period of time. The requirement of the works has been diverse and it has resulted in forming the management of the specific work requirements for the users. The different level of requirements of the factors for aligning the management work development.
Resource management can be implied with the help of the resource distribution and the management of the works and implying the utilization of work for the implication. The confinement of the works with the completeness management of the resources would be effective. It is possible that the process of refining the resources and distributing the works would be implied successfully. The alignment and the work distribution has been managed with the confinement of the work developing the implication of the smart project resource management.
Task Mode |
WBS |
Task Name |
% Complete |
Duration |
Auto Scheduled |
0 |
Project Apex_first 25 |
24% |
495 days |
Auto Scheduled |
1 |
Preliminaries |
99% |
85 days |
Auto Scheduled |
1.1 |
Planning |
99% |
25 days |
Auto Scheduled |
1.1.1 |
Identify mission and Objectives, Create Project Charter |
100% |
7 days |
Auto Scheduled |
1.1.2 |
Create Business Plan and Issue |
100% |
5 days |
Auto Scheduled |
1.1.3 |
Create Project Initiation Document and Issue |
99% |
12 days |
Auto Scheduled |
1.2 |
Design |
100% |
73 days |
Auto Scheduled |
1.1 |
Soil Investigation |
100% |
3 days |
Auto Scheduled |
1.2 |
Architectural |
100% |
60 days |
Auto Scheduled |
1.2.3 |
Structural |
100% |
15 days |
Auto Scheduled |
1.2.4 |
Mechanical |
100% |
10 days |
Auto Scheduled |
1.2.5 |
Electrical |
100% |
15 days |
Auto Scheduled |
2 |
Basement and Floors 1 – 9 |
16% |
440 days |
Auto Scheduled |
2.1 |
Earthworks |
100% |
44 days |
Auto Scheduled |
2.1.1 |
Survey |
100% |
5 days |
Auto Scheduled |
2.1.2 |
Excavation |
100% |
10 days |
Auto Scheduled |
2.1.3 |
Groundworks |
100% |
44 days |
Auto Scheduled |
2.1.3.1 |
Grading |
100% |
5 days |
Auto Scheduled |
2.1.3.2 |
Water Control |
100% |
29 days |
Auto Scheduled |
2.1.3.3 |
Erosion control |
100% |
29 days |
Auto Scheduled |
2.1.3.4 |
Underground utilities |
100% |
10 days |
Auto Scheduled |
2.2 |
Structures |
37% |
136 days |
Auto Scheduled |
2.2.1 |
Reinforcements |
37% |
136 days |
Auto Scheduled |
2.2.1.1 |
Piles (Precast) |
100% |
14 days |
Auto Scheduled |
2.2.1.2 |
Columns |
47% |
44 days |
Auto Scheduled |
2.2.1.2.1 |
Columns (Basement – Floor 2) |
50% |
28 days |
Auto Scheduled |
2.2.1.2.2 |
Columns (Floor 3 – 4) |
100% |
10 days |
Auto Scheduled |
2.2.1.2.3 |
Columns (Floor 5 – 6) |
0% |
20 days |
Auto Scheduled |
2.2.1.2.4 |
Columns (Floor 7 – 9) |
80% |
10 days |
Auto Scheduled |
2.3.3 |
Stairway |
100% |
8 days |
Auto Scheduled |
2.3.3.1 |
Stairway (Basement – Floor 2) |
100% |
2 days |
Auto Scheduled |
2.3.3.2 |
Stairway Floor(3 – 4) |
100% |
2 days |
Auto Scheduled |
2.3.3.3 |
Stairway Floor( 5 -6) |
100% |
4 days |
Auto Scheduled |
2.3.3.4 |
Stairway Floor( 7 – 8) |
100% |
4 days |
Auto Scheduled |
2.3.4 |
Patios |
100% |
1 day |
Task Mode |
WBS |
Task Name |
% Complete |
Auto Scheduled |
0 |
Project Apex_last 25 |
74% |
Auto Scheduled |
1 |
Preliminaries |
99% |
Auto Scheduled |
1.1 |
Planning |
99% |
Auto Scheduled |
1.1.1 |
Identify mission and Objectives, Create Project Charter |
100% |
Auto Scheduled |
1.1.2 |
Create Business Plan and Issue |
100% |
Auto Scheduled |
1.1.3 |
Create Project Initiation Document and Issue |
99% |
Auto Scheduled |
1.2 |
Design |
100% |
Auto Scheduled |
1.1 |
Soil Investigation |
100% |
Auto Scheduled |
1.2 |
Architectural |
100% |
Auto Scheduled |
1.2.3 |
Structural |
100% |
Auto Scheduled |
1.2.4 |
Mechanical |
100% |
Auto Scheduled |
1.2.5 |
Electrical |
100% |
Auto Scheduled |
2 |
Basement and Floors 1 – 9 |
75% |
Auto Scheduled |
2.1 |
Earthworks |
100% |
Auto Scheduled |
2.1.1 |
Survey |
100% |
Auto Scheduled |
2.1.2 |
Excavation |
100% |
Auto Scheduled |
2.1.3 |
Groundworks |
100% |
Auto Scheduled |
2.1.3.1 |
Grading |
100% |
Auto Scheduled |
2.1.3.2 |
Water Control |
100% |
Auto Scheduled |
2.1.3.3 |
Erosion control |
100% |
Auto Scheduled |
2.1.3.4 |
Underground utilities |
100% |
Auto Scheduled |
2.2 |
Structures |
100% |
Auto Scheduled |
2.2.1 |
Reinforcements |
100% |
Auto Scheduled |
2.2.1.1 |
Piles (Precast) |
100% |
Auto Scheduled |
2.2.1.2 |
Columns |
100% |
Auto Scheduled |
2.2.1.2.1 |
Columns (Basement – Floor 2) |
100% |
Auto Scheduled |
2.2.1.2.2 |
Columns (Floor 3 – 4) |
100% |
Auto Scheduled |
2.2.1.2.3 |
Columns (Floor 5 – 6) |
100% |
Auto Scheduled |
2.2.1.2.4 |
Columns (Floor 7 – 9) |
100% |
Auto Scheduled |
2.2.1.3 |
Slab-Beams |
100% |
Auto Scheduled |
2.2.1.3.1 |
Slab -Beams (Basement – Floor 2) |
100% |
Auto Scheduled |
2.2.1.3.2 |
Slab-Beams (Floor 3- 4) |
100% |
Auto Scheduled |
2.2.1.3.3 |
Slab-Beams (Floor 5 – 6) |
100% |
Auto Scheduled |
2.2.1.3.4 |
Slab-Beams (Floor 7 – 9) |
100% |
Auto Scheduled |
2.2.1.4 |
Roofing |
100% |
Auto Scheduled |
2.2.1.4.1 |
Roofing Trusses |
100% |
Auto Scheduled |
2.2.1.4.2 |
Roofing Cover |
100% |
Auto Scheduled |
2.3 |
Concrete |
100% |
Auto Scheduled |
2.3.1 |
Columns |
100% |
Auto Scheduled |
2.3.1.1 |
Columns (Basement – Floor 2) |
100% |
Auto Scheduled |
2.3.1.2 |
Columns Floor( 3 – 4) |
100% |
Auto Scheduled |
2.3.1.3 |
Columns Floor( 5 – 6) |
100% |
Auto Scheduled |
2.3.1.4 |
Columns Floor( 7 – 9) |
100% |
Auto Scheduled |
2.3.2 |
Slab-Beams |
100% |
Auto Scheduled |
2.3.2.1 |
Slab-Beams (Basement – Floor 2) |
100% |
Auto Scheduled |
2.3.2.2 |
Slab-Beams Floor( 3 – 4) |
100% |
Auto Scheduled |
2.3.2.3 |
Slab-Beams Floor( 5 – 6) |
100% |
Auto Scheduled |
2.3.2.4 |
Slab-Beams Floor( 7 – 8) |
100% |
Auto Scheduled |
2.3.3 |
Stairway |
100% |
Auto Scheduled |
2.3.3.1 |
Stairway (Basement – Floor 2) |
100% |
Auto Scheduled |
2.3.3.2 |
Stairway Floor(3 – 4) |
100% |
Auto Scheduled |
2.3.3.3 |
Stairway Floor( 5 -6) |
100% |
Auto Scheduled |
2.3.3.4 |
Stairway Floor( 7 – 8) |
100% |
Auto Scheduled |
2.3.4 |
Patios |
100% |
Auto Scheduled |
2.3.4 |
Blockwall-Masonry |
100% |
Auto Scheduled |
2.4.1 |
Bockwall |
100% |
Auto Scheduled |
2.4.1.1 |
Internal wall |
100% |
Auto Scheduled |
2.4.1.2 |
External wall |
100% |
Auto Scheduled |
2.4.1.3 |
Screeding |
100% |
Auto Scheduled |
2.5 |
Interior -Finishes |
59% |
Auto Scheduled |
2.5..5 |
Partitions |
100% |
Auto Scheduled |
2.5.1 |
Dry wall |
100% |
Auto Scheduled |
2.5.2 |
Insulation |
55% |
Auto Scheduled |
2.5.2.1 |
Interior doors |
100% |
Auto Scheduled |
2.5.2.2 |
Windows |
100% |
Auto Scheduled |
2.5.2.3 |
Security doors |
60% |
Auto Scheduled |
2.5.2.4 |
Tiles |
36% |
Auto Scheduled |
2.5.2.5 |
Glazing works |
80% |
Auto Scheduled |
2.5.2.6 |
Decoration |
0% |
Auto Scheduled |
2.5.4 |
Carpeting |
0% |
Auto Scheduled |
2.6 |
MEP systems |
100% |
Auto Scheduled |
2.6.1 |
Plumbing |
100% |
Auto Scheduled |
2.6.1.1 |
Plumbing systems (Main Line) |
100% |
Auto Scheduled |
2.6.1.2 |
Plumbing systems (Floor. 1-2) |
100% |
Auto Scheduled |
2.6.1.3 |
Plumbing systems (Floor. 3-4) |
100% |
Auto Scheduled |
2.6.1.4 |
Plumbing systems (Floor. 4-6) |
100% |
Auto Scheduled |
2.6.1.5 |
Plumbing systems (Floor. 7-9) |
100% |
Auto Scheduled |
2.6.2 |
Electrical |
100% |
Auto Scheduled |
2.6.2.1 |
Electrical Fixtures (Distribution) |
100% |
Auto Scheduled |
2.6.2.2 |
Electrical Fixtures (Floor. 1-2) |
100% |
Auto Scheduled |
2.6.2.3 |
Electrical Fixtures (Floor. 3-4) |
100% |
Auto Scheduled |
2.6.2.4 |
Electrical Fixtures (Floor. 5-6) |
100% |
Auto Scheduled |
2.6.2.5 |
Electrical Fixtures (Floor. 7-9) |
100% |
Conclusion
The assignment had include the construction works of making sure that the work gas been implied with the utilization of the successive management works. The alignment had been helpful for maintaining the works and it would be helpful for aligning the works and improving the management process.
References
Fleming, Q. W., & Koppelman, J. M. (2016, December). Earned value project management. Project Management Institute.
Harrison, F., & Lock, D. (2017). Advanced project management: a structured approach. Routledge.
Kerzner, H., & Kerzner, H. R. (2017). Project management: a systems approach to planning, scheduling, and controlling. John Wiley & Sons.
Larson, E. W., Gray, C. F., Danlin, U., Honig, B., & Bacarini, D. (2014). Project management: The managerial process (Vol. 6). Grandview Heights, OH: McGraw-Hill Education.
Marchewka, J. T. (2014). Information technology project management. John Wiley & Sons.
Nicholas, J. M., & Steyn, H. (2017). Project management for engineering, business and technology. Routledge.
Verzuh, E. (2015). The fast forward MBA in project management. John Wiley & Sons.
Walker, A. (2015). Project management in construction. John Wiley & Sons.
Essay Writing Service Features
Our Experience
No matter how complex your assignment is, we can find the right professional for your specific task. Contact Essay is an essay writing company that hires only the smartest minds to help you with your projects. Our expertise allows us to provide students with high-quality academic writing, editing & proofreading services.Free Features
Free revision policy
$10Free bibliography & reference
$8Free title page
$8Free formatting
$8How Our Essay Writing Service Works
First, you will need to complete an order form. It's not difficult but, in case there is anything you find not to be clear, you may always call us so that we can guide you through it. On the order form, you will need to include some basic information concerning your order: subject, topic, number of pages, etc. We also encourage our clients to upload any relevant information or sources that will help.
Complete the order formOnce we have all the information and instructions that we need, we select the most suitable writer for your assignment. While everything seems to be clear, the writer, who has complete knowledge of the subject, may need clarification from you. It is at that point that you would receive a call or email from us.